水利水电工程基本建设程序的思考

水利水电工程基本建设程序的思考

作者:阿吉古•牙克甫

来源:《中国建筑科学》2014年第02期

摘 要:水利工程建设程序一般分为:项目建议书、可行性研究报告、初步设计、施工准备、建设实施、生产准备、竣工验收、后评价等阶段。一般情况下,项目建议书、可行性研究报告、初步设计称为前期工作。水利工程建设项目的实施,必须通过基本建设程序立项。基本建设程序是基本建设项目从决策、设计、施工到竣工验收整个工作过程中各个阶段必须遵循的先后次序。水利水电基本建设因其规模大、费用高、制约因素多等特点,更具复杂性及失事后的严重性。因此,其基本建设程序更复杂,要求更严格。

关键词:水利水电工程;基本建设;程序

Reflections on Water Resources and Hydropower Engineering Infrastructure Program

A ji gu·Ya ke fu

(Xinjiang Kashgar River Basin Water Resources Department of Administration, Kashi 844000)

Abstract:The water conservancy construction procedures are generally divided into: project proposal, feasibility study report, preliminary design, construction preparation, construction and implementation, production preparation, completion and acceptance, the evaluation stage. In general, project proposals, feasibility studies, preliminary design called the preliminary work. Implementation of water conservancy construction projects must project through capital construction program. The basic construction of infrastructure projects from the program is making, design, construction, completion and acceptance of the entire work process must be followed at all stages of the order. The basic construction of water conservancy and hydropower because of its large scale, high costs, constraints and more features, more complexity and seriousness of the accident after. Therefore, the basic construction procedures more complex, requiring more stringent.

Keywords: Water Resources and Hydropower Engineering; basic construction; program

1.项目建议书阶段

项目建议书应根据国民经济和社会发展规划、流域综合规划、区域综合规划、专业规划,按照国家产业政策和国家有关投资建设方针进行编制,是对拟进行建设项目提出的初步说明。项目建议书编制应当委托有相应资格的工程咨询或设计单位承担。

2.可行性研究报告阶段

根据批准的项目建议书,可行性研究报告应对项目进行方案比较,对技术上是否可行和经济上是否合理进行充分的科学分析和论证。经过批准的可行性研究报告,是项目决策和进行初步设计的依据。可行性研究报告编制应当委托有相应资格的工程咨询或设计单位承担。可行性研究报告经批准后,不得随意修改或变更,在主要内容上有重要变动,应经过原批准机关复审同意。

3.初步设计阶段

初步设计是根据批准的可行性研究报告和必要而准确的勘察设计资料,对设计对象进行通盘研究,进一步阐明拟建工程在技术上的可行性和经济上的合理性,确定项目的各项基本技术参数,编制项目的总概算。其中概算静态总投资原则上不得突破已批准的可行性研究报告估算的静态总投资。由于工程项目基本条件发生变化,因其工程规模、工程标准、设计方案、工程量的改变,其静态总投资超过可行性研究报告相应估算静态总投资在15%以下时,要对工程变化内容和增加投资提出专题分析报告。超过15%以上(含15%)时,必须重新编制可行性研究报告并按原程序报批。初步设计报告经批准后,主要内容不得随意修改或变更,并作为项目建设实施的的技术文件基础。在工程项目建设标准和概算投资范围内,依据批准的初步设计原则,一般非重大设计变更、生产性子项目之间的调整,由主管部门批准。在主要内容上有重要变动或修改等,应按照程序上报原批准机关复审同意。初步设计任务应选择有项目相应资格的设计单位承担。

4.施工准备阶段

施工准备阶段(包括招标设计)是指建设项目的主题工程开工前,必须完成的各项准备工作。其中,招标设计指为施工一级设备材料招标而进行的设计工作。

5.建设实施阶段

建设实施阶段是指主体工程的建设实施,项目法人按照批准的建设文件,组织工程建设,保证项目建设目标的实现。

6.生产准备(运行准备)阶段

生产准备(运行准备)指为工程建设项目投入运行前所进行的准备工作,完成生产准备是工程由建设转入生产(运行)的必要条件。项目法人应按照建管结合和项目法人责任制的要求,适时做好有关生产准备(运行准备)工作。生产准备(运行准备)应根据不同类型的工程要求确定,一般包括以下主要工作内容:

(1)生产(运行)组织准备。建立生产(运行)经营的管理机构及相应管理制度。

(2)招收和培训人员。按照生产(运行)的要求,配套生产(运行)管理人员,并通过多种形式的培训,提高人员的素质,使之能满足生产(运行)要求。生产(运行)管理人员要

尽早介入工程的施工建设,参加设备的安装调试工作,熟悉有关情况,掌握生产(运行)技术,为顺利衔接基本建设和生产(运行)阶段做好准备。

(3)生产(运行)技术准备。主要包括技术资料的汇总、生产(运行)技术方案的制定、岗位操作规程制定和新技术准备。

(4)生产(运行)物资准备。主要是落实生产(运行)所需的材料、工器具、备品备件和其他协作配合条件的准备。

(5)正常的生活福利设施准备。

7.竣工验收阶段

竣工验收是工程完成建设目标的标志,是全面考核建设成果、检验设计和工程质量的重要步骤。竣工验收合格的工程建设项目即可以从基本建设转入生产(运行)。

8.后评价阶段

工程建设项目竣工验收后,一般经过1——2年生产(运行)后,要进行一次系统的项目后评价,主要内容包括:影响评价——项目投入生产(运行)后对各方面的影响进行评价;经济效益评价——项目投资、国民经济效益、财务效益、技术进步和规模效益、可行性研究深度等进行评价;过程评价——对项目的立项、勘察设计、施工、建设管理、生产(运行)等全过程进行评价。

项目后评价一般按三个层次组织实施,即项目法人的自我评价、项目行业的评价、主管部门的评价。项目后评价工作必须遵循客观、公正、科学的原则,做到分析合理、评价公正。 上述基本建设程序的八项内容,基本反映了水利工程基本建设工作的全过程。

水利水电工程基本建设程序的思考

作者:阿吉古•牙克甫

来源:《中国建筑科学》2014年第02期

摘 要:水利工程建设程序一般分为:项目建议书、可行性研究报告、初步设计、施工准备、建设实施、生产准备、竣工验收、后评价等阶段。一般情况下,项目建议书、可行性研究报告、初步设计称为前期工作。水利工程建设项目的实施,必须通过基本建设程序立项。基本建设程序是基本建设项目从决策、设计、施工到竣工验收整个工作过程中各个阶段必须遵循的先后次序。水利水电基本建设因其规模大、费用高、制约因素多等特点,更具复杂性及失事后的严重性。因此,其基本建设程序更复杂,要求更严格。

关键词:水利水电工程;基本建设;程序

Reflections on Water Resources and Hydropower Engineering Infrastructure Program

A ji gu·Ya ke fu

(Xinjiang Kashgar River Basin Water Resources Department of Administration, Kashi 844000)

Abstract:The water conservancy construction procedures are generally divided into: project proposal, feasibility study report, preliminary design, construction preparation, construction and implementation, production preparation, completion and acceptance, the evaluation stage. In general, project proposals, feasibility studies, preliminary design called the preliminary work. Implementation of water conservancy construction projects must project through capital construction program. The basic construction of infrastructure projects from the program is making, design, construction, completion and acceptance of the entire work process must be followed at all stages of the order. The basic construction of water conservancy and hydropower because of its large scale, high costs, constraints and more features, more complexity and seriousness of the accident after. Therefore, the basic construction procedures more complex, requiring more stringent.

Keywords: Water Resources and Hydropower Engineering; basic construction; program

1.项目建议书阶段

项目建议书应根据国民经济和社会发展规划、流域综合规划、区域综合规划、专业规划,按照国家产业政策和国家有关投资建设方针进行编制,是对拟进行建设项目提出的初步说明。项目建议书编制应当委托有相应资格的工程咨询或设计单位承担。

2.可行性研究报告阶段

根据批准的项目建议书,可行性研究报告应对项目进行方案比较,对技术上是否可行和经济上是否合理进行充分的科学分析和论证。经过批准的可行性研究报告,是项目决策和进行初步设计的依据。可行性研究报告编制应当委托有相应资格的工程咨询或设计单位承担。可行性研究报告经批准后,不得随意修改或变更,在主要内容上有重要变动,应经过原批准机关复审同意。

3.初步设计阶段

初步设计是根据批准的可行性研究报告和必要而准确的勘察设计资料,对设计对象进行通盘研究,进一步阐明拟建工程在技术上的可行性和经济上的合理性,确定项目的各项基本技术参数,编制项目的总概算。其中概算静态总投资原则上不得突破已批准的可行性研究报告估算的静态总投资。由于工程项目基本条件发生变化,因其工程规模、工程标准、设计方案、工程量的改变,其静态总投资超过可行性研究报告相应估算静态总投资在15%以下时,要对工程变化内容和增加投资提出专题分析报告。超过15%以上(含15%)时,必须重新编制可行性研究报告并按原程序报批。初步设计报告经批准后,主要内容不得随意修改或变更,并作为项目建设实施的的技术文件基础。在工程项目建设标准和概算投资范围内,依据批准的初步设计原则,一般非重大设计变更、生产性子项目之间的调整,由主管部门批准。在主要内容上有重要变动或修改等,应按照程序上报原批准机关复审同意。初步设计任务应选择有项目相应资格的设计单位承担。

4.施工准备阶段

施工准备阶段(包括招标设计)是指建设项目的主题工程开工前,必须完成的各项准备工作。其中,招标设计指为施工一级设备材料招标而进行的设计工作。

5.建设实施阶段

建设实施阶段是指主体工程的建设实施,项目法人按照批准的建设文件,组织工程建设,保证项目建设目标的实现。

6.生产准备(运行准备)阶段

生产准备(运行准备)指为工程建设项目投入运行前所进行的准备工作,完成生产准备是工程由建设转入生产(运行)的必要条件。项目法人应按照建管结合和项目法人责任制的要求,适时做好有关生产准备(运行准备)工作。生产准备(运行准备)应根据不同类型的工程要求确定,一般包括以下主要工作内容:

(1)生产(运行)组织准备。建立生产(运行)经营的管理机构及相应管理制度。

(2)招收和培训人员。按照生产(运行)的要求,配套生产(运行)管理人员,并通过多种形式的培训,提高人员的素质,使之能满足生产(运行)要求。生产(运行)管理人员要

尽早介入工程的施工建设,参加设备的安装调试工作,熟悉有关情况,掌握生产(运行)技术,为顺利衔接基本建设和生产(运行)阶段做好准备。

(3)生产(运行)技术准备。主要包括技术资料的汇总、生产(运行)技术方案的制定、岗位操作规程制定和新技术准备。

(4)生产(运行)物资准备。主要是落实生产(运行)所需的材料、工器具、备品备件和其他协作配合条件的准备。

(5)正常的生活福利设施准备。

7.竣工验收阶段

竣工验收是工程完成建设目标的标志,是全面考核建设成果、检验设计和工程质量的重要步骤。竣工验收合格的工程建设项目即可以从基本建设转入生产(运行)。

8.后评价阶段

工程建设项目竣工验收后,一般经过1——2年生产(运行)后,要进行一次系统的项目后评价,主要内容包括:影响评价——项目投入生产(运行)后对各方面的影响进行评价;经济效益评价——项目投资、国民经济效益、财务效益、技术进步和规模效益、可行性研究深度等进行评价;过程评价——对项目的立项、勘察设计、施工、建设管理、生产(运行)等全过程进行评价。

项目后评价一般按三个层次组织实施,即项目法人的自我评价、项目行业的评价、主管部门的评价。项目后评价工作必须遵循客观、公正、科学的原则,做到分析合理、评价公正。 上述基本建设程序的八项内容,基本反映了水利工程基本建设工作的全过程。


相关文章

  • 水利水电工程施工组织设计管理
  • 水利水电工程施工组织设计 1.什么是施工组织设计 1.1 设计阶段的概念 水利水电工程是一项复杂的系统工程,按我国项目建设现行的基本建设程序,可以划分为9个阶段,一般包括: 2).项目建议书阶段: 3).可行性研究阶段: a.初步设计: b ...查看


  • 竣工验收讲话
  • 同志们: 我省太湖治理工程在省委.省政府和水利部的正确领导以及流域机构指导支持下,经过太湖地区市.县(区)党委.政府和广大水利建设者的共同努力,总体工程已经基本完成,并已发挥显著的抗洪减灾和生态环境效益.根据水利部和流域机构的统一部署,按照 ...查看


  • 论水利工程代建制的模式应用
  • 论水利工程代建制的模式应用 第一章:绪论 1.1 研究背景 水利工程多为国家投资项目,业主方通常以地方水利局为基础而组建,2002年浙江省水利厅在黄岩长潭水库除险加固工程中开始引入代建制,委托浙江省水利水电工程局试行.其后,在乐清市白石水库 ...查看


  • 水利工程建设监理基础知识及相关法规思考题1
  • 水利工程建设监理基础知识及相关法规思考题 一.单项选择题 1.项目是指在一定的约束条件下,具有特定的明确目标的( )事业. A.一次性 B.重复性 C.多次性 D.公共性 2.任何一个项目,不论是大型项目.中型项目,还是小型项目,都必须有( ...查看


  • 我国的水利水电工程移民补偿发展历程分析
  • 探讨与共享 水利水电工程造价・2007年・第1期 我国的水利水电工程移民补偿发展历程分析 曹永强,赵娜,张栾栾 (辽宁师范大学城市与环境学院,大连116029) 关键词:水库移民:移民政策:法律法规摘 要:移民及其安置不仅是一个经济补偿问题 ...查看


  • 水利工程信息化建设的必要性分析
  • 水利工程信息化建设的必要性分析 1 前言 随着科学技术水平的飞速发展,信息化将成为未来发展的大趋所势.可以说,未来社会,信息化将成为一个国家综合国力.现代化水平的重要衡量标准.水利信息化,就是充分利用现代信息技术,开发和利用水利信息资源,包 ...查看


  • 水利水电论文
  • 水利水电工程专业(水工方向)(专科)毕业设计大纲 ( 2003年02月15日) 中央广播电视大学水利水电工程专业 (水工方向)(专科) 毕业设计大纲 毕业设计是完成电大开放式教育水利水电工程专业培养目标所必须的实践性教学环节,学生参加毕业设 ...查看


  • 对农村公共基础设施建设管理的思考
  • 对农村公共基础设施建设管理的思考 区发改委 课题组 农村基础设施是农村经济社会发展和农民生产生活改善的重要物质基础.从我区农村经济社会发展现状和发展全局看,加快农村基础设施建设,着力突破当前农业农村发展关键环节和薄弱环节,不仅对于解决&qu ...查看


  • 都江堰说课稿
  • <都江堰>说课稿 大家好!今天,我说课的内容是<都江堰>.下面我就从教材分析.教法学法.辅助教学.教学程序.板书设计等方面加以说明. 一.说教材 [教材分析] <都江堰>是人教版<中国现代诗歌散文& ...查看


热门内容