进度计划及进度控制措施

目 录

一、项目概况: ........................................................................................................................................................ 2

1、施工内容: ................................................................................................................. 2 2、工期要求: ................................................................................................................. 2 3、施工特点: ................................................................................................................. 2

二、进度总方针: ................................................................................................................................................... 2

1、线路划分: ................................................................................................................. 2 2、进度计划总原则: ..................................................................................................... 3

三、具体施工计划安排: ................................................................................................................................... 3

1、施工准备期: ............................................................................................................. 3 2、围墙及室外给排水工程: ......................................................................................... 3 3、校区道路工程: ......................................................................................................... 4 4、广场及绿化工程: ..................................................................................................... 4 5、运动场及篮球场工程: ............................................................................................. 4 6、资料整理: ................................................................................................................. 5 7、竣工验收: ................................................................................................................. 5

四、劳动力使用计划: ........................................................................................................................................ 5 五、机械使用计划: ............................................................................................................................................. 5 六、材料准备计划: ............................................................................................................................................. 6 七、进度计划保证措施: ................................................................................................................................... 8

1、组织措施: ................................................................................................................. 8 2、技术措施: ................................................................................................................. 8 3、经济措施: ................................................................................................................. 9

八、需要业主协调解决事宜: ........................................................................................................................ 9 九、网络进度图: ................................................................................................................................................... 9

郴州出口加工区一完小附属工程

进度计划

一、项目概况: 1、施工内容:

郴州出口加工区一完小附属工程包括有:室外给排水工程、校区道路、围墙工程、广场及绿化工程、运动场及篮球场工程。 2、工期要求:

本附属工程要求与主体工程同时完工,并确保在2014年8月20日全部完工;以便于9月1日正常开学。 3、施工特点:

本项目因主体工程进度缓慢,整体外架未拆除。且多处施工场地被主体工程作为材料堆放地,无法大范围整体施工。整个项目施工任务重,交叉作业多,安全隐患大。

二、进度总方针:

本项目按关键线路与非关建线路划分为两条线路,将平行施工作业与流水施工作业相结合。 1、线路划分:

非关键线路:准备期围墙工程运动场及篮球场工程资料整理竣工验收

关键线路:准备期校区道路工程广场及绿化工程资料整理 2、进度计划总原则:

每条线路里各项目施工采用流水施工作业,做到专业划施工,线路与线路之间的项目采用平行作业施工。重点紧抓关键线路不放松,合理安排、科学管理;确保进度目标,详情参见后面所附施工进度时标计划图。

三、具体施工计划安排: 1、施工准备期:

本项目施工准备期为7天(5月28日-6月3日),主要将各分包商及施工队确定好并签订分包合同,与业主签订好附属工程补充协议。关键是确定分包商及施工队伍的工作,因为本工作处于关键线路上为关键工作;如此项工作不能按期完成,将会影响总工期。 2、围墙及室外给排水工程:

本项目围墙工程已完成整体80%,仅剩下瓷砖及围栏未行安装施工任务不重,时间富余。计划与室外给排水工程同时施工,平行作业,计划26天(6月4日-6月29日)完成。室外给排水工程为关键工作,计划28天(6月4日-7月1日)内完成。整个工程必须在计划工期内准时开工及完工,否则会影响整个施工进度。现阶段室外给排水工程中还有6个化粪池及一个隔油池及1700多米给排水管道未完成,施工任务重。为保证施工质量及进度,我部建议到池体构筑物四周回填时改用透水性材料卵石或碎石。在施工中先施工道路范围内及运动

场区给排水,为下步校区道路及运动场篮球场工程施工赢得时间。排水管道与池体构筑物采用平行施工,确保整个工程在计划工期内完成。

3、校区道路工程:

整个校区道路全长260米,路宽6米。整个道路工程,路基基本与主体工程场地平整时到达设计标高。主要施工量为路面结构层、停车场及路缘石,整个施工采用机械化施工及人工辅助;进度快,相对施工任务较轻,计划在22天(7月2日-7月23日)内完成。主要受主体工程外架及室外给排水工程施工影响,所以要确保在7月2日前施工范围内外架及道路内给排水如期完工。该工作为关键工作,必须确保按计划完工,否则影响下步广场及绿化工程施工开展,并最终影响整体工期。所以准备期内确定好的分包商尤为重要。 4、广场及绿化工程:

广场及绿化工程主要是7月24日前主体工程进入室内装饰,无大材料堆放要求。整体施工范围内采材料清理干净,对整个广场进行平整。整个工程计划在28天(7月24日-8月20日)完成,绿化工程与广场要做到平行作业。该工作也为关键工作,必须在要计划期内完工;否则影响整体施工工期。 5、运动场及篮球场工程:

运动场及篮球场项目为非关键工作,计划在

50天(6月30日-8

月18日)完工。主要受主体工程及给排水工程影响,现运动场区内为主体工程钢筋加工区及堆放区。要在6月30日前将场区给排水工程及钢筋材料清理出场,消除影响。否则将会发生关键线路转移,影

响整个施工期。在准备期及室外给排水工程施工时选定好分包商及相关准备工作。 6、资料整理:

整体附属工程完工后,我部计划安排7天(8月21日-8月27日)时间进行竣工资料收集整理及场地清理工作。 7、竣工验收:

本项目计划在8月28日进行竣工验收。

四、劳动力使用计划: 劳动力计划表:

五、机械使用计划: 机械使用计划表:

六、材料准备计划: 材料准备计划表:

七、进度计划保证措施: 1、组织措施:

我项目部对建设单位确定的施工进度目标高度重视,自项目负责

人到下属施工队多次召开专题会议。并进行了运员大会,成立了赶工领导小组,明确了各自工作责任及分工。增派施工人手,增加每天施工时间,在确保安全的前提下安排夜间加班作业,由原来的两班制改为三班制。 赶工领导小组: 组 长:蔡贤武 副组长:周新平

组 员:欧阳志钢、欧阳帆、蔡宇航、邓利敏、胡小红 2、技术措施:

采用平行作业与流水施工相结合,能用机械施工绝不用人工施工。对施工进度实行动态管理,并对相关工作进行跟踪管理。发现偏差及时找出原因,并进行纠偏。

3、经济措施:

实行包干奖励,提高奖金数额。赶工小组可以对下属施工队采取相关赶工措施对行拍板定价。相关施工队在规定计划工期内提前完工并保证了工程质量,实行现金奖励制度。

八、需要业主协调解决事宜:

1、尽快落实附属工程补充合同,明确工程价款及相关付款条件。 2、对我部所采取赶工措施进行记录及经济补偿。

3、尽快落实运动场设计施工图图纸审工作,方便我部下步工作施工。 4、协调监理方,对我部上报相关方案及资料尽快批复,及时办理。

九、网络进度图:

目 录

一、项目概况: ........................................................................................................................................................ 2

1、施工内容: ................................................................................................................. 2 2、工期要求: ................................................................................................................. 2 3、施工特点: ................................................................................................................. 2

二、进度总方针: ................................................................................................................................................... 2

1、线路划分: ................................................................................................................. 2 2、进度计划总原则: ..................................................................................................... 3

三、具体施工计划安排: ................................................................................................................................... 3

1、施工准备期: ............................................................................................................. 3 2、围墙及室外给排水工程: ......................................................................................... 3 3、校区道路工程: ......................................................................................................... 4 4、广场及绿化工程: ..................................................................................................... 4 5、运动场及篮球场工程: ............................................................................................. 4 6、资料整理: ................................................................................................................. 5 7、竣工验收: ................................................................................................................. 5

四、劳动力使用计划: ........................................................................................................................................ 5 五、机械使用计划: ............................................................................................................................................. 5 六、材料准备计划: ............................................................................................................................................. 6 七、进度计划保证措施: ................................................................................................................................... 8

1、组织措施: ................................................................................................................. 8 2、技术措施: ................................................................................................................. 8 3、经济措施: ................................................................................................................. 9

八、需要业主协调解决事宜: ........................................................................................................................ 9 九、网络进度图: ................................................................................................................................................... 9

郴州出口加工区一完小附属工程

进度计划

一、项目概况: 1、施工内容:

郴州出口加工区一完小附属工程包括有:室外给排水工程、校区道路、围墙工程、广场及绿化工程、运动场及篮球场工程。 2、工期要求:

本附属工程要求与主体工程同时完工,并确保在2014年8月20日全部完工;以便于9月1日正常开学。 3、施工特点:

本项目因主体工程进度缓慢,整体外架未拆除。且多处施工场地被主体工程作为材料堆放地,无法大范围整体施工。整个项目施工任务重,交叉作业多,安全隐患大。

二、进度总方针:

本项目按关键线路与非关建线路划分为两条线路,将平行施工作业与流水施工作业相结合。 1、线路划分:

非关键线路:准备期围墙工程运动场及篮球场工程资料整理竣工验收

关键线路:准备期校区道路工程广场及绿化工程资料整理 2、进度计划总原则:

每条线路里各项目施工采用流水施工作业,做到专业划施工,线路与线路之间的项目采用平行作业施工。重点紧抓关键线路不放松,合理安排、科学管理;确保进度目标,详情参见后面所附施工进度时标计划图。

三、具体施工计划安排: 1、施工准备期:

本项目施工准备期为7天(5月28日-6月3日),主要将各分包商及施工队确定好并签订分包合同,与业主签订好附属工程补充协议。关键是确定分包商及施工队伍的工作,因为本工作处于关键线路上为关键工作;如此项工作不能按期完成,将会影响总工期。 2、围墙及室外给排水工程:

本项目围墙工程已完成整体80%,仅剩下瓷砖及围栏未行安装施工任务不重,时间富余。计划与室外给排水工程同时施工,平行作业,计划26天(6月4日-6月29日)完成。室外给排水工程为关键工作,计划28天(6月4日-7月1日)内完成。整个工程必须在计划工期内准时开工及完工,否则会影响整个施工进度。现阶段室外给排水工程中还有6个化粪池及一个隔油池及1700多米给排水管道未完成,施工任务重。为保证施工质量及进度,我部建议到池体构筑物四周回填时改用透水性材料卵石或碎石。在施工中先施工道路范围内及运动

场区给排水,为下步校区道路及运动场篮球场工程施工赢得时间。排水管道与池体构筑物采用平行施工,确保整个工程在计划工期内完成。

3、校区道路工程:

整个校区道路全长260米,路宽6米。整个道路工程,路基基本与主体工程场地平整时到达设计标高。主要施工量为路面结构层、停车场及路缘石,整个施工采用机械化施工及人工辅助;进度快,相对施工任务较轻,计划在22天(7月2日-7月23日)内完成。主要受主体工程外架及室外给排水工程施工影响,所以要确保在7月2日前施工范围内外架及道路内给排水如期完工。该工作为关键工作,必须确保按计划完工,否则影响下步广场及绿化工程施工开展,并最终影响整体工期。所以准备期内确定好的分包商尤为重要。 4、广场及绿化工程:

广场及绿化工程主要是7月24日前主体工程进入室内装饰,无大材料堆放要求。整体施工范围内采材料清理干净,对整个广场进行平整。整个工程计划在28天(7月24日-8月20日)完成,绿化工程与广场要做到平行作业。该工作也为关键工作,必须在要计划期内完工;否则影响整体施工工期。 5、运动场及篮球场工程:

运动场及篮球场项目为非关键工作,计划在

50天(6月30日-8

月18日)完工。主要受主体工程及给排水工程影响,现运动场区内为主体工程钢筋加工区及堆放区。要在6月30日前将场区给排水工程及钢筋材料清理出场,消除影响。否则将会发生关键线路转移,影

响整个施工期。在准备期及室外给排水工程施工时选定好分包商及相关准备工作。 6、资料整理:

整体附属工程完工后,我部计划安排7天(8月21日-8月27日)时间进行竣工资料收集整理及场地清理工作。 7、竣工验收:

本项目计划在8月28日进行竣工验收。

四、劳动力使用计划: 劳动力计划表:

五、机械使用计划: 机械使用计划表:

六、材料准备计划: 材料准备计划表:

七、进度计划保证措施: 1、组织措施:

我项目部对建设单位确定的施工进度目标高度重视,自项目负责

人到下属施工队多次召开专题会议。并进行了运员大会,成立了赶工领导小组,明确了各自工作责任及分工。增派施工人手,增加每天施工时间,在确保安全的前提下安排夜间加班作业,由原来的两班制改为三班制。 赶工领导小组: 组 长:蔡贤武 副组长:周新平

组 员:欧阳志钢、欧阳帆、蔡宇航、邓利敏、胡小红 2、技术措施:

采用平行作业与流水施工相结合,能用机械施工绝不用人工施工。对施工进度实行动态管理,并对相关工作进行跟踪管理。发现偏差及时找出原因,并进行纠偏。

3、经济措施:

实行包干奖励,提高奖金数额。赶工小组可以对下属施工队采取相关赶工措施对行拍板定价。相关施工队在规定计划工期内提前完工并保证了工程质量,实行现金奖励制度。

八、需要业主协调解决事宜:

1、尽快落实附属工程补充合同,明确工程价款及相关付款条件。 2、对我部所采取赶工措施进行记录及经济补偿。

3、尽快落实运动场设计施工图图纸审工作,方便我部下步工作施工。 4、协调监理方,对我部上报相关方案及资料尽快批复,及时办理。

九、网络进度图:


相关文章

  • 施工进度管理
  • 工程项目进度管理是指在既定的工期内,编制出最优的施工进度计划,在执行该计划的施工中,经常检查施工实际进度情况,并将其与计划进度相比较,若出现偏差,便分析产生的原因和对工期的影响程度,找出必要的调整措施,修改原计划,不断地如此循环,直至工程竣 ...查看


  • 2Z103040施工方进度控制的任务和措施
  • 2009年二级建造师考试网上辅导课程 建设工程施工管理 2Z103040 施工方进度控制的任务和措施 2Z103040 施工方进度控制的任务和措施(P133-136) 2Z103041 掌握施工方进度控制的任务(P133-134) 施工方进 ...查看


  • 进度控制措施
  • 二.进度控制措施 一.工程进度控制目标 在施工合同工期内完成所有工作. 二.进度控制的主要方法与措施 针对本工程的特点,结合我公司多年来丰富的现场监理工作经验,我们认为现场监理部要真正做好进度控制工作,首先得有组织上的保证,即应该在监理部内 ...查看


  • 工程项目管理-建设工程项目进度控制的措施
  • 建设工程项目进度控制的措施 项目进度控制的组织措施 正如前文所述,组织是目标能否实现的决定性因素,为实现项目的进度目标,应充分重视健全项目管理的组织体系.在项目组织结构中应有专门的工作部门和符合进度控制岗位资格的专人负责进度控制工作. 进度 ...查看


  • 进度控制方案及措施
  • --------------------------------工程 进 度 控 制 方 编 制: 审 批: 福建-----工程监理有限公司 ----------项目监理部 年 月 日 案 一. 施工进度控制目标分解图 二.进度风险分析 为 ...查看


  • 监理进度计划管理体系
  • 某市轨道交通1号线第某总监办 土 建 工 程 施 工 监 理 监理进度计划管理体系 编 制 人: 审 批 人: 批准日期: 目 录 一.建立完善的计划管理组织机构 . .................................... ...查看


  • 监理工程师---进度控制知识点
  • 第一章 建设工程进度控制概述 第一节 建设工程项目进度的概念 一.进度控制的概念 建设工程进度控制的总目标是建设工期. 二.影响进度的因素分析 1.业主因素:2.勘察设计因素:3.施工技术因素:4.自然环境因素:5.社会环境因素:6.组织管 ...查看


  • 建设单位工程进度管理办法
  • 建设单位进度管理办法 第一章 总 则 第一条 为确保福建省XXX开发有限公司(以下简称"建设单位")工程项目建设能按预定的时间交付使用进度,及时发挥投资效益和社会效益,特制定本办法. 第二条 本办法适用于建设单位辖区内的 ...查看


  • 工程进度计划书
  • 新建××工程土方及地基处理标段 编制:审核:审批: 施 工 进 度 计 划 ×有限公司 ××项目部 × 一.进度计划 (一)施工进度计划编制的原则 依据施工组织与策划,对里程碑计划的进行分解,确保我公司对业主承诺的各项管理目标的实现.结合本 ...查看


  • 建设工程项目进度控制
  • 12203000建设工程项国进度控制 12203010建设工程项目进度控制与进度计划系统 建设工程项目管理有多种类型,代表不同利益方的项目管理都有进度控制的任务,其控制的目标和时间范畴是不相同的. 建设项目进度控制是一个动态的管理过程,它包 ...查看


热门内容