锦绣路雨水管沟槽拉森钢板桩支护方案

锦绣路沙福河桥新建工程 钢板桩支护施工方案 编制人: 审核人: 审批人: 企业名称:中铁二十局集团有限公司 编制日期: 年 月 日

目录

第一章 编制依据···························································3。

第一章 编制原则···················································3。

第三章 工程概况···················································4。

一、 工程简介···················································4。

二、 工程量概况·················································4。

三、 平面布置图·················································5。

第四章 拉森钢板桩支护施工·········································6。

一、 施工准备···················································6。

二、 插打钢板桩、安装内支撑·····················7—11。

三、 基坑开挖、钢板桩内支撑·····································11。

四、 支护内排水·················································11。

五、 变形观测···················································12。

六、 管道施工(不作详细论述)·······································12。

七、 拔桩··············································12。

八、 钢板桩支护合拢措施保证·································13。

九、 八字排放口钢板桩围堰施工··································13。

十、质量保证措施··························14—16。 十一、安全文明保证措施·······················16—17。

第一章、编制依据

一、依据西安市政设计研究院有限公司设计的沙井锦绣路沙福河桥(涵)工程施

工图;

二、沙井锦绣路沙福河桥(涵)工程施工合同及工程量清单;

三、现场调查所获取的有关资料;

四、沙井锦绣路沙福河桥(涵)工程指导性施工组织设计;

五、本单位拥有的机械设备、施工技术、管理水平及施工经验。

第二章、编制原则

一、确保工期目标实现

合理配置资源,突出重点工程施工,确保工程工期。

二、确保质量

以质量为核心,以科技为保证,坚持“质量第一,全面创优”的目标,完善质保体系,针对打拉森钢板桩支护进行编制方案,用于指导现场施工,严格控制,精心组织。

三、文明施工与环境安全

采用科学的工法、工艺,确保施工与环境安全,文明施工,爱护环境,主动做好各方协调,减少施工干扰;创造良好的施工、生活环境,确保职工安全、健康。

四、标准化管理

结合钢板桩施工项目特点,建立建设管理的目标体系、责任体系、分级控

制系统,按照本专项方案组织、指挥、协调、控制等基本环节。

第三章、工程概况

一、工程简介

锦绣路沙福河桥新建工程位于宝安沙井,该工程所在场地原始地貌属海成一级阶地,原状为宽约25米的河涌,河道两旁为厂房、道路等,河床地势平缓,场地较平整。原状桥台附近没有经过处理的地基,人工填土层较厚,一般为3.60~6.30m,地下水位较高。因锦绣路东、西侧新建雨水管及八字排放口沟槽开挖过程中,槽边两侧土质稳定性较差,均为淤泥、杂填土,杂填土为新近堆填,成份不均匀,结构疏松,未完成自重固结;淤泥、淤泥质土呈流软塑状。为了防止沟槽开挖塌方,且确保钢板桩入土深度稳固性,锦绣路东、西侧设计的全部雨水主管沟槽两侧均采用Ⅲ型桩长9m的拉森钢板桩密扣支护。八字排放口周边为防止河水涨潮涌入沟槽内,采用9m长Ⅲ型的拉森钢板桩支护及袋装砂包进行支护。

二、工程量概况

钢板桩、支护工程量分布表如下:

三、平面布置图

5

第四章、拉森钢板桩支护施工

一、施工准备

1.1、施工通道

在支护施工前,应保持施工便道通畅,以便非适用性材料的外运和回填材料的内运。

1.2、材料的准备

1.2.1、材料的选用

根据工程所在地特点,结合钢板桩的特性、施工方法等方面进行考虑,选用德国拉森式SP-III槽型钢板桩长9m*宽0.4m*高*0.125m*厚0.013m,钢板桩宽度适中,抗弯性能好,其主要技术参数为:W=1600cm3,g=6 0kg/m,依地质资料及作业条件决定选用,且钢板桩入土深度达桩长0.5倍以上。

1.2.2、材料理论重量计算

采用钢板桩支护总用量:【269长*2*1单重(dn1500管)+28长*2*1单重(dn2000管)+18长*1单重(八字口)】-180原=432吨

1.3、人员机构配备及打桩设备

拟投入50T履带吊和振动锤采用振动沉桩法插打钢板桩,同时可以利用履带吊车吊装内支撑材料来安装内支撑,振动锤为曰本产NPK-HP-7SXB 型,激振力200kN。

人员机构配备图如下:

二、插打钢板桩、安装内支撑

对于该项目管道沟槽两侧钢板桩支护的施工包括插打钢板桩和安装内支撑。 图示:

2.1、钢板桩支护施工流程:

测量放线——插打定位钢板桩——设置导桩框架——清理钢板桩——插打钢板桩——设置内支撑——抽水堵漏——管道施工——拆除内支撑——拔除钢板桩。

2.2、钢板桩的吊运插打

2.2.1、插打桩前的准备工作

①、施工放样与定位,将施工区域控制点标明并经过复核无误后加以有效保护。在打桩时作为导向位置及高程控制标志,定位桩与需施工桩的位置布置。

②、钢板桩不论是新购置还是租的,进入施工现场前均需检查整理,只有完整平直的钢板桩可运入现场。对多次利用的板桩,尤其要强调检查,使用过的板桩,在拨桩、运输、堆放过程中,容易受外界因素影响而变形,如不整理,不利于打入。检查方法可用小平车,在其上放置一块长1.5至2.0m的标准板桩,从头至尾沿被检查板桩走一次,发现缺陷随时调整,板桩整理后,在运输和堆放时要尽量不使其弯曲变形,避免碰撞,尤其不能将连续锁口碰坏。堆放场地应平整坚实,不产生大的沉陷。最下层板桩应垫木块。不同断面板桩需分开堆放,每堆板桩间要留出一定通道,便于吊机或运输车辆的通行。

③、插打钢板桩的导向设备是确保施工后的板桩轴线,对一些要求闭合的围护结构,更需导向。先由测量人员定出钢板桩支护的轴线,可每隔一定距离设置导向桩,导向桩直接使用钢板桩,然后挂绳线作为导线,打桩时利用导线控制钢板桩的轴线。在钢板桩支护合拢后,拆除导向装置,拨除导向桩。导向装置在用完后,可拆出移至下一个钢板桩支护继续使用。

④、钢板桩运输到作业现场,由履带吊吊起插正,然后开启振动锤一边振动,一边插打。在插打钢板桩之前,为保证钢板桩顺利合拢,应先打下导向架。

在插打钢板桩时,第一根钢板桩必须插正、打正,以免影响后面的钢板桩。在整个钢板桩支护施打过程中,开始时可插一根打一根,即将每一片钢板桩打到设计位置,到剩下最后20片时,要先插后打,若合拢有误,用倒链或滑车组对拉使之合拢,合拢后,再逐根打到设计深度。单桩逐根连续施打,注意桩顶高程不宜相差太大。

2.2.2、钢板桩的插打作业步骤和技术要点

①、在钢板桩锁口内涂黄油,安置吊点,根据履带吊起重高度可在桩顶利用拔桩孔系千斤顶,如起重机高度不够,可用钢丝绳在钢板桩1/3以上处捆扎,捆扎处应有夹板,并垫有木块,胶皮以防滑移和受力后吊点处锁口变形。

②、钢板桩下端系揽风绳二根,履带吊起吊钢板桩接近垂直状态时,利用揽风绳控制正反方向。

③、钢板桩就位下插,第一片钢板桩沿活动导向下插是整个支护的基准,要反复测量检查,使其方向垂直,位置准确,必要时可加辅助设施,控制桩在导向内的左右位置。

④、移动履带吊,将桩夹住后,进一步复核桩的垂直度、位置,认可后进行插打。使钢板桩(第一片或第一组)下沉到设计标高,其它钢板桩则以插打好的桩为准。对准锁口,控制好方向,利用自重下插,当自重不能迫使下插时,可利用配重或滑车组加压。

2.2.3、钢板桩打入施工工艺

①、履带吊停在离打桩点就近的平台,侧向施工,便于测量人员观察。挂上振动锤,升高,理顺油管及电缆。

②、锤下降,开液压口,拉一根桩至打桩锤下,锁口抹上润滑油,起锤。 ③、待钢板桩尖离开水面30cm 时,停止上升。锤下降,使桩至夹口中,开动液压机,夹紧桩。上升锤与桩,至打桩地点。

④、对准桩与定位桩的锁口,锤下降,靠锤与桩自重压桩至淤泥以下一定深度不能下降为止。

⑤、试开打桩锤30 秒左右,停止振动,利用锤惯性打桩至坚实土层,开动

振动锤打桩下降,控制打桩锤下降的速度,尽可能的使桩保持竖直,以便锁口能顺利咬合,提高止水能力。

⑥、板桩至设计高度前40cm 时,停止振动,振动锤因惯性继续转动一定时间,打桩至设计高度。

⑦、松开液压夹口,锤上升,打第二根桩,以上类推至打完所有桩。打桩前一般应在锁口内涂以黄油、锯末等混合物,在打完钢板桩后,开始进行钢板桩支护内的止水处理。

2.3、钢板桩施工注意事项

①、导向桩打好之后,以槽钢焊接牢固,确保导向桩不晃动,以便打桩时提高精确度。

②、线桩插打,钢板桩起吊后人力将桩插入锁口,动作缓慢,防止损坏锁口,插入后可稍松吊绳,使桩凭自重滑入。

③、钢板桩振动插打到小于设计标高40cm 时,小心施工,防止超深发生。 ④、封口时,精确计算异形钢板桩的尺寸,确保止水质量。

⑤、防渗与堵漏,钢板桩打入之前一般应在锁口内涂以黄油、锯末等混合物。当锁口不紧密漏水时,用棉絮等在内侧嵌塞,外侧包裹一层防水彩条布,起到防水和减小水压力的双重效果,抽水时同时在外侧水中漏缝处撒大量木屑或谷糠和炉渣的混合物,使其由水夹带至漏水处自行堵塞,在桩脚漏水处,采用局部砼封底等措施。若漏水严重,堵漏困难时,在钢板桩外侧补打木桩支护,木桩支护内侧铺设彩条布,在彩条布与钢板桩支护间填筑粘土进行封堵。

2.4、钢板桩的施工中遇到的问题及处理:

由于地质结构复杂,钢板桩打拔施工中常遇到一些难题,常采用如下几点办法解决:

①、桩过程中有时遇上大的块石或其它不明障碍物,导致钢板桩打入深度不够,采用转角桩或弧形桩绕过障碍物。

②、钢板桩杂填土地段挤进过程中受到石块等侧向挤压作用力大小不同容易发生偏斜,采取以下措施进行纠偏:在发生偏斜位置将钢板桩往上拔l.0m~2.0m,再往下锤进,如此上下往复振拔数次,可使大的块石被振碎或使其发生位移,让钢板桩的位置得到纠正,减少钢板桩的倾斜度。

③、钢板桩沿轴线倾斜度较大时,采用异形桩来纠正,异形桩一般为上宽下窄和宽度大于或小于标准宽度的板桩,异形桩可根据据实际倾斜度进行焊接加工;倾斜度较小时也可以用卷扬机或葫芦和钢索将桩反向拉住再锤击。④在基础较软处,有时发生施工当时将邻桩带入现象,采用的措施是把相邻的数根桩焊接在一起,并且在施打当桩的连接锁口上涂以黄油等润滑济减少阻力。

三、 基坑开挖、钢板桩内支撑

在钢板桩支护合拢后,将设置内支撑,矩形支护宜采用平面钢架支撑为宜,四个角设置为三角形,其稳定性较好,又可以做成抽水平台,内支撑的安装由上往下。

钢支护内基础开挖,采用的方法是:钢板桩合拢后,安装内支撑。内支撑施工具体做法:先在钢板桩上焊接内支撑牛腿(型钢),然后进行内支撑安装,根据水压力和土压力计算决定,该项目两侧支护的拉森钢板桩之间每排隔4米安装1根内支撑,考虑到水下地质情况较差,周围动荷载和主动土压力较大,因此决定在支护内部采用Ф108×8mm 的钢管桩做成骨架进行支撑。

四、支护内排水

支护内排水是利用抽水机进行排水,其排水量应大于支护内渗水量的1.5至2倍,抽完支护内水,要留有1-2台抽水机备用。

由于钢板桩的锁口之间连接不紧密,支护通常会漏水,因此在抽水过程中,通常采用细麻丝、棉条等材料,在钢板桩内侧嵌塞、塞紧,或者用锯屑加细煤

灰在漏缝外侧周围放入,随水夹带至漏缝处自行堵塞。

五、变形观测

在钢板桩支护挡水期间,我们定期对钢板桩顶的位移进行观测,发现桩顶向基坑内的偏移量稳定在2~10cm 之间,说明堰体是稳定的。

六、管道施工

根据施工图设计及规范要求对管道安装、沟槽回填进行施工。

七、拔桩

8.1、施工要点

支护内沟槽回填达到规范要求压实度后,清除支护内残留物,才能进行拔桩。在拔桩前应向支护内抽水达到一定水位时,由下往上拆除内支撑,直到支护内支撑全部拆除完,支护内外水位相同,方可进行拔桩。拔桩时,可以借助千斤顶松动钢板桩,减少钢板桩与土、钢板桩之间的摩擦力,然后由履带吊吊起,当钢板桩还有较大的摩擦力,履带吊不能吊起时,应在钢板桩上设立支点,用千斤顶继续向上松动,直到履带吊能吊动为止。拔桩时注意桩机的负荷情况,发现上拔困难或拔不上来时,应停止拔桩,显获动1min~2min 后再往下锤

0.5m~1.0m 再往上振拔,如此反复可将桩拔出来,钢板桩拔除后留下的桩孔,必须即做回填处理,回填一般用挤密法或填入法,所用材料为中砂。

8.2、拔桩注意事项

①、为防止将临近板桩同时拔出,宜将钢板桩和加固的槽钢逐根割断。

②、先割除钢板桩的支撑,然后再拔支护钢板桩。

③、拔出的钢板桩应及时清除土砂,涂以油脂。变形较大的板桩需调直,完整的板桩要及时运出工地,堆置在平整的场地上。

④、将钢板桩用振动锤再复打一次,可克服土的黏附力。

⑤、按与打板桩顺序相反的次序拔桩。

八、钢板桩支护合拢措施保证

钢板桩支护插打至合拢面时,应精确丈量尺寸,考虑到钢板桩锁口的间隙和钢板桩本身的性能,合拢面尺寸应大于理论尺寸15-20厘米为宜,避免合拢口尺寸过小的出现:同时与合拢口相邻的10-15片(组)钢板桩采取先插至桩的稳定标高,主要是有利于钢板桩的调整,并且合拢口两侧钢板桩具有高差,便于插桩,待合拢后,再将桩打至设计标高。合拢口解决措施如下:

9.1、钢板状合拢口尺寸上下都大时:

9.1.1、当尺寸上大下小时,在合拢口两侧钢板桩上下平行吊耳,位置根据尺寸大小的差值而定,利用倒链或转向滑轮进行对位,直至符合要求合拢为止。其优点是:钢板桩对向平行受拉能保证桩的两侧锁口在同一平面内,通过对拉,使两侧钢板桩连接有利于稳定,便于插桩合拢。

9.1.2、当尺寸下大上小时,钢板桩上设置的吊耳,应尽量向桩的下部安置,必要时可安放在水下对位,直至合拢。

9.1.3、合拢口尺寸上下都小时:此时应将合拢口的位置设置在合拢面一侧的角桩附近。用千斤顶在钢板桩顶端顶推和设置吊耳,将合拢口向两侧张拉,调整上下尺寸,但要采取保证两侧钢板桩锁口在同一平面内,一般是在桩内外安置活动导向,迫使钢板桩在导梁平面内移动。

九、八字排放口钢板桩围堰施工

八字排放口周边为防止河水涨潮涌入沟槽内,采用9m长Ⅲ型的拉森钢板桩支护及袋装砂包进行四周围堰。拉森钢板桩围堰长度为18m,支护施工工艺同上述内容。四周围堰采用尼龙编织袋装砂包围堰,围堰顶宽及底宽为2m,围堰高度为1.2m, 砂包围堰工程量为:18长×2宽×1.2高=43.2m³。

如下图:

III型的拉森钢板桩支护且八字排放口周边采用砂袋围堰图

十、质量保证措施

10.1、质量保证措施

建立健全质量安全管理网络,及时发现和清除各种质量安全隐患,防患于未然。

10.1.1、严格遵守和执行有关的施工质量规范。

10.1.2、根据ISO9001 标准要求,推行全面质量管理,建立质量保证体系,提高全员质量意识,确保质量管理惯彻整个施工过程。坚持质量自检、互检、交

接检“三检”制。

10.1.3、以项目经理为质量第一负责人,任命1至2名合适的有资格人员负责质量管理方面的工作,并保持与设计施工等各方面有效协调。

10.1.4、各种原材料,半成品严格按质量要求进行采购。钢板桩送到现场后,应及时检查、分类、编号,钢板桩锁口应以一块长1.5~2.0m 标准钢板桩进行滑动检查,凡锁口不合应进行修正合格后方能使用。

10.1.5、钢板桩质量要求

①、桩的垂直度控制在1%以内;

②、桩底高程误差控制在10cm 左右;

③、沉桩要连续,不允许出现不连锁现象;

④、桩的平面位移控制在15cm 以内。

10.1.6、在使用拼接接长的钢板桩时,钢板桩的拼接接头不能在支护的同一断面上,而且相邻桩的接头上下错开至少2m,所以,在组拼钢板桩时要预先配桩,在运输、存放时,按插桩顺利堆码,插桩时按规定的顺序吊插。

10.1.7、钢板桩支护在使用过程中,防止支护内水位高于支护外水位。在低水位处设置连通管,到支护内抽水时,再予封闭,在支护内抽水时,钢板桩锁口漏水,在支护外撒大量细煤渣、木屑、谷糠等细物,借漏水的吸力附于锁口内堵水,或者在支护内用板条、棉絮等楔入锁口内嵌缝,撒煤渣等物堵漏时,要考虑水流方向并尽量接近漏缝,漏缝较深时,用袋装下放到漏缝附近处徐徐倒撒,同时当支护内抽水至各层支撑导梁处,逐层将导梁与钢板桩之间的缝隙用木楔紧,使导梁受力均匀。

10.2、工期保证措施

10.2.1、项目经理部立即开展工作,调遣具有丰富同类工程施工经验和责任心

强的工程技术、经济、行政等各类专业管理人员和施工队伍上场。

10.2.2、实行项目法施工管理方式,做到统一组织、统一管理、统一计划协调、统一物资供应、统一资金收付。各施工队伍在项目经理部的统一领导下,互相协作配合共同完成所承担的施工任务。

10.2.3、发挥整体优势,对施工队伍实行动态管理,合理组合。

10.2.4、加强现场的思想政治工作,抓住时机,开展以比质量、比安全、比进度、比效益的劳动竞赛,使每一位参加施工的职工都充满责任感、荣誉感和紧迫感,发挥出最大的积极性。

10.2.5、正确处理好与当地政府及兄弟单位的关系,取得各方面的支持与配合,为施工生产创造一个良好的外部环境。

十一、安全文明保证措施

11.1、机械设备安全保证措施

11.1.1、机械设备操作人员(或驾驶员)必须经过专门训练,熟悉机械操作性能,经专业管理部门考核取得操作证或驾驶证后上机(车)操作。

11.1.2、机械设备操作人员和指挥人员严格遵守安全操作技术规程,工作时集中精力,谨慎工作,不擅离职守,严禁酒后驾驶。

11.1.3、机械设备发生故障后及时检修,决不带故障运行,不违规操作,杜绝机械和车辆事故。

11.1.4、机械操作人员做好各项记录,达到准确、及时,严格贯彻操作制度,认真执行清洁、润滑、坚固、防腐、安全的十字作业法。

11.1.5、设备及工具摆放整齐,不得随意摆放。

11.2、安全文明施工

11.2.1、为避免施工现场的混乱现象,现场文明施工划区域派专人负责,落实

岗位责任制,搞好环境卫生工作。

11.2.2、施工现场必须按施工平面图进行布置,不能随意改变。

11.2.3、工地现场入口设置现场标志牌,明确各区域负责范围,不定期检查和督促。

11.2.4、现场材料进场道路保持畅通无阻,排水畅通,无积水,场地整洁、材料堆放整齐,无施工垃圾。

11.2.5、进入现场施工人员必须佩戴安全帽,讲究文明用语,杜绝打架斗殴,酗酒等不文明行为。

11.2.6、注意工地防火,现场要摆放防火器材。

11.2.7、与当地医疗保健和消防等部门保持密切联系,做到有备无患。 11.2.8、现场必须配足足够的消防设备。

锦绣路沙福河桥新建工程 钢板桩支护施工方案 编制人: 审核人: 审批人: 企业名称:中铁二十局集团有限公司 编制日期: 年 月 日

目录

第一章 编制依据···························································3。

第一章 编制原则···················································3。

第三章 工程概况···················································4。

一、 工程简介···················································4。

二、 工程量概况·················································4。

三、 平面布置图·················································5。

第四章 拉森钢板桩支护施工·········································6。

一、 施工准备···················································6。

二、 插打钢板桩、安装内支撑·····················7—11。

三、 基坑开挖、钢板桩内支撑·····································11。

四、 支护内排水·················································11。

五、 变形观测···················································12。

六、 管道施工(不作详细论述)·······································12。

七、 拔桩··············································12。

八、 钢板桩支护合拢措施保证·································13。

九、 八字排放口钢板桩围堰施工··································13。

十、质量保证措施··························14—16。 十一、安全文明保证措施·······················16—17。

第一章、编制依据

一、依据西安市政设计研究院有限公司设计的沙井锦绣路沙福河桥(涵)工程施

工图;

二、沙井锦绣路沙福河桥(涵)工程施工合同及工程量清单;

三、现场调查所获取的有关资料;

四、沙井锦绣路沙福河桥(涵)工程指导性施工组织设计;

五、本单位拥有的机械设备、施工技术、管理水平及施工经验。

第二章、编制原则

一、确保工期目标实现

合理配置资源,突出重点工程施工,确保工程工期。

二、确保质量

以质量为核心,以科技为保证,坚持“质量第一,全面创优”的目标,完善质保体系,针对打拉森钢板桩支护进行编制方案,用于指导现场施工,严格控制,精心组织。

三、文明施工与环境安全

采用科学的工法、工艺,确保施工与环境安全,文明施工,爱护环境,主动做好各方协调,减少施工干扰;创造良好的施工、生活环境,确保职工安全、健康。

四、标准化管理

结合钢板桩施工项目特点,建立建设管理的目标体系、责任体系、分级控

制系统,按照本专项方案组织、指挥、协调、控制等基本环节。

第三章、工程概况

一、工程简介

锦绣路沙福河桥新建工程位于宝安沙井,该工程所在场地原始地貌属海成一级阶地,原状为宽约25米的河涌,河道两旁为厂房、道路等,河床地势平缓,场地较平整。原状桥台附近没有经过处理的地基,人工填土层较厚,一般为3.60~6.30m,地下水位较高。因锦绣路东、西侧新建雨水管及八字排放口沟槽开挖过程中,槽边两侧土质稳定性较差,均为淤泥、杂填土,杂填土为新近堆填,成份不均匀,结构疏松,未完成自重固结;淤泥、淤泥质土呈流软塑状。为了防止沟槽开挖塌方,且确保钢板桩入土深度稳固性,锦绣路东、西侧设计的全部雨水主管沟槽两侧均采用Ⅲ型桩长9m的拉森钢板桩密扣支护。八字排放口周边为防止河水涨潮涌入沟槽内,采用9m长Ⅲ型的拉森钢板桩支护及袋装砂包进行支护。

二、工程量概况

钢板桩、支护工程量分布表如下:

三、平面布置图

5

第四章、拉森钢板桩支护施工

一、施工准备

1.1、施工通道

在支护施工前,应保持施工便道通畅,以便非适用性材料的外运和回填材料的内运。

1.2、材料的准备

1.2.1、材料的选用

根据工程所在地特点,结合钢板桩的特性、施工方法等方面进行考虑,选用德国拉森式SP-III槽型钢板桩长9m*宽0.4m*高*0.125m*厚0.013m,钢板桩宽度适中,抗弯性能好,其主要技术参数为:W=1600cm3,g=6 0kg/m,依地质资料及作业条件决定选用,且钢板桩入土深度达桩长0.5倍以上。

1.2.2、材料理论重量计算

采用钢板桩支护总用量:【269长*2*1单重(dn1500管)+28长*2*1单重(dn2000管)+18长*1单重(八字口)】-180原=432吨

1.3、人员机构配备及打桩设备

拟投入50T履带吊和振动锤采用振动沉桩法插打钢板桩,同时可以利用履带吊车吊装内支撑材料来安装内支撑,振动锤为曰本产NPK-HP-7SXB 型,激振力200kN。

人员机构配备图如下:

二、插打钢板桩、安装内支撑

对于该项目管道沟槽两侧钢板桩支护的施工包括插打钢板桩和安装内支撑。 图示:

2.1、钢板桩支护施工流程:

测量放线——插打定位钢板桩——设置导桩框架——清理钢板桩——插打钢板桩——设置内支撑——抽水堵漏——管道施工——拆除内支撑——拔除钢板桩。

2.2、钢板桩的吊运插打

2.2.1、插打桩前的准备工作

①、施工放样与定位,将施工区域控制点标明并经过复核无误后加以有效保护。在打桩时作为导向位置及高程控制标志,定位桩与需施工桩的位置布置。

②、钢板桩不论是新购置还是租的,进入施工现场前均需检查整理,只有完整平直的钢板桩可运入现场。对多次利用的板桩,尤其要强调检查,使用过的板桩,在拨桩、运输、堆放过程中,容易受外界因素影响而变形,如不整理,不利于打入。检查方法可用小平车,在其上放置一块长1.5至2.0m的标准板桩,从头至尾沿被检查板桩走一次,发现缺陷随时调整,板桩整理后,在运输和堆放时要尽量不使其弯曲变形,避免碰撞,尤其不能将连续锁口碰坏。堆放场地应平整坚实,不产生大的沉陷。最下层板桩应垫木块。不同断面板桩需分开堆放,每堆板桩间要留出一定通道,便于吊机或运输车辆的通行。

③、插打钢板桩的导向设备是确保施工后的板桩轴线,对一些要求闭合的围护结构,更需导向。先由测量人员定出钢板桩支护的轴线,可每隔一定距离设置导向桩,导向桩直接使用钢板桩,然后挂绳线作为导线,打桩时利用导线控制钢板桩的轴线。在钢板桩支护合拢后,拆除导向装置,拨除导向桩。导向装置在用完后,可拆出移至下一个钢板桩支护继续使用。

④、钢板桩运输到作业现场,由履带吊吊起插正,然后开启振动锤一边振动,一边插打。在插打钢板桩之前,为保证钢板桩顺利合拢,应先打下导向架。

在插打钢板桩时,第一根钢板桩必须插正、打正,以免影响后面的钢板桩。在整个钢板桩支护施打过程中,开始时可插一根打一根,即将每一片钢板桩打到设计位置,到剩下最后20片时,要先插后打,若合拢有误,用倒链或滑车组对拉使之合拢,合拢后,再逐根打到设计深度。单桩逐根连续施打,注意桩顶高程不宜相差太大。

2.2.2、钢板桩的插打作业步骤和技术要点

①、在钢板桩锁口内涂黄油,安置吊点,根据履带吊起重高度可在桩顶利用拔桩孔系千斤顶,如起重机高度不够,可用钢丝绳在钢板桩1/3以上处捆扎,捆扎处应有夹板,并垫有木块,胶皮以防滑移和受力后吊点处锁口变形。

②、钢板桩下端系揽风绳二根,履带吊起吊钢板桩接近垂直状态时,利用揽风绳控制正反方向。

③、钢板桩就位下插,第一片钢板桩沿活动导向下插是整个支护的基准,要反复测量检查,使其方向垂直,位置准确,必要时可加辅助设施,控制桩在导向内的左右位置。

④、移动履带吊,将桩夹住后,进一步复核桩的垂直度、位置,认可后进行插打。使钢板桩(第一片或第一组)下沉到设计标高,其它钢板桩则以插打好的桩为准。对准锁口,控制好方向,利用自重下插,当自重不能迫使下插时,可利用配重或滑车组加压。

2.2.3、钢板桩打入施工工艺

①、履带吊停在离打桩点就近的平台,侧向施工,便于测量人员观察。挂上振动锤,升高,理顺油管及电缆。

②、锤下降,开液压口,拉一根桩至打桩锤下,锁口抹上润滑油,起锤。 ③、待钢板桩尖离开水面30cm 时,停止上升。锤下降,使桩至夹口中,开动液压机,夹紧桩。上升锤与桩,至打桩地点。

④、对准桩与定位桩的锁口,锤下降,靠锤与桩自重压桩至淤泥以下一定深度不能下降为止。

⑤、试开打桩锤30 秒左右,停止振动,利用锤惯性打桩至坚实土层,开动

振动锤打桩下降,控制打桩锤下降的速度,尽可能的使桩保持竖直,以便锁口能顺利咬合,提高止水能力。

⑥、板桩至设计高度前40cm 时,停止振动,振动锤因惯性继续转动一定时间,打桩至设计高度。

⑦、松开液压夹口,锤上升,打第二根桩,以上类推至打完所有桩。打桩前一般应在锁口内涂以黄油、锯末等混合物,在打完钢板桩后,开始进行钢板桩支护内的止水处理。

2.3、钢板桩施工注意事项

①、导向桩打好之后,以槽钢焊接牢固,确保导向桩不晃动,以便打桩时提高精确度。

②、线桩插打,钢板桩起吊后人力将桩插入锁口,动作缓慢,防止损坏锁口,插入后可稍松吊绳,使桩凭自重滑入。

③、钢板桩振动插打到小于设计标高40cm 时,小心施工,防止超深发生。 ④、封口时,精确计算异形钢板桩的尺寸,确保止水质量。

⑤、防渗与堵漏,钢板桩打入之前一般应在锁口内涂以黄油、锯末等混合物。当锁口不紧密漏水时,用棉絮等在内侧嵌塞,外侧包裹一层防水彩条布,起到防水和减小水压力的双重效果,抽水时同时在外侧水中漏缝处撒大量木屑或谷糠和炉渣的混合物,使其由水夹带至漏水处自行堵塞,在桩脚漏水处,采用局部砼封底等措施。若漏水严重,堵漏困难时,在钢板桩外侧补打木桩支护,木桩支护内侧铺设彩条布,在彩条布与钢板桩支护间填筑粘土进行封堵。

2.4、钢板桩的施工中遇到的问题及处理:

由于地质结构复杂,钢板桩打拔施工中常遇到一些难题,常采用如下几点办法解决:

①、桩过程中有时遇上大的块石或其它不明障碍物,导致钢板桩打入深度不够,采用转角桩或弧形桩绕过障碍物。

②、钢板桩杂填土地段挤进过程中受到石块等侧向挤压作用力大小不同容易发生偏斜,采取以下措施进行纠偏:在发生偏斜位置将钢板桩往上拔l.0m~2.0m,再往下锤进,如此上下往复振拔数次,可使大的块石被振碎或使其发生位移,让钢板桩的位置得到纠正,减少钢板桩的倾斜度。

③、钢板桩沿轴线倾斜度较大时,采用异形桩来纠正,异形桩一般为上宽下窄和宽度大于或小于标准宽度的板桩,异形桩可根据据实际倾斜度进行焊接加工;倾斜度较小时也可以用卷扬机或葫芦和钢索将桩反向拉住再锤击。④在基础较软处,有时发生施工当时将邻桩带入现象,采用的措施是把相邻的数根桩焊接在一起,并且在施打当桩的连接锁口上涂以黄油等润滑济减少阻力。

三、 基坑开挖、钢板桩内支撑

在钢板桩支护合拢后,将设置内支撑,矩形支护宜采用平面钢架支撑为宜,四个角设置为三角形,其稳定性较好,又可以做成抽水平台,内支撑的安装由上往下。

钢支护内基础开挖,采用的方法是:钢板桩合拢后,安装内支撑。内支撑施工具体做法:先在钢板桩上焊接内支撑牛腿(型钢),然后进行内支撑安装,根据水压力和土压力计算决定,该项目两侧支护的拉森钢板桩之间每排隔4米安装1根内支撑,考虑到水下地质情况较差,周围动荷载和主动土压力较大,因此决定在支护内部采用Ф108×8mm 的钢管桩做成骨架进行支撑。

四、支护内排水

支护内排水是利用抽水机进行排水,其排水量应大于支护内渗水量的1.5至2倍,抽完支护内水,要留有1-2台抽水机备用。

由于钢板桩的锁口之间连接不紧密,支护通常会漏水,因此在抽水过程中,通常采用细麻丝、棉条等材料,在钢板桩内侧嵌塞、塞紧,或者用锯屑加细煤

灰在漏缝外侧周围放入,随水夹带至漏缝处自行堵塞。

五、变形观测

在钢板桩支护挡水期间,我们定期对钢板桩顶的位移进行观测,发现桩顶向基坑内的偏移量稳定在2~10cm 之间,说明堰体是稳定的。

六、管道施工

根据施工图设计及规范要求对管道安装、沟槽回填进行施工。

七、拔桩

8.1、施工要点

支护内沟槽回填达到规范要求压实度后,清除支护内残留物,才能进行拔桩。在拔桩前应向支护内抽水达到一定水位时,由下往上拆除内支撑,直到支护内支撑全部拆除完,支护内外水位相同,方可进行拔桩。拔桩时,可以借助千斤顶松动钢板桩,减少钢板桩与土、钢板桩之间的摩擦力,然后由履带吊吊起,当钢板桩还有较大的摩擦力,履带吊不能吊起时,应在钢板桩上设立支点,用千斤顶继续向上松动,直到履带吊能吊动为止。拔桩时注意桩机的负荷情况,发现上拔困难或拔不上来时,应停止拔桩,显获动1min~2min 后再往下锤

0.5m~1.0m 再往上振拔,如此反复可将桩拔出来,钢板桩拔除后留下的桩孔,必须即做回填处理,回填一般用挤密法或填入法,所用材料为中砂。

8.2、拔桩注意事项

①、为防止将临近板桩同时拔出,宜将钢板桩和加固的槽钢逐根割断。

②、先割除钢板桩的支撑,然后再拔支护钢板桩。

③、拔出的钢板桩应及时清除土砂,涂以油脂。变形较大的板桩需调直,完整的板桩要及时运出工地,堆置在平整的场地上。

④、将钢板桩用振动锤再复打一次,可克服土的黏附力。

⑤、按与打板桩顺序相反的次序拔桩。

八、钢板桩支护合拢措施保证

钢板桩支护插打至合拢面时,应精确丈量尺寸,考虑到钢板桩锁口的间隙和钢板桩本身的性能,合拢面尺寸应大于理论尺寸15-20厘米为宜,避免合拢口尺寸过小的出现:同时与合拢口相邻的10-15片(组)钢板桩采取先插至桩的稳定标高,主要是有利于钢板桩的调整,并且合拢口两侧钢板桩具有高差,便于插桩,待合拢后,再将桩打至设计标高。合拢口解决措施如下:

9.1、钢板状合拢口尺寸上下都大时:

9.1.1、当尺寸上大下小时,在合拢口两侧钢板桩上下平行吊耳,位置根据尺寸大小的差值而定,利用倒链或转向滑轮进行对位,直至符合要求合拢为止。其优点是:钢板桩对向平行受拉能保证桩的两侧锁口在同一平面内,通过对拉,使两侧钢板桩连接有利于稳定,便于插桩合拢。

9.1.2、当尺寸下大上小时,钢板桩上设置的吊耳,应尽量向桩的下部安置,必要时可安放在水下对位,直至合拢。

9.1.3、合拢口尺寸上下都小时:此时应将合拢口的位置设置在合拢面一侧的角桩附近。用千斤顶在钢板桩顶端顶推和设置吊耳,将合拢口向两侧张拉,调整上下尺寸,但要采取保证两侧钢板桩锁口在同一平面内,一般是在桩内外安置活动导向,迫使钢板桩在导梁平面内移动。

九、八字排放口钢板桩围堰施工

八字排放口周边为防止河水涨潮涌入沟槽内,采用9m长Ⅲ型的拉森钢板桩支护及袋装砂包进行四周围堰。拉森钢板桩围堰长度为18m,支护施工工艺同上述内容。四周围堰采用尼龙编织袋装砂包围堰,围堰顶宽及底宽为2m,围堰高度为1.2m, 砂包围堰工程量为:18长×2宽×1.2高=43.2m³。

如下图:

III型的拉森钢板桩支护且八字排放口周边采用砂袋围堰图

十、质量保证措施

10.1、质量保证措施

建立健全质量安全管理网络,及时发现和清除各种质量安全隐患,防患于未然。

10.1.1、严格遵守和执行有关的施工质量规范。

10.1.2、根据ISO9001 标准要求,推行全面质量管理,建立质量保证体系,提高全员质量意识,确保质量管理惯彻整个施工过程。坚持质量自检、互检、交

接检“三检”制。

10.1.3、以项目经理为质量第一负责人,任命1至2名合适的有资格人员负责质量管理方面的工作,并保持与设计施工等各方面有效协调。

10.1.4、各种原材料,半成品严格按质量要求进行采购。钢板桩送到现场后,应及时检查、分类、编号,钢板桩锁口应以一块长1.5~2.0m 标准钢板桩进行滑动检查,凡锁口不合应进行修正合格后方能使用。

10.1.5、钢板桩质量要求

①、桩的垂直度控制在1%以内;

②、桩底高程误差控制在10cm 左右;

③、沉桩要连续,不允许出现不连锁现象;

④、桩的平面位移控制在15cm 以内。

10.1.6、在使用拼接接长的钢板桩时,钢板桩的拼接接头不能在支护的同一断面上,而且相邻桩的接头上下错开至少2m,所以,在组拼钢板桩时要预先配桩,在运输、存放时,按插桩顺利堆码,插桩时按规定的顺序吊插。

10.1.7、钢板桩支护在使用过程中,防止支护内水位高于支护外水位。在低水位处设置连通管,到支护内抽水时,再予封闭,在支护内抽水时,钢板桩锁口漏水,在支护外撒大量细煤渣、木屑、谷糠等细物,借漏水的吸力附于锁口内堵水,或者在支护内用板条、棉絮等楔入锁口内嵌缝,撒煤渣等物堵漏时,要考虑水流方向并尽量接近漏缝,漏缝较深时,用袋装下放到漏缝附近处徐徐倒撒,同时当支护内抽水至各层支撑导梁处,逐层将导梁与钢板桩之间的缝隙用木楔紧,使导梁受力均匀。

10.2、工期保证措施

10.2.1、项目经理部立即开展工作,调遣具有丰富同类工程施工经验和责任心

强的工程技术、经济、行政等各类专业管理人员和施工队伍上场。

10.2.2、实行项目法施工管理方式,做到统一组织、统一管理、统一计划协调、统一物资供应、统一资金收付。各施工队伍在项目经理部的统一领导下,互相协作配合共同完成所承担的施工任务。

10.2.3、发挥整体优势,对施工队伍实行动态管理,合理组合。

10.2.4、加强现场的思想政治工作,抓住时机,开展以比质量、比安全、比进度、比效益的劳动竞赛,使每一位参加施工的职工都充满责任感、荣誉感和紧迫感,发挥出最大的积极性。

10.2.5、正确处理好与当地政府及兄弟单位的关系,取得各方面的支持与配合,为施工生产创造一个良好的外部环境。

十一、安全文明保证措施

11.1、机械设备安全保证措施

11.1.1、机械设备操作人员(或驾驶员)必须经过专门训练,熟悉机械操作性能,经专业管理部门考核取得操作证或驾驶证后上机(车)操作。

11.1.2、机械设备操作人员和指挥人员严格遵守安全操作技术规程,工作时集中精力,谨慎工作,不擅离职守,严禁酒后驾驶。

11.1.3、机械设备发生故障后及时检修,决不带故障运行,不违规操作,杜绝机械和车辆事故。

11.1.4、机械操作人员做好各项记录,达到准确、及时,严格贯彻操作制度,认真执行清洁、润滑、坚固、防腐、安全的十字作业法。

11.1.5、设备及工具摆放整齐,不得随意摆放。

11.2、安全文明施工

11.2.1、为避免施工现场的混乱现象,现场文明施工划区域派专人负责,落实

岗位责任制,搞好环境卫生工作。

11.2.2、施工现场必须按施工平面图进行布置,不能随意改变。

11.2.3、工地现场入口设置现场标志牌,明确各区域负责范围,不定期检查和督促。

11.2.4、现场材料进场道路保持畅通无阻,排水畅通,无积水,场地整洁、材料堆放整齐,无施工垃圾。

11.2.5、进入现场施工人员必须佩戴安全帽,讲究文明用语,杜绝打架斗殴,酗酒等不文明行为。

11.2.6、注意工地防火,现场要摆放防火器材。

11.2.7、与当地医疗保健和消防等部门保持密切联系,做到有备无患。 11.2.8、现场必须配足足够的消防设备。


相关文章

  • 深基坑方案
  • 中山路(中环西路-秀洲路)综合整治工程三标段 环城西路倒虹管深基坑及支护专项施工方案 一. 工程概况 (1)工程名称:嘉兴市中山路(中环西路-秀洲路)综合整治工程三标段 (2)工程地点:环城西路 (3)建设单位:嘉兴市城市建设投资有限公司 ...查看


  • 地下综合管廊监理细则
  • 郑州市中心城区地下综合管廊(金水科教园区杨金路首开段)工程 监理实施细则 编 审核人(项目总监): 李之昭 河南省万安工程建设监理有限公司 2016 年 11 月 20 日 制人(专业监理工程师): 李之昭 一.本细则编写依椐 1.1本项目 ...查看


  • 深沟槽开挖专项施工方案
  • 天水市供热公司 亚行贷款城区供热管网敷设工程 王家磨滨河路西延段(KD0+076-KD0+760) 沟槽开挖及钢板桩支护安全专项方案 审批: 日期: 审核: 日期: 编制: 日期 甘肃省安装建设集团公司 二〇一七年三月十五日 目 录 一.工 ...查看


  • 管道工程定向钻施工方案
  • XXXX工程 定 向 钻 施 工 方 案 XXXXX工程有限公司 一.工程概况 本工程为XXXX工程,支管施工工程,位于小榄镇东宝路.乐盛南街上,工程量主要集中在乐盛南街.北街,该支管收集的污水统一流到东宝南路主干管.其工程内容包括: D4 ...查看


  • 广州某引水工程明挖输水管道埋设施工方案_secret
  • 某路明挖输水管道埋设方案 一.概述 广州市某引水工程,需经过某路并排铺设2条DN3600输水钢管,开挖中心距西二环南侧约23.9米.管中线相距5.6m, 沟槽坑底开挖宽度11.8 m(路 三.路面切割 测量人员根据设计管道坐标确定基坑开挖边 ...查看


  • 钢板桩支护方案
  • 南宁市轨道交通2号一期管线横岗双层车辆段主体工程 工程某深基坑拉森钢板桩支护专项施工方案 一.编制依据 1.<横岗双层车辆段排洪渠框架涵与深惠路雨水箱涵排水系统接驳图(1)-(4)>. 2.<建筑基坑工程技术规范>( ...查看


  • 初期雨水池开挖支护方案
  • 目 录 第一章 工程概况----------------------------------------------------1 第二章 编制依据---------------------------------------------- ...查看


  • 沟槽支护施工方案
  • 沟槽开挖支护施工方案 一.编制依据 (1)海口市长流起步区市政道路工程长滨二路(南)设计图纸.招标文件 (2)<给水排水管道工程施工及验收规范> GB50268-2008 (3)<建设工程质量管理条例> (4)< ...查看


  • 格栅池方案
  • 创新家园 格栅沉砂池施工方案 唐镇新市镇E-5-4.E-6-2A地块配套商品房项目室外总体 格栅沉砂池施工方案 第一章:工程概况 唐镇新市镇E-5-4.E-6-2A地块配套商品房项目位于浦东新区创新中路.以齐爱路为界,共分为东西地块.为了确 ...查看


热门内容