佛山市狮山镇博爱湖溢流坝工程

施工组织设计

作者:向洪建 专业班级:水利水电工程113 指导教师:朱林

摘 要:佛山市狮山镇博爱调蓄湖水系整治工程建设内容为:新建博爱调蓄湖、挡水溢流堰一座、补水泵站一座、整治河涌两条、排水闸站两座。狮山镇博爱调蓄湖挡水溢流堰工程为博爱调蓄湖与下游河涌水系建设工程的组成部分;是该工程重要建筑物之一。本工程位于南海区狮山镇,狮山镇西南面为北江,西北面为西南涌。

博爱调蓄湖建设包括湖区约 545 亩的水面及 7.265km 的环岛岸线的建设,新建湖区挡水溢流堰一座、补水泵站一座及补水管线。博爱湖将其建成一个具有雨洪调蓄、生态、景观、休闲功能于一体的生态湖区。

其中挡水溢流堰为新建湖区主要调蓄建筑物。该溢流堰为混凝土结构,地基为淤泥质粘土,采用高压旋喷桩处理;溢流堰下游设消力池、海曼、防冲槽等,地基处理采用土方换填措施;下游两岸混凝土翼墙基础均采用高压旋喷桩。

本设计要求根据设计布置和建筑物结构特征、根据现场地形地质条件、气象水文条件及场内外交通、风水电供应、材料供应条件等,确定导流方案,围堰施工方案,基坑开挖,施工临时设施面积,确定溢流坝工程施工方案,进行施工总布置,编制施工总进度计划,提出资源配置计划,作为指导施工管理的纲领、进行成施工本核算的依据。

本次设计分析现场各种因素对建设施工的影响,研究各种可能的对策和措施,经比选确定采用方案;并对方案进行分析计算,使之技术上可靠,经济上合理。经比较筛选,最后得出博爱湖溢流坝工程施工组织设计的具体内容,并绘制出图纸。

关键词:溢流堰;施工组织设计;条件;施工总进度;施工总布置

THE CONSTRUCTION ORGANIZATION OF BO’AI LAKE

DAM PROJECT IN SHISHAN TOWN FOSHAN CITY Author:Hongjian Xiang Major and Class:Water Conservancy and Hydropower Engineering of Class 113

Instructor:Lin Zhu

Abstract:The aim of Bo’ai lake and water system improvement project in Shishan Town Foshan City is build a new Bo’ai lake,a water retaining weir ,a water pump station,the remediation of two rivers,two drainage sluice stations.The Bo’ai retaining weir lake project in Shishan Town is a part of Bo’ai retaining weir and the downstream river construction works; is one of the important buildings of the project.The project is located in Shishan Town, Nanhai District, Shishan town is located on southwest of North River, northwest of the town is southwest River.

The project including about 545 acres of water surface and 7.265km of shoreline around the island,to build a new retaining a weir lake,a water pump station and water pipeline.The Bo’ai Lake will be a ecological lake system which can maintain rainwater and flood storage, is a ecological lake, landscape, has leisure functions.

The water retaining weir is the main building of the new lake.The water retaining weir is a concrete construction.the base of the weir is sludge clay. Use high-pressure rotary jet grouting pile to process the foundation. In the downstream are stilling pool,the apron, guards against flushes the trough etc.The placement of earth to treat the foundation.The high-pressure rotary jet grouting pile is used to treat the basement of the two sides concrete wing wall.

The design requires the determination of the construction scheme and layout,resource allocation plan,construction schedule according to the designed arrangements,the structure characteristics,the site topography and geological conditions, meteorological hydrological conditions,traffic and wind,water,electricity supplement,and material supply conditions, as the guide of the construction management program and the construction of the accounting basis.

The design analyses the different influences factors on the construction of the building, do research on different policies and measures, by comparison to determine the scheme,calculate the scheme , make the scheme reliable on technology, reasonable on economic.By comparing, and finally get the the specific content of the project, and draw the blueprint.

To work out the diversion scheme, cofferdam construction program, excavation,area of temporary facilities construction.

Keywords: water retaining weir,construction organization, conditions,allocation plan, construction layout

佛山市狮山镇博爱湖溢流坝工程

施工组织设计

作者:向洪建 专业班级:水利水电工程113 指导教师:朱林

摘 要:佛山市狮山镇博爱调蓄湖水系整治工程建设内容为:新建博爱调蓄湖、挡水溢流堰一座、补水泵站一座、整治河涌两条、排水闸站两座。狮山镇博爱调蓄湖挡水溢流堰工程为博爱调蓄湖与下游河涌水系建设工程的组成部分;是该工程重要建筑物之一。本工程位于南海区狮山镇,狮山镇西南面为北江,西北面为西南涌。

博爱调蓄湖建设包括湖区约 545 亩的水面及 7.265km 的环岛岸线的建设,新建湖区挡水溢流堰一座、补水泵站一座及补水管线。博爱湖将其建成一个具有雨洪调蓄、生态、景观、休闲功能于一体的生态湖区。

其中挡水溢流堰为新建湖区主要调蓄建筑物。该溢流堰为混凝土结构,地基为淤泥质粘土,采用高压旋喷桩处理;溢流堰下游设消力池、海曼、防冲槽等,地基处理采用土方换填措施;下游两岸混凝土翼墙基础均采用高压旋喷桩。

本设计要求根据设计布置和建筑物结构特征、根据现场地形地质条件、气象水文条件及场内外交通、风水电供应、材料供应条件等,确定导流方案,围堰施工方案,基坑开挖,施工临时设施面积,确定溢流坝工程施工方案,进行施工总布置,编制施工总进度计划,提出资源配置计划,作为指导施工管理的纲领、进行成施工本核算的依据。

本次设计分析现场各种因素对建设施工的影响,研究各种可能的对策和措施,经比选确定采用方案;并对方案进行分析计算,使之技术上可靠,经济上合理。经比较筛选,最后得出博爱湖溢流坝工程施工组织设计的具体内容,并绘制出图纸。

关键词:溢流堰;施工组织设计;条件;施工总进度;施工总布置

THE CONSTRUCTION ORGANIZATION OF BO’AI LAKE

DAM PROJECT IN SHISHAN TOWN FOSHAN CITY Author:Hongjian Xiang Major and Class:Water Conservancy and Hydropower Engineering of Class 113

Instructor:Lin Zhu

Abstract:The aim of Bo’ai lake and water system improvement project in Shishan Town Foshan City is build a new Bo’ai lake,a water retaining weir ,a water pump station,the remediation of two rivers,two drainage sluice stations.The Bo’ai retaining weir lake project in Shishan Town is a part of Bo’ai retaining weir and the downstream river construction works; is one of the important buildings of the project.The project is located in Shishan Town, Nanhai District, Shishan town is located on southwest of North River, northwest of the town is southwest River.

The project including about 545 acres of water surface and 7.265km of shoreline around the island,to build a new retaining a weir lake,a water pump station and water pipeline.The Bo’ai Lake will be a ecological lake system which can maintain rainwater and flood storage, is a ecological lake, landscape, has leisure functions.

The water retaining weir is the main building of the new lake.The water retaining weir is a concrete construction.the base of the weir is sludge clay. Use high-pressure rotary jet grouting pile to process the foundation. In the downstream are stilling pool,the apron, guards against flushes the trough etc.The placement of earth to treat the foundation.The high-pressure rotary jet grouting pile is used to treat the basement of the two sides concrete wing wall.

The design requires the determination of the construction scheme and layout,resource allocation plan,construction schedule according to the designed arrangements,the structure characteristics,the site topography and geological conditions, meteorological hydrological conditions,traffic and wind,water,electricity supplement,and material supply conditions, as the guide of the construction management program and the construction of the accounting basis.

The design analyses the different influences factors on the construction of the building, do research on different policies and measures, by comparison to determine the scheme,calculate the scheme , make the scheme reliable on technology, reasonable on economic.By comparing, and finally get the the specific content of the project, and draw the blueprint.

To work out the diversion scheme, cofferdam construction program, excavation,area of temporary facilities construction.

Keywords: water retaining weir,construction organization, conditions,allocation plan, construction layout


相关文章

  • 如何通过文献检索浏览器解决cnki中国知网翻译助手的问题
  • 如何通过文献检索浏览器解决cnki中国知网翻译助 手的问题 近来要写个论文,需要下载一些参考文献,但是在中国知网,万方,维普等文献检索网站上只能查看论文摘要,无法下载全文,怎么办呢,于是就开始了百度论文免费全文下载方法的艰苦历程,终于有所收 ...查看


  • 2013届毕业设计工作手册
  • 土 木 工 程 专 业 13 届毕业设计工作手册 长春工程学院 土木工程学院 二 0 一二年十二月 目 录 土木学院 13 届毕业设计工作管理细则 „„„„„„„„„„„„„„„„„„„1 本科生毕业设计(论文)工作条例 附录 1 附录 2 ...查看


  • 2015届毕业设计工作手册 1
  • 土 木 工 程 专 业 2015 届毕业设计工作手册长春工程学院 土木工程学院 二 0 一四年十二月土木工程学院 2015 届毕业设计工作管理细则为了加强毕业设计管理,提高毕业设计质量,根据长春工程学院的<本科生 毕业设计(论文)工作 ...查看


  • 建设工程项目管理方案编制编制指导书
  • 2010级工程管理专业 毕业论文指导书 课 题: 建设工程项目管理方案编制 指导老师:周振国 时 间:2013年12月9日- 2014年6月20日 扬州大学建筑科学与工程学院 二0一三年十二月 <建设工程项目管理方案编制> 毕业 ...查看


  • 修改毕业论文重复率的经典方法以及常用的论文检测系统
  • 修改毕业论文重复率的经典方法以及常用的论文检测系统 我们的建议未必会把您的重复率降低到0,但是至少可以最大程度地降低您的重复率,使您顺利通过学校的论文检测.下面是修改论文重复率的几个经典方法,希望能够帮助您! 修改方法案例分析 例如下句: ...查看


  • 毕业设计扉页.任务书.评阅书.摘要.目录格式
  • 注:纸型:A4 上.下.左.右页边距:2厘米 页眉:1.5厘米 页脚:1.75厘米 装订线:0.5厘米 中国矿业大学 毕业设计格式模板 中 国 矿 业 大 学 本科生毕业设计 姓 名:学 院:专 业:设计题目:专 题:指导教师: 陈亮 学 ...查看


  • [桥梁建设]征稿
  • <桥梁建设>2012征稿须知 <桥梁建设>为中国科技论文统计源期刊.中国科学引文数据库来源期刊.中国学术期刊综合评价数据库统计源期刊.中文核心期刊.中国核心期刊(遴选)数据库收录期刊.中国学术期刊(光盘版)入编期刊, ...查看


  • 医学论文英语摘要的写作及难句翻译
  • 医学论文英语摘要的写作及难句翻译 创新医学网www.yixue360.com [摘要]根据自己在编审医学论文英文摘要工作中的实际经验,总结和归纳在翻译医学论文摘要时应注意的问题及使用的方法.策略,重点论述医学论文英文摘要的写作格式.文章标题 ...查看


  • 论文的标题和摘要
  • 论文的标题和摘要 1 论文的标题(Title,Topic) 标题又称题目或题名.题目是以最恰当.最 简明的词语反映论文中最重要的特定内容的逻辑 组合. 论文题目是一篇论文给出的涉及论文范围与 水平的第一个重要信息,也是必须考虑到有助于 选定 ...查看


热门内容