施工现场平面布置方案

目 录

一、工程概况 ............................................................ 2 1.1总体概况 ............................................................ 2 1.2土建设计概况 ........................................................ 2 1.3机电设计概况 ........................................................ 4 二、编制依据 ............................................................ 5 三、现场平面布置原则 .................................................... 5 3.1总则 ................................................................ 5 3.2施工平面布置原则 .................................................... 5 四、现场平面布置及做法 .................................................. 6 4.1场地平整 ............................................................ 6 4.3大门出入口 .......................................................... 6 4.4现场洗车设备 ........................................................ 7 4.5现场道路 ............................................................ 9 4.6现场厕所 ............................................................ 9 4.7化粪池 ............................................................. 11 4.7临时办公区硬化 ..................................................... 12 4.8临水、临电布置 ..................................................... 12 4.9钢筋加工区布置 ..................................................... 12 4.10木工加工棚 ........................................................ 13 4.11发电机防护棚 ...................................................... 15 4.12配电室 ............................................................ 17 4.13配电箱防护棚 ...................................................... 18 4.14工人生活区 ........................................................ 19 五、现场临时设施施工组织机构 ........................................... 21 六、进度计划 ........................................................... 22 七、安全注意事项: ..................................................... 22

一、工程概况

1.2.1建筑设计概况

1.2.2结构设计概况

二、编制依据

1.1北京景山学校大爱城分校施工组织设计文件 1.2北京景山学校大爱城分校施工图纸 1.3《施工手册》 (第五版)

1.4现场红线,建设单位给定的电源、水源位置,现场勘查结果。 1.5总体部署及主要施工方案 1.6当地安全文明施工标准要求。

1.7《施工现场临时用电安全技术规范》JGJ 46-2005 1.8《建筑施工安全检查技术标准》JGJ 59-2011 三、现场平面布置原则

3.1总则

平面布置图根据施工现场实际情况分两个阶段进行设计,对施工现场实行动态管理,包括基础和主体结构施工阶段总平面布置;装修施工阶段总平面布置。

3.2施工平面布置原则 3.2.1办公设施 1、办公用房由于需要多次移位,计划采用租赁临时集装箱式办公用房。 2、办公、生产区分开布置。 3.2.2现场布置

1、现场无法形成循环道路,道路宽度满足双车通过,设停车场供停车和回车用,路尽头设12m×12m回车场地。

2、临时用电引自甲方指定杆变或两台柴油发电机。 3、临水临电线路采用暗敷方式。

4、为满足消防要求,室外消火栓布置必须临近道路。 3.2.3机械布置

1、塔式起重机布置数量应满足施工吊次的要求;布置位置应使塔式起

重机大臂尽量覆盖全部施工作业面,同时便于塔式起重机的安装和拆除。

2、物料提升机布置数量应满足装修、机电安装要求;布置位置应尽量减少搬运距离,并考虑装修和机电安装的需要。

3、中小型机械布置于安全的环境中,避开高空物体打击的范围 3.2.4材料堆放

1、结构用料堆放区尽量设在塔吊覆盖范围内,减少二次搬运。 2、装修材料和安装材料堆放应靠近道路并便于二次搬运。 四、现场平面布置及做法

4.1场地平整

由于场地为耕地,土质松软,且地势较低,进场后应根据平面布置方案对现场进行场地平整,将加工场地、临时道路、办公区等部位的地面回填土、平整,回填土厚度约300mm,压实系数为0.95。整个场地需从结构边向路边或外围档放坡,坡度为1.5%,以便顺利排水避免场内积水。 4.3大门出入口

4.3.1在现场西北角处操场东侧设置一个带门楼出入口,门楼净宽度8.18米,净高6米,横梁高度0.8米,门柱采用50*50*5角铁焊接制作,尺寸为800mm*800mm,高度6.8米。

4.3.2门楼东侧设置工人门禁过道和彩钢房门卫室,门禁上方设置彩钢顶,宽度同门卫室宽度。

4.3.3大门为铁制四折平开门,总宽8米,大门为50*50*5角钢、2.5mm厚钢板制作,分四扇设置,每扇宽度2米,高度2.4米,开启方式为向内平开。门楼颜色应为蓝底白字,大门颜色为红底白字。详见下图:

工地现场主大门

50×50×5角铁

±0.00

立面图

大门立柱做法

1-1断面做法

1

4.4现场洗车设备

采用简易洗车设备,人工洗车,砖砌沉淀池,详见下图: 50×50×5角铁

4.4.1平面图:

上横柱立面做法

1

4.4.2剖面图

4.5现场道路

采用现浇混凝土路面,路面宽度4米,具体做法及布置详见《临时道路施工方案》。 4.6现场厕所

现场临时工人厕所布置在拟建工程的西南角,临时办公区厕所布置在办公区的西侧。采用砖砌240墙体,彩钢瓦坡屋顶,屋顶桁架采用钢管搭设,厕所高度2米。详见下图:

4.7化粪池

化粪池采用实心砖M5混合砂浆砌筑,厚度240mm,办公区化粪池尺寸为2.5米*2米,2米深,化粪池内侧10厚1:3

水泥砂浆抹面。化粪池盖板为50厚预制钢筋混凝土盖板,配筋6@150、单排双向。详见下图:

4.7临时办公区硬化

临时办公室采用租赁的集装箱办公用房,地面采用素土夯实+100mm厚C30混凝土硬化。硬化范围为办公区四周2米范围,靠近临时道路一侧应扩至临时道路边。具体位置详见现场硬化平面布置图。

4.8临水、临电布置

详见《临水施工方案》、《临电施工组织设计》。

4.9钢筋加工区布置

钢筋加工区布置在拟建建筑北侧,临时道路南侧,方便材料进场及成品钢筋的倒运。加工区地面采用100厚C30混凝土硬化。加工棚采用成品架子上铺设双层防雨防砸棚,防护棚采用脚手管搭设、上铺双层脚手板,加工棚尺寸5米*12米,净高3米,防护棚高度700mm。详见下图:

4.10木工加工棚

木工加工区布置在拟建建筑西北侧,临时道路南侧。加工棚采用开敞式,便于防火。加工棚有定型桁架和钢管柱组成,桁架除主梁外全部采用50*150mm方钢,桁架主梁采用150*150mm方钢,顶铺0.5厚压型钢板,上层檩条上设置20*20mm网孔钢板网,下层檩条上方铺设脚手板,下层檩条下挂0.5mm厚压型钢板或塑料扣板吊顶,檩条为40*40mm

方钢,立柱

为150*150mm方钢,立柱与桁架各焊接一片250*250*10mm耳板,以m12螺栓连接。详见下图:

4.11发电机防护棚

现场拟布置两台柴油发电机,布置在拟建建筑西南角,操场东侧。发电机基础采用150厚C20混凝土,四周地面采用80厚C20混凝土硬化,基础及地面应高出附近场地100mm,防护棚立柱处应浇筑200厚300*300mm基础,预埋地脚螺栓。防护棚立柱采用40*40*2.5mm方钢,栏杆采用30*30*2.5mm方钢,焊接连接。防护棚上铺设双层脚手板,间距500mm,并在下层脚手板下铺设双层塑料布防雨。防护棚尺寸为3.2米*6.5米,高

3.6米。详见下图:

基础图:

4.12配电室

一级配电柜放在专门的配电室内,配电间为实心砖和M5混合砂浆砌筑而成,屋顶采用彩钢板搭设。墙体厚度240,房间尺寸为4米*3米,高度为3.2米。配电间内外墙面采用1:3水泥砂浆抹面,地面为100厚C20混凝土地面。详见下图:

4.13配电箱防护棚

二级配电箱采用固定式布置,配电箱外侧架设防砸防雨功能防护棚。高度2.65米,尺寸为2米*2米,采用30*30*2.5方钢焊接而成,防护栏基础为300mm高240mm厚实心砖M5混合砂浆砌筑而成,外侧抹10厚1:3水泥砂浆抹面,防护棚内填满砂子。顶上满铺脚手板,脚手板下铺两层塑料布。详见下图:

4.14工人生活区

工人生活区采用在场外搭设,全部采用岩棉板芯彩钢房。

4.15办公区厕所

办公区厕所设置在办公区西侧,墙体采用标准砖砌筑,房顶采用彩钢顶,蹲坑、小便器及洗手池均采用成品卫生器具,隔断选用成品隔断,门采用成品木板门。厕所尺寸为4.48米×8.48米,高2.5米。装修做法为:

1)外墙采用实心标准砖,M5混合砂浆砌筑,

2)外墙面做法:

(1)12厚1:1:6水泥石灰砂浆打底;

(2)8厚1:1:6水泥石灰沙浆粉面拉毛。

3)内墙面做法:

(1)12厚1:3水泥砂浆打底;

(2)6厚1:0.1:2.5水泥石灰膏砂浆结合层;

(3)瓷砖,白水泥檫缝。

4)地面做法:

(1)混凝土基层;

(2)刷素水浆一道;

(3)10厚1:2干硬性水泥砂浆结合层;

(4)撒素水泥面(洒适量清水);

(5)瓷砖(地砖)地面,干水泥檫缝。

具体做法详见下图:

五、现场临时设施施工组织机构

六、进度计划

根据建设单位提供的进场时间及预定的开工时间,编制施工现场临时设施施工进度计划,具体的时间节点如下:

临水、临电起始时间:2016年9月5日——2016年9月15日, 现场临时道路完成时间:2016年9月5日——2016年9月15日, 现场临时场地硬化时间:2016年9月15日——2016年9月22日, 防护棚搭建时间:2016年9月10日——2016年9月30日, 办公区搭建时间:2016年9月10日——2016年9月25日。 七、安全注意事项:

7.1所有进入现场施工的工人均需佩戴安全帽,穿防滑平底鞋,现场禁止吸烟。

7.2工人进场施工前应接受安全教育,并经考核合格。

7.3工人开始作业前,工长应对作业内容进行交底,对存在的危险因素告知工人,使工人熟悉施工工艺、工序,掌握安全防范措施。 7.4所有用电设备及工具均由电工统一接线,不得私自节电。 7.5特种作业人员应具有上岗证,无证不得上岗。

7.6需要动火作业的,应及时申请动火证,并安排专人看火。 7.7作业现场不具备消防水时,应配足灭火器具。

目 录

一、工程概况 ............................................................ 2 1.1总体概况 ............................................................ 2 1.2土建设计概况 ........................................................ 2 1.3机电设计概况 ........................................................ 4 二、编制依据 ............................................................ 5 三、现场平面布置原则 .................................................... 5 3.1总则 ................................................................ 5 3.2施工平面布置原则 .................................................... 5 四、现场平面布置及做法 .................................................. 6 4.1场地平整 ............................................................ 6 4.3大门出入口 .......................................................... 6 4.4现场洗车设备 ........................................................ 7 4.5现场道路 ............................................................ 9 4.6现场厕所 ............................................................ 9 4.7化粪池 ............................................................. 11 4.7临时办公区硬化 ..................................................... 12 4.8临水、临电布置 ..................................................... 12 4.9钢筋加工区布置 ..................................................... 12 4.10木工加工棚 ........................................................ 13 4.11发电机防护棚 ...................................................... 15 4.12配电室 ............................................................ 17 4.13配电箱防护棚 ...................................................... 18 4.14工人生活区 ........................................................ 19 五、现场临时设施施工组织机构 ........................................... 21 六、进度计划 ........................................................... 22 七、安全注意事项: ..................................................... 22

一、工程概况

1.2.1建筑设计概况

1.2.2结构设计概况

二、编制依据

1.1北京景山学校大爱城分校施工组织设计文件 1.2北京景山学校大爱城分校施工图纸 1.3《施工手册》 (第五版)

1.4现场红线,建设单位给定的电源、水源位置,现场勘查结果。 1.5总体部署及主要施工方案 1.6当地安全文明施工标准要求。

1.7《施工现场临时用电安全技术规范》JGJ 46-2005 1.8《建筑施工安全检查技术标准》JGJ 59-2011 三、现场平面布置原则

3.1总则

平面布置图根据施工现场实际情况分两个阶段进行设计,对施工现场实行动态管理,包括基础和主体结构施工阶段总平面布置;装修施工阶段总平面布置。

3.2施工平面布置原则 3.2.1办公设施 1、办公用房由于需要多次移位,计划采用租赁临时集装箱式办公用房。 2、办公、生产区分开布置。 3.2.2现场布置

1、现场无法形成循环道路,道路宽度满足双车通过,设停车场供停车和回车用,路尽头设12m×12m回车场地。

2、临时用电引自甲方指定杆变或两台柴油发电机。 3、临水临电线路采用暗敷方式。

4、为满足消防要求,室外消火栓布置必须临近道路。 3.2.3机械布置

1、塔式起重机布置数量应满足施工吊次的要求;布置位置应使塔式起

重机大臂尽量覆盖全部施工作业面,同时便于塔式起重机的安装和拆除。

2、物料提升机布置数量应满足装修、机电安装要求;布置位置应尽量减少搬运距离,并考虑装修和机电安装的需要。

3、中小型机械布置于安全的环境中,避开高空物体打击的范围 3.2.4材料堆放

1、结构用料堆放区尽量设在塔吊覆盖范围内,减少二次搬运。 2、装修材料和安装材料堆放应靠近道路并便于二次搬运。 四、现场平面布置及做法

4.1场地平整

由于场地为耕地,土质松软,且地势较低,进场后应根据平面布置方案对现场进行场地平整,将加工场地、临时道路、办公区等部位的地面回填土、平整,回填土厚度约300mm,压实系数为0.95。整个场地需从结构边向路边或外围档放坡,坡度为1.5%,以便顺利排水避免场内积水。 4.3大门出入口

4.3.1在现场西北角处操场东侧设置一个带门楼出入口,门楼净宽度8.18米,净高6米,横梁高度0.8米,门柱采用50*50*5角铁焊接制作,尺寸为800mm*800mm,高度6.8米。

4.3.2门楼东侧设置工人门禁过道和彩钢房门卫室,门禁上方设置彩钢顶,宽度同门卫室宽度。

4.3.3大门为铁制四折平开门,总宽8米,大门为50*50*5角钢、2.5mm厚钢板制作,分四扇设置,每扇宽度2米,高度2.4米,开启方式为向内平开。门楼颜色应为蓝底白字,大门颜色为红底白字。详见下图:

工地现场主大门

50×50×5角铁

±0.00

立面图

大门立柱做法

1-1断面做法

1

4.4现场洗车设备

采用简易洗车设备,人工洗车,砖砌沉淀池,详见下图: 50×50×5角铁

4.4.1平面图:

上横柱立面做法

1

4.4.2剖面图

4.5现场道路

采用现浇混凝土路面,路面宽度4米,具体做法及布置详见《临时道路施工方案》。 4.6现场厕所

现场临时工人厕所布置在拟建工程的西南角,临时办公区厕所布置在办公区的西侧。采用砖砌240墙体,彩钢瓦坡屋顶,屋顶桁架采用钢管搭设,厕所高度2米。详见下图:

4.7化粪池

化粪池采用实心砖M5混合砂浆砌筑,厚度240mm,办公区化粪池尺寸为2.5米*2米,2米深,化粪池内侧10厚1:3

水泥砂浆抹面。化粪池盖板为50厚预制钢筋混凝土盖板,配筋6@150、单排双向。详见下图:

4.7临时办公区硬化

临时办公室采用租赁的集装箱办公用房,地面采用素土夯实+100mm厚C30混凝土硬化。硬化范围为办公区四周2米范围,靠近临时道路一侧应扩至临时道路边。具体位置详见现场硬化平面布置图。

4.8临水、临电布置

详见《临水施工方案》、《临电施工组织设计》。

4.9钢筋加工区布置

钢筋加工区布置在拟建建筑北侧,临时道路南侧,方便材料进场及成品钢筋的倒运。加工区地面采用100厚C30混凝土硬化。加工棚采用成品架子上铺设双层防雨防砸棚,防护棚采用脚手管搭设、上铺双层脚手板,加工棚尺寸5米*12米,净高3米,防护棚高度700mm。详见下图:

4.10木工加工棚

木工加工区布置在拟建建筑西北侧,临时道路南侧。加工棚采用开敞式,便于防火。加工棚有定型桁架和钢管柱组成,桁架除主梁外全部采用50*150mm方钢,桁架主梁采用150*150mm方钢,顶铺0.5厚压型钢板,上层檩条上设置20*20mm网孔钢板网,下层檩条上方铺设脚手板,下层檩条下挂0.5mm厚压型钢板或塑料扣板吊顶,檩条为40*40mm

方钢,立柱

为150*150mm方钢,立柱与桁架各焊接一片250*250*10mm耳板,以m12螺栓连接。详见下图:

4.11发电机防护棚

现场拟布置两台柴油发电机,布置在拟建建筑西南角,操场东侧。发电机基础采用150厚C20混凝土,四周地面采用80厚C20混凝土硬化,基础及地面应高出附近场地100mm,防护棚立柱处应浇筑200厚300*300mm基础,预埋地脚螺栓。防护棚立柱采用40*40*2.5mm方钢,栏杆采用30*30*2.5mm方钢,焊接连接。防护棚上铺设双层脚手板,间距500mm,并在下层脚手板下铺设双层塑料布防雨。防护棚尺寸为3.2米*6.5米,高

3.6米。详见下图:

基础图:

4.12配电室

一级配电柜放在专门的配电室内,配电间为实心砖和M5混合砂浆砌筑而成,屋顶采用彩钢板搭设。墙体厚度240,房间尺寸为4米*3米,高度为3.2米。配电间内外墙面采用1:3水泥砂浆抹面,地面为100厚C20混凝土地面。详见下图:

4.13配电箱防护棚

二级配电箱采用固定式布置,配电箱外侧架设防砸防雨功能防护棚。高度2.65米,尺寸为2米*2米,采用30*30*2.5方钢焊接而成,防护栏基础为300mm高240mm厚实心砖M5混合砂浆砌筑而成,外侧抹10厚1:3水泥砂浆抹面,防护棚内填满砂子。顶上满铺脚手板,脚手板下铺两层塑料布。详见下图:

4.14工人生活区

工人生活区采用在场外搭设,全部采用岩棉板芯彩钢房。

4.15办公区厕所

办公区厕所设置在办公区西侧,墙体采用标准砖砌筑,房顶采用彩钢顶,蹲坑、小便器及洗手池均采用成品卫生器具,隔断选用成品隔断,门采用成品木板门。厕所尺寸为4.48米×8.48米,高2.5米。装修做法为:

1)外墙采用实心标准砖,M5混合砂浆砌筑,

2)外墙面做法:

(1)12厚1:1:6水泥石灰砂浆打底;

(2)8厚1:1:6水泥石灰沙浆粉面拉毛。

3)内墙面做法:

(1)12厚1:3水泥砂浆打底;

(2)6厚1:0.1:2.5水泥石灰膏砂浆结合层;

(3)瓷砖,白水泥檫缝。

4)地面做法:

(1)混凝土基层;

(2)刷素水浆一道;

(3)10厚1:2干硬性水泥砂浆结合层;

(4)撒素水泥面(洒适量清水);

(5)瓷砖(地砖)地面,干水泥檫缝。

具体做法详见下图:

五、现场临时设施施工组织机构

六、进度计划

根据建设单位提供的进场时间及预定的开工时间,编制施工现场临时设施施工进度计划,具体的时间节点如下:

临水、临电起始时间:2016年9月5日——2016年9月15日, 现场临时道路完成时间:2016年9月5日——2016年9月15日, 现场临时场地硬化时间:2016年9月15日——2016年9月22日, 防护棚搭建时间:2016年9月10日——2016年9月30日, 办公区搭建时间:2016年9月10日——2016年9月25日。 七、安全注意事项:

7.1所有进入现场施工的工人均需佩戴安全帽,穿防滑平底鞋,现场禁止吸烟。

7.2工人进场施工前应接受安全教育,并经考核合格。

7.3工人开始作业前,工长应对作业内容进行交底,对存在的危险因素告知工人,使工人熟悉施工工艺、工序,掌握安全防范措施。 7.4所有用电设备及工具均由电工统一接线,不得私自节电。 7.5特种作业人员应具有上岗证,无证不得上岗。

7.6需要动火作业的,应及时申请动火证,并安排专人看火。 7.7作业现场不具备消防水时,应配足灭火器具。


相关文章

  • 施工现场平面布置及临时水电方案
  • 第六章 施工现场平面布置和临时设施.临时道路布置 6.1 周边环境分析 6.1.1 工程位置 本工程位于丹阳市市中心,位于新建丹阳市实验幼儿园以东,白云街以北,新建荣城国际小区以西. 6.1.1-1 工程平面图 6.1.2 周边情况 施工现 ...查看


  • 施工现场平面布置方案 1
  • 渔洋关大丽寨保障安居住房小区 16#.17#.18#楼工程 施工现场临时设施 规 划 方 案 编制: 审核: 批准: 北 龙 建 设 集 团 有 限 公 司 年 月 日 目 录 第一节 工程概况 第二节 编制依据 第三节 施工总平面布置 一 ...查看


  • 施工现场总平面图布置方案
  • 施工现场总平面图绘制方案 施工总平面图是拟建项目施工场地的总布置图.它按照施工方案和施工进度的要求,对施工现场的道路交通.材料仓库.附属企业.临时房屋.临时水电管线等做出合理的规划布置,从而正确处理全工地施工期间所需各项设施和永久建筑.拟建 ...查看


  • (六)施工平面布置和临时设施布置方案
  • (六)施工平面布置和临时设施布置方案 1.施工场地布置原则 经过认真细致地调查,分析.研究,在尽可能满足正常施工所要求的情况下,尽量减少所占用的施工场地,整个工程的平面布置要围绕工期安排,并严格执行武汉市有关安全.文明施工的规定和招标人针对 ...查看


  • 如何绘制好施工平面布置
  • 如何绘制好施工平面布置(广联达三维现场 布置) 一.前言 施工总平面布置图是拟建项目施工场地的总布置图.它按照施工方案和施工进度的要求,对施工现场的道路交通.材料仓库.加工场地.主要机械设备.临时房屋.临时水电管线等做出合理的规划布置,从而 ...查看


  • 施工方案管理制度
  • 安全技术方案编制.评审制度 一.术语 施工方案:是以技术复杂.施工技术难度大的分部(分项)工程为对象而编制的具体控制指导施工的技术文件.施工方案是对施工组织设计中施工方法的延续和深化,要求编制内容详细.具体,具有针对性和可操作性. 二.编制 ...查看


  • 专项施工方案编制指南
  • 专项施工方案编制指南 中建七局第四建筑有限公司 2013年5月3日 中建七局第四建筑有限公司专项施工方案编制指南 目录 第一章前言....................................................... ...查看


  • 各专项方案编制要求
  • 各专项方案编制要求 1.基坑支护.降水工程施工方案 1.1 编制说明及依据 简述安全专项施工方案的编制目的以及方案编制所依据的相关法律.法规.规范性文件.标准.规范及图纸(国标图集).施工组织设计等,及编制依据的版本.编号等.采用电算软件的 ...查看


  • 建筑工程安全专项施工方案编制指南
  • 建筑工程安全专项施工方案 编 制 指 南 目 录 1 基坑支护.降水工程施工方案 ............................................................................... ...查看