照明工程施工方案-万安南33路

万安路

照明工程

施工方案

******建设工程有限公司

年 月 日

目 录

第一章 工程概述 ......................................................................................................................................................2

1.1 设计依据及规范 ........................................................................................................................................2

1.2 设计范围 ....................................................................................................................................................2

1.3 供电工程 ....................................................................................................................................................2

1.4 照明工程 ....................................................................................................................................................3

1.5 施工注意事项 ............................................................................................................................................5

第二章 施工安排 ....................................................................................................................................................6

2.1 前期准备 ....................................................................................................................................................6

2.2 人员组织 ....................................................................................................................................................6

2.2.1、工程管理、技术人员配置如下:.......................................................................................................6

2.3 主要设备情况 ............................................................................................................................................7

第三章 施工工艺 ....................................................................................................................................................8

3.1 测量放样 ....................................................................................................................................................8

3.2技术要求 .....................................................................................................................................................8

3.2.2.其他要求 ................................................................................................................................................8

3.4.电缆、导线的选型及敷设 ..........................................................................................................................8

3.5.防雷与接地 .........................................................................................................................................................9

3.6施工方法 .....................................................................................................................................................9

3.6.1管、沟槽开挖方法 .................................................................................................................................9

3.6.2管道铺设 .................................................................................................................................................9

3.6.3照明手孔井及路灯基础施工 ...............................................................................................................10

3.6.4箱式变电站基础施工 ...........................................................................................................................10

第四章 质量保证措施 ..........................................................................................................................................10

4.1 质保体系及质保要求 ...............................................................................................................................10

4.1.1、本工程的质量目标:工程质量,合同履约率100%,分部、分项工程合格率100%。 ...............10

4.2 技术保证措施 .......................................................................................................................................... 11

第五章 工期计划及保证措施 ..............................................................................................................................11

5.1 工期计划 .................................................................................................................................................. 11

5.2 工期保证措施 ..........................................................................................................................................12

第六章 安全、文明及其他保证措施 ..................................................................................................................13

6.1 安全管理总目标 ......................................................................................................................................13

6.2.5、安全生产内业工作 ............................................................................................................................15

6.3 文明施工措施 ..........................................................................................................................................15

第一章 工程概述

1.1 设计依据及规范

1、《城市道路照明设计标准》(CJJ45-2006);

2、《电力工程电缆设计规范》(GB50217-2007);

3、《供电系统设计规范》(GB50052-2009);

4、《低压配电设计规范》(GB 50054-2011);

5、《建筑物防雷设计规范》(GB 50057-2010);

6、《交流电气装置的接地设计规范》(GB/T 50065-2011);

7、《天府新区成都直管区城乡环境综合治理工作领导小组办公室-关于规范成都天府新区部分城市家具主色系的通知》天成管环治办发[2015]26号

1.2 设计范围

本工程设计范围为万安南33路供电照明施工设计,支路:万安南33路(WA33K0+027.050~ WA33 K1+216.203)。

1.3 供电工程

1、负荷等级

道路照明负荷等级按三级负荷设计。

2、照明供电电源及电压

道路照明采用10/0.4kV路灯专用箱式变电站供电,箱变设置在人行道或绿化带内。箱式变电站就近从城市电网引接1路10kV电源供电。10kV供电电缆暂按YJV22-8.7/10kV-3×70电缆直埋敷设考虑,具体由当地供电部门负责实施。

3、供电方式

采用1台10/0.4kV 100kVA箱式变电站,其编号为XB1,供电半径约650m,为本工程道路照明工程用电并考虑一定的裕量;同时设置配电箱AL01~AL05为道路照明进行配电。

箱式变电站内设置10kV高压配电装置1套、设置1台10/0.4kV SCB11型干式变压器(采用D,Yn11接线组别)、设置0.4kV低压配电装置1套和电容补偿1套。照明配电箱内设置路灯控制器1套(含远程控制模块、时控器和照度控制器)。

4、计量方式

本工程计量方式采用低压计量方式。

5、功率因数补偿

为提高用电负荷的功率因数,无功补偿采用集中补偿方式。在箱式变电站低压母线侧设置功率因数自动补偿装置,补偿后的功率因数不小于0.95。

1.4 照明工程

1、照明标准

支路:平均照度10x;总均匀度:0.3;眩光限制:≤15%。

路口交会区照明标准:平均照度20lx/50lx。

2、布灯方式

光源采用高压钠灯,采用半截光型灯具,灯具防护等级IP65。照明灯杆、箱体统一采用标准深灰色(CD-001)。每盏灯具安装可变功率镇流器,250W设置250W/150W, 150W设置150W/100W,100W设置100W/70W。

光源采用高压钠灯,采用半截光型灯具,灯具防护等级IP65,色温不低于2000K,400W高压钠灯光通量不低于48000lm,250W高压钠灯光通量不低于28000lm,100W高压钠灯光通量不低于10000lm,灯杆中心距离路缘石0.5米。照明灯杆、箱体统一采用标准深灰色(CD-001)。每盏灯具安装可变功率镇流器,400W设置400W/250W,250W设置250W/150W,100W设置100W/70W。每套路灯配套设置熔断器(150W及以下为4A,250W为6A,400W为10A)等元器件。

(1)万安南33路

在左右两侧人行道内分别设置一单臂道路灯,光源功率100W 高压钠灯,灯杆高度为10.0m,挑臂1.0m,双侧交错布置,单侧间距约40 m。

(2)较大路口

在较大路口设置投光灯,光源功率2*250W/3*400W高压钠灯,灯杆高度为16.0 m,投光灯应有防雷击保护措施。。

3、控制方式

路灯由安装于箱式变电站内的远程控制模块、时控器和照度控制器进行控制,自动控制采用时钟控制和照度控制,预留远程控制接口。

道路照明采用时控器自动控制,纳入城市统一管理,接入当地路灯远程集中控制系统,可实现光控、时控、远控及手动控制功能。

4.电缆及敷设方式

道路照明采用三相五芯YJLHV22-0.6/1kV低压电缆供电,照明负荷在A、B、C相上平衡分布,灯具引下线采用RVV-500V-3*2.5护套线,照明回路末端电压损失按不大于5%设计。

照明电缆敷设采用直埋敷设方式,敷设于绿化带或人行道下,埋深距地面下0.7米;电缆在穿越道路处采用穿SC100镀锌钢管保护埋地敷设,埋设深度距路面不小于1米,两端伸出道路边0.5米,并在道路两侧设置电缆手孔井。在电缆转弯、过路及每个路灯处设置电缆手孔井,用于拉线、接线。电缆手孔井采用双层检查井盖,下层井盖采用圆形井盖(采用复合材料防盗型),上层采用隐形井盖,其铺装层样式、材质与人行道景观铺装设计一致。

与本工程道路相交的道路上路灯应做好电缆连通设计,保证所有路灯回路能连通,暂不做电器连接。

5、功率密度

经过计算,本次设计中道路的功率密度值如下表所示,满足城市道路照明节能设计标准。

6、节能

(1)严格执行《城市道路照明设计标准》(CJJ45-2006)中对功率密度值的要求;

(2)箱变尽量设置于负荷中心,LED灯做单灯补偿,补充后功率因数不低于0.9;

(3)采用高光效光源、光效灯具及高效的灯具附件(节能型电源模块);

(4)配置变功率整流器,深夜自动降低照明功率,节约能耗;

(5)单相照明负荷尽可能的均匀平衡到三相负荷中,减少损耗;

(6)选用绿色、环保的经国家认证的电气产品。

7、防雷及接地

(1)防雷

箱式变电站高压侧设置避雷器,低压侧设置浪涌保护器,用于防雷保护。

(2)接地

本工程接地型式采用TN-S系统,每个箱式变电站处设置接地网,接地电阻不大于4欧姆;沿道路照明回路通长埋设一根φ10热镀锌圆钢作为道路照明灯具及灯杆接地干线,接地干线与箱变接地网可靠焊接并与路灯基础地脚螺栓焊接接地;在箱变供电范围的中部和末端分别设置接地极组,要求接地干线综合接地电阻不大于4欧姆,否则须采取相应措施(如补打接地极、降阻剂等)直至满足要求。

箱式变电站金属外壳、金属底座以及预埋钢管、铠装电缆的金属保护层、φ10热镀锌圆钢均应与接地网可靠焊接接地。

8、防盗

(1)照明供电线路的电缆井井盖及人孔井井盖、照明灯杆的检修门、箱变及路灯户外配电箱,均应设置需使用专用工具开启的闭锁防盗装置,防盗装置方式及规格需与主管部门协调,以便今后维护管理。

(2)电缆线路采用尼龙绑扎带每隔两米和接地圆钢牢固绑扎一次。

1.5 施工注意事项

1、灯具、灯杆安装时,应保证固定及接地可靠,漆层完整、整洁。灯具内所装电器元件应齐全完好,安装位置正确,固定牢固。灯杆焊接完成后,必须采用专用设备进行调直处理,以保证灯杆直线度在千分之一以内。所有接线准确,连接可靠,标志齐全清楚,绝缘符合要求。

2、电缆及电缆保护管施工时,所有预埋管线要求敷设平直,管内无异物,接口应衔接牢固、防水。电缆在敷设时不能损伤外层绝缘,放电缆时拉力不能超过电缆允许的最大拉力,电缆及电缆保护管弯曲半径均应符合现行国家颁布的各项标准。电缆管道安装完成后,应作好封堵。

3、接地线焊接均采用搭接,搭接长度为圆钢直径的6倍,焊接应饱满牢固,不应有夹渣虚焊、咬肉、气孔及未焊透现象。

4、管道铺设完毕后要进行试通,并穿φ3mm钢丝,要采取妥当措施防止钢丝缩入管中,管口应用专用的管堵封堵,防止异物进入管中。

5、管道工程采用的混凝土、钢筋、砂浆、预制构件和混凝土拌制材料应符合《公路桥涵施工技术规范》JTG/T F50-2011的有关规定。

6、管道工程的回填,应在该项工程施工工序全部完成后,先清除沟(坑)内的遗留木料、草帘、纸袋等杂物,并经隐蔽工程检验合格后进行,管道回填采用中粗砂,不得含有直径大于5cm的砾石、碎砖等坚硬物。管道两侧应同时进行回填,每层回填中粗砂厚不得超过15cm,并夯实,回填土质量按路基要求,并分层夯实。

7、道路灯施工完毕,灯杆基础地脚螺栓需作水泥包封。

第二章 施工安排

2.1 前期准备

施工前充分做好各项准备工作,包括控制测量工作;原材料检验,砂浆、砼配合比设计;钢筋加工场地的建设;施工用水;电力供应;道路交通疏解;管线调查;施工材料等统筹安排;进场人员安全教育等确保满足施工需要。

2.2 人员组织

根据合同要求和我部总体施工计划,为顺利完成市政地面管线工程,我公司组织具有丰富施工和管理经验的工程技术人员担任项目主管和技术主管,并组织技术过硬、操作熟练的现场技术人员和进行监督作业。

2.2.1、工程管理、技术人员配置如下:

2.2.2、其他人员配置:将根据实际情况,合理调配,及时安排,以满足施工需要。

2.3 主要设备情况

主要机械设备一览表

施工仪器及试验仪器一览表

第三章 施工工艺

3.1 测量放样

根据设计院提供疏港道路工程地下管线探测成果报告资料及项目部实际地下管线探摸结果报告,利用全站仪,根据设计院给导线点以及监理批复加密的控制点成果,将管线中线、标高测量放样,并用木桩做好标识,做好保护工作。

3.2技术要求

3.2.1灯具

(1)万安南12路:机动车道双侧交错布置,采用单挑半截光路灯,灯高10米,1x150W高压钠灯,杆间距30米。

(2)交叉路口:单侧布置,采用中杆灯,杆高16米,3×250W高压钠灯。

3.2.2.其他要求

路灯基础施工时,如遇给水、电信、电力等支管时,基础位置可进行适当调整。

3.3. 照明控制:

(1)由配电箱内路灯节电器自控(路灯控制仪)或手动控制路灯起,闭,采用光控、程控、时间控制等控制方式;远期安装路灯处专制的遥控仪进行遥控遥测。

(2)整个区域内的路段远期采用集中控制方式,纳入城市统一控制,近期采用照明配电箱分散控制。

(3)灯杆及基础:

灯杆采用热镀锌喷塑,其镀锌层厚度≥70μm,锥度12/1000,灯杆高度12米以下灯杆厚度≥4mm、12米以上灯杆厚度≥6mm。灯杆焊接质量应符合有关规范要求。

(4)照明供电线路的人孔井盖及手孔井盖、照明灯杆的检修门及路灯户外配电箱,均应设置成都市路灯专用磁性防盗锁。

3.4.电缆、导线的选型及敷设

(1)高压电缆选用YJV22-8.7/15kV电力电缆;配电干线采用YJHLV22-0.6/1KV电力电缆,灯具内支线采用RVV-0.45/0.75kV电线。

(2)YJHLV22-0.6/1KV电力电缆直埋敷设,电缆埋深0.7m;施工详施工图及08D800-7/P13~30。埋地敷设的电缆严禁平行敷设于地下管道的正上方或下方。

电缆与电缆及各种设施平行或交叉最小净距离应满足《民用建筑电气设计规范》 JGJ/T 16-2008 表8.7.2的要求。电缆通过道路应穿钢管保护,保护管的内径不应小于电缆外径的1. 5倍。

3.5.防雷与接地

(1)配电系统接地形式采用 TN-S系统。沿线路通长敷设Φ10圆钢作为接地线并和路灯灯杆基础连接,并在每回路末端作重复接地,接地电阻不大于4Ω。箱式变电站处工作接地与保护接地、防雷接地共用一组接地极,要求接地电阻不大于4Ω。箱变内采用TN—S系统,接地电阻不大于4Ω。

(2)配电柜金属外壳须可靠接地,要求接地电阻不大于4Ω。

(3)灯杆避雷装置由供应商按三类防雷要求配置;灯杆金属外露件与接地极用-40×4热镀锌扁钢跨接,要求接地电阻不大于4Ω,当灯杆基础接地电阻不满足要求时,另加人工接地极。

4)配电箱接地极:采用50×5长为2.5m的角钢,采用-40×4热镀锌扁钢跨接形成接地网。

3.6施工方法

3.6.1管、沟槽开挖方法

照明管线在绿化带中用YJV交联铜芯电缆穿塑料管保护敷设,覆土厚度不小于0.5米,敷设时注意避开行道树。过街部分采用穿钢管保护,过街部分覆土深度不小于0.7米,照明保护管埋深在0.8米左右。

沟槽开挖放坡1:0.33,开挖时先进行测量定位,抄平放线,定出开挖宽度,按放线分段施工。沟槽开挖采用人工开挖,开挖时应控制开挖断面将槽帮挖出,槽帮边坡应不陡于规定坡度,检查时可用坡度尺检验,外观检查不能有亏损、鼓胀现象,表面应平顺。槽底土壤严禁扰动,挖槽在接近槽底时,要加强测量,注意清底,不要超挖。

路灯基础施工时,如遇给水、电信、电力等支管时,基础进行适当的位移。

3.6.2管道铺设

箱变进出线电缆埋管,根据实际方向进行预埋,保护管的埋设数量应考虑用回路。

电缆过街穿钢管保护,管端伸出500~1000,管端用麻丝沥青油封口,电缆

保护板采用150#混凝土制作,板厚35mm。

3.6.3照明手孔井及路灯基础施工

1、井身用75#机砖砌成,内壁1:2水泥砂浆抹面,厚度10mm;

2、盖板采用C20混凝土,Ⅰ级钢筋,双向配筋6@φ150;

3、井底采用手摆块石灌砂,设1%坡度,以免管内积水;

4、垫层采用细砂夯实;

5、路灯基础砼为C25钢筋砼,钢筋保护层厚度不小于50mm;

6、基础栓应与厂家配合做好预埋工作;

7、路灯基底应夯实,压实系数不小于0.85;

8、基坑回填每回填300mm夯实一次,压实系数不小于0.8。

3.6.4箱式变电站基础施工

基坑用C20、S6混凝土浇筑,面层采用1:2水泥砂浆抹平,最薄处厚20mm,按1%坡度向外找坡,表面适当设置导水坑,避免大量积水流进电缆沟,基坑必须落在粘土层上、环境地势较高处;

第四章 质量保证措施

4.1 质保体系及质保要求

4.1.1、本工程的质量目标:工程质量,合同履约率100%,分部、分项工程合格率100%。

4.1.2、建立行之有效的质量管理体系,通过对总体质量目标的合理分解,通过过程管理,实现过程精品,以确保实现总体质量目标。

4.1.3、结合我公司质量目标:单位工程、分部、分项工程合格率100%。,顾客满意率≥90%,返工损失率≤0.5‰,创局优,争创省部优。

4.1.4、为确保工程质量目标的实现,公司按GB/T19002:1994—ISO9002:1994标准建立质量保证体系,并持续保持有效性。

4.1.5、在施工过程中认真加强施工技术管理和质量管理。全体管理人员必须严格执行国家和地方各级政府部门颁发的各项规范、规程和标准,严格执行本公司制定质量程序文件(包括各项技术管理和质量管理制度),严格履行自己的岗位责任制和质量责任制,树“百年大计,质量第一”、“质量是企业的生命”、

“以质量求效益,以质量求信誉,以质量求发展”的思想,树立牢固的质量意识,实现工程质量合同目标。

4.2 技术保证措施

4.2.1、推行全面质量管理,广泛开展QC小组活动。对关键工程,组织专家攻关。贯彻ISO9002国际质量标准体系,编制项目《质量计划》,实行标准化作业。

4.2.2、加强计量、测量、试验工作;严格控制混凝土的配合比;试验室配备足够的试验设备,并随工程进展及时进行试验检验工作。

4.2.3、严格把好材料关。本工程所需的原材料、设备一律从正规厂家购进,只采用通过国家认证合格的产品或建设单位推荐使用的合格产品。地产材料的品质符合国家现行标准。材料进场后经工地试验室进行复检实验合格后使用,不合格材料坚决不用。

4.2.4、混凝土先按设计标号的要求做好配合比实验,拌和前石料用水清洗,严格控制砂、石用量,含泥量和水灰比,保证混凝土和易性,增加振捣的密实度,对接头部位要采用凿毛清洗的措施,保证混凝土的整体性和强度达到要求。

4.2.5、施工过程中认真积累、整理内业及原始施工资料,做到准确、详实、工整,使工程质量检验资料统一规范化,符合工程档案资料立卷归档要求。

第五章 工期计划及保证措施

5.1 工期计划

1、施工准备:包括控制测量工作;原材料检验,砂浆、砼配合比设计;施工用水;电力供应;道路交通疏解;管线调查;施工材料等工作,计划为半个月,即从2012年8月1日始至2012年8月15日止。

2、沟槽开挖:计划从2012年8月16日始至2013年1月16日止。

3、混凝土垫层:计划从2012年8月18日始至2013年1月18日止。

4、安管:计划从2012年8月20日始至2013年1月20日止。

5、手孔井:计划从2012年8月25日始至2013年1月25日止。

6、沟槽回填砂、土:计划从2012年8月28日始至2013年1月28日止。

7、路灯基座:计划从2012年9月28日始至2013年1月28日止。

8、灯杆、灯具安装:计划从2012年10月1日始至2013年1月31日止。 照明工程安排施工工期为180天完成。具体施工进度安排见下表

照明工程施工横道图

5.2 工期保证措施

5.2.1、坚持定期召开由施工负责人主持,各专业工程施工负责人参加的工程施工协调会议,听取关于工程施工进度问题的汇报,协调工程施工外部关系,解决工程施工内部矛盾,对其中有关施工进度的问题,提出明确的计划调整意见。

5.2.2、提前为下道工序的施工,做好人力、物力和机械设备的准备,确保工程一环扣一环地紧凑进行。对于影响工程施工总进度的关键项目、关键工序,主要领导和有关管理人员必须跟班作业,必要时组织有效力量,加班加点突破难点,以确保工程进度计划的实现。

5.2.3、按施工方案的要求配备足够的机械设备和施工机具,及时做好机械设备的保养和维修工作。

5.2.4、采用技术熟练、责任心强的人员负责各工种的管理,并保证施工强度所要求的施工人数。

5.2.5、有节奏、有重点地组织各分部分项工程施工,尽量组织流水作业,避免出现窝工现象,努力降低施工成本。

5.2.6、充分利用无雨天气,集中力量快速施工。工程施工因雨而耽搁的进度,雨后增派力量及时挽回。

5.2.7、材料后勤供应及时、杜绝停工待料现象。

5.2.8、严抓工程质量,杜绝返工。

第六章 安全、文明及其他保证措施

6.1 安全管理总目标

6.1.1、目标

1、重大因工死亡责任事故为0,死亡率为0;

2、因工重伤责任事故为0,因工轻伤责任事故≤2‰;

3、重大交通责任事故为0;

4、火灾责任事故为0;

5、杜绝因管理不善、施工方法不当而造成的机械设备、爆炸、中毒等重大事故。

6.1.2、在施工的过程中,要坚持公司历来的“安全第一,预防为主”的方针,严格执行国务院、部、省、市的安全法规、规范,搞好安全教育与培训,强化员工的安全意识;保证安全专管人员的权威性,保证合理的安全投入,从制度上、组织上、技术上、投入上多管齐下,狠抓施工安全管理。

6.2 安全生产保证措施

1、现场所有作业人员、行政管理、参观、检查、监理工程师人员,进入现场必须戴好安全帽外,登高者必须系好安全带;特种作业人员必须持上岗证作 业;各工序施工中要有严格的安全技术交底。

2、建立电器安全管理和经济责任制度。安质科配一名专职电器工程师负责电器采购、安装和安全工作。专职安全员负责巡视监督检查,专业电工在专管部门的领导下,负责施工现场的电器安全。

3、由专业人员独立编制施工用电组织设计、供电方式、配电装置的设置及其配电容量,供配电线路的走向和现场照明的设置及生活设施的用电负荷情况,编制有针对性的电器安全技术规范。

4、施工现场装备行业统一规定的标准电源箱。电器线路和用电设备安装完成后,由专业管理部门验收合格后方可运行操作。

5、经常对用设备用电设备进行安全检查、测试,每周一次测试漏电开关和接地电阻并有书面记录,发现问题,及时整改。

6、机械设备操作人员(或驾驶员)经过专门训练,经考试取得操作证或驾 驶执照后方可上机(车)。

7、机械操作人员和指挥人员严格遵守安全操作技术规程,工作时集中注意力,谨慎工作,不擅离职守,不酒后驾车。

8、机械设备发生故障后及时检修,严禁带故障运行。

9、机械操作人员严格贯彻例保制度,认真执行清洁、润滑、紧固、防腐、安全的十字作业法。

10、物资部设物资配件仓库,统一对物资进行管理,按照材料的储存要求修建具备相应功能的仓库,做到分门别类储放。

11、仓库设专人负责保管、看护,值班室内设报警系统,随时与派出所和消防部门取得联系。

6.2.5、安全生产内业工作

安全生产“七图二牌”必须上墙。七图即:①施工总平面图;②安全网络图;③电路平面布置图;④管线分布图;⑤临时排水走向图;⑥消防器材布置图;⑦工程进度形象图。二牌即:①无重大伤亡事故累计天数牌;②百日无事故累计天数牌。现场布置安全生产标语和警示牌,做到无违章现象发生。

6.3 文明施工措施

6.3.1、加强现场管理和对全体施工人员的文明教育管理工作,做到紧张有序,文明礼貌,团结协作,刻苦顽强,遵纪守法。

6.3.2、设置宣传标语和标牌,增强环保意识。

6.3.3、车辆不准带泥土出现场,如有泥砂带入场外道路,要及时清扫处理,绝不影响市容环境。

6.3.4、合理规划施工现场,将生产、生活区分开设置。

6.3.5、服从建设单位的管理。

6.3.6、搞好驻地周围的环境卫生,保持良好的生活环境。

6.5 环境保护措施

6.5.1、认真学习地方政府有关环境保护、水利设施保护、文物保护、防止水土流失、施工现场管理等规定和文件,制定相应的措施和办法,并贯穿于施工全过程。

6.5.2、将文明施工与环境保护管理纳入常规施工管理,安排专人负责,对用于工程的各种材料机具设备摆放整齐有序,并设立标志,防、排水设施齐全,性能良好,保持工地整洁。

6.5.3、对于临时用地,不乱取弃土,合理规划,珍惜每一寸土地。施工中认真

做好防护工程,防止水土流失。

6.5.4、随着工程进度的推进,及时清理施工现场,施工废水用汽车清理出场外,不随意排放,尽量维持现有渠道、道路畅通、保护生态平衡。

6.5.5、采取有效措施控制现场的各种粉尘、废气、污水、固体垃圾及噪声震动对环境的污染和危害,不在现场燃烧各种有毒的物质。

6.5.6、工程施工过程中及时清理各种垃圾、废油、废渣,及时处理废气。

6.5.7、运输道路经常洒水,避免扬尘。

万安路

照明工程

施工方案

******建设工程有限公司

年 月 日

目 录

第一章 工程概述 ......................................................................................................................................................2

1.1 设计依据及规范 ........................................................................................................................................2

1.2 设计范围 ....................................................................................................................................................2

1.3 供电工程 ....................................................................................................................................................2

1.4 照明工程 ....................................................................................................................................................3

1.5 施工注意事项 ............................................................................................................................................5

第二章 施工安排 ....................................................................................................................................................6

2.1 前期准备 ....................................................................................................................................................6

2.2 人员组织 ....................................................................................................................................................6

2.2.1、工程管理、技术人员配置如下:.......................................................................................................6

2.3 主要设备情况 ............................................................................................................................................7

第三章 施工工艺 ....................................................................................................................................................8

3.1 测量放样 ....................................................................................................................................................8

3.2技术要求 .....................................................................................................................................................8

3.2.2.其他要求 ................................................................................................................................................8

3.4.电缆、导线的选型及敷设 ..........................................................................................................................8

3.5.防雷与接地 .........................................................................................................................................................9

3.6施工方法 .....................................................................................................................................................9

3.6.1管、沟槽开挖方法 .................................................................................................................................9

3.6.2管道铺设 .................................................................................................................................................9

3.6.3照明手孔井及路灯基础施工 ...............................................................................................................10

3.6.4箱式变电站基础施工 ...........................................................................................................................10

第四章 质量保证措施 ..........................................................................................................................................10

4.1 质保体系及质保要求 ...............................................................................................................................10

4.1.1、本工程的质量目标:工程质量,合同履约率100%,分部、分项工程合格率100%。 ...............10

4.2 技术保证措施 .......................................................................................................................................... 11

第五章 工期计划及保证措施 ..............................................................................................................................11

5.1 工期计划 .................................................................................................................................................. 11

5.2 工期保证措施 ..........................................................................................................................................12

第六章 安全、文明及其他保证措施 ..................................................................................................................13

6.1 安全管理总目标 ......................................................................................................................................13

6.2.5、安全生产内业工作 ............................................................................................................................15

6.3 文明施工措施 ..........................................................................................................................................15

第一章 工程概述

1.1 设计依据及规范

1、《城市道路照明设计标准》(CJJ45-2006);

2、《电力工程电缆设计规范》(GB50217-2007);

3、《供电系统设计规范》(GB50052-2009);

4、《低压配电设计规范》(GB 50054-2011);

5、《建筑物防雷设计规范》(GB 50057-2010);

6、《交流电气装置的接地设计规范》(GB/T 50065-2011);

7、《天府新区成都直管区城乡环境综合治理工作领导小组办公室-关于规范成都天府新区部分城市家具主色系的通知》天成管环治办发[2015]26号

1.2 设计范围

本工程设计范围为万安南33路供电照明施工设计,支路:万安南33路(WA33K0+027.050~ WA33 K1+216.203)。

1.3 供电工程

1、负荷等级

道路照明负荷等级按三级负荷设计。

2、照明供电电源及电压

道路照明采用10/0.4kV路灯专用箱式变电站供电,箱变设置在人行道或绿化带内。箱式变电站就近从城市电网引接1路10kV电源供电。10kV供电电缆暂按YJV22-8.7/10kV-3×70电缆直埋敷设考虑,具体由当地供电部门负责实施。

3、供电方式

采用1台10/0.4kV 100kVA箱式变电站,其编号为XB1,供电半径约650m,为本工程道路照明工程用电并考虑一定的裕量;同时设置配电箱AL01~AL05为道路照明进行配电。

箱式变电站内设置10kV高压配电装置1套、设置1台10/0.4kV SCB11型干式变压器(采用D,Yn11接线组别)、设置0.4kV低压配电装置1套和电容补偿1套。照明配电箱内设置路灯控制器1套(含远程控制模块、时控器和照度控制器)。

4、计量方式

本工程计量方式采用低压计量方式。

5、功率因数补偿

为提高用电负荷的功率因数,无功补偿采用集中补偿方式。在箱式变电站低压母线侧设置功率因数自动补偿装置,补偿后的功率因数不小于0.95。

1.4 照明工程

1、照明标准

支路:平均照度10x;总均匀度:0.3;眩光限制:≤15%。

路口交会区照明标准:平均照度20lx/50lx。

2、布灯方式

光源采用高压钠灯,采用半截光型灯具,灯具防护等级IP65。照明灯杆、箱体统一采用标准深灰色(CD-001)。每盏灯具安装可变功率镇流器,250W设置250W/150W, 150W设置150W/100W,100W设置100W/70W。

光源采用高压钠灯,采用半截光型灯具,灯具防护等级IP65,色温不低于2000K,400W高压钠灯光通量不低于48000lm,250W高压钠灯光通量不低于28000lm,100W高压钠灯光通量不低于10000lm,灯杆中心距离路缘石0.5米。照明灯杆、箱体统一采用标准深灰色(CD-001)。每盏灯具安装可变功率镇流器,400W设置400W/250W,250W设置250W/150W,100W设置100W/70W。每套路灯配套设置熔断器(150W及以下为4A,250W为6A,400W为10A)等元器件。

(1)万安南33路

在左右两侧人行道内分别设置一单臂道路灯,光源功率100W 高压钠灯,灯杆高度为10.0m,挑臂1.0m,双侧交错布置,单侧间距约40 m。

(2)较大路口

在较大路口设置投光灯,光源功率2*250W/3*400W高压钠灯,灯杆高度为16.0 m,投光灯应有防雷击保护措施。。

3、控制方式

路灯由安装于箱式变电站内的远程控制模块、时控器和照度控制器进行控制,自动控制采用时钟控制和照度控制,预留远程控制接口。

道路照明采用时控器自动控制,纳入城市统一管理,接入当地路灯远程集中控制系统,可实现光控、时控、远控及手动控制功能。

4.电缆及敷设方式

道路照明采用三相五芯YJLHV22-0.6/1kV低压电缆供电,照明负荷在A、B、C相上平衡分布,灯具引下线采用RVV-500V-3*2.5护套线,照明回路末端电压损失按不大于5%设计。

照明电缆敷设采用直埋敷设方式,敷设于绿化带或人行道下,埋深距地面下0.7米;电缆在穿越道路处采用穿SC100镀锌钢管保护埋地敷设,埋设深度距路面不小于1米,两端伸出道路边0.5米,并在道路两侧设置电缆手孔井。在电缆转弯、过路及每个路灯处设置电缆手孔井,用于拉线、接线。电缆手孔井采用双层检查井盖,下层井盖采用圆形井盖(采用复合材料防盗型),上层采用隐形井盖,其铺装层样式、材质与人行道景观铺装设计一致。

与本工程道路相交的道路上路灯应做好电缆连通设计,保证所有路灯回路能连通,暂不做电器连接。

5、功率密度

经过计算,本次设计中道路的功率密度值如下表所示,满足城市道路照明节能设计标准。

6、节能

(1)严格执行《城市道路照明设计标准》(CJJ45-2006)中对功率密度值的要求;

(2)箱变尽量设置于负荷中心,LED灯做单灯补偿,补充后功率因数不低于0.9;

(3)采用高光效光源、光效灯具及高效的灯具附件(节能型电源模块);

(4)配置变功率整流器,深夜自动降低照明功率,节约能耗;

(5)单相照明负荷尽可能的均匀平衡到三相负荷中,减少损耗;

(6)选用绿色、环保的经国家认证的电气产品。

7、防雷及接地

(1)防雷

箱式变电站高压侧设置避雷器,低压侧设置浪涌保护器,用于防雷保护。

(2)接地

本工程接地型式采用TN-S系统,每个箱式变电站处设置接地网,接地电阻不大于4欧姆;沿道路照明回路通长埋设一根φ10热镀锌圆钢作为道路照明灯具及灯杆接地干线,接地干线与箱变接地网可靠焊接并与路灯基础地脚螺栓焊接接地;在箱变供电范围的中部和末端分别设置接地极组,要求接地干线综合接地电阻不大于4欧姆,否则须采取相应措施(如补打接地极、降阻剂等)直至满足要求。

箱式变电站金属外壳、金属底座以及预埋钢管、铠装电缆的金属保护层、φ10热镀锌圆钢均应与接地网可靠焊接接地。

8、防盗

(1)照明供电线路的电缆井井盖及人孔井井盖、照明灯杆的检修门、箱变及路灯户外配电箱,均应设置需使用专用工具开启的闭锁防盗装置,防盗装置方式及规格需与主管部门协调,以便今后维护管理。

(2)电缆线路采用尼龙绑扎带每隔两米和接地圆钢牢固绑扎一次。

1.5 施工注意事项

1、灯具、灯杆安装时,应保证固定及接地可靠,漆层完整、整洁。灯具内所装电器元件应齐全完好,安装位置正确,固定牢固。灯杆焊接完成后,必须采用专用设备进行调直处理,以保证灯杆直线度在千分之一以内。所有接线准确,连接可靠,标志齐全清楚,绝缘符合要求。

2、电缆及电缆保护管施工时,所有预埋管线要求敷设平直,管内无异物,接口应衔接牢固、防水。电缆在敷设时不能损伤外层绝缘,放电缆时拉力不能超过电缆允许的最大拉力,电缆及电缆保护管弯曲半径均应符合现行国家颁布的各项标准。电缆管道安装完成后,应作好封堵。

3、接地线焊接均采用搭接,搭接长度为圆钢直径的6倍,焊接应饱满牢固,不应有夹渣虚焊、咬肉、气孔及未焊透现象。

4、管道铺设完毕后要进行试通,并穿φ3mm钢丝,要采取妥当措施防止钢丝缩入管中,管口应用专用的管堵封堵,防止异物进入管中。

5、管道工程采用的混凝土、钢筋、砂浆、预制构件和混凝土拌制材料应符合《公路桥涵施工技术规范》JTG/T F50-2011的有关规定。

6、管道工程的回填,应在该项工程施工工序全部完成后,先清除沟(坑)内的遗留木料、草帘、纸袋等杂物,并经隐蔽工程检验合格后进行,管道回填采用中粗砂,不得含有直径大于5cm的砾石、碎砖等坚硬物。管道两侧应同时进行回填,每层回填中粗砂厚不得超过15cm,并夯实,回填土质量按路基要求,并分层夯实。

7、道路灯施工完毕,灯杆基础地脚螺栓需作水泥包封。

第二章 施工安排

2.1 前期准备

施工前充分做好各项准备工作,包括控制测量工作;原材料检验,砂浆、砼配合比设计;钢筋加工场地的建设;施工用水;电力供应;道路交通疏解;管线调查;施工材料等统筹安排;进场人员安全教育等确保满足施工需要。

2.2 人员组织

根据合同要求和我部总体施工计划,为顺利完成市政地面管线工程,我公司组织具有丰富施工和管理经验的工程技术人员担任项目主管和技术主管,并组织技术过硬、操作熟练的现场技术人员和进行监督作业。

2.2.1、工程管理、技术人员配置如下:

2.2.2、其他人员配置:将根据实际情况,合理调配,及时安排,以满足施工需要。

2.3 主要设备情况

主要机械设备一览表

施工仪器及试验仪器一览表

第三章 施工工艺

3.1 测量放样

根据设计院提供疏港道路工程地下管线探测成果报告资料及项目部实际地下管线探摸结果报告,利用全站仪,根据设计院给导线点以及监理批复加密的控制点成果,将管线中线、标高测量放样,并用木桩做好标识,做好保护工作。

3.2技术要求

3.2.1灯具

(1)万安南12路:机动车道双侧交错布置,采用单挑半截光路灯,灯高10米,1x150W高压钠灯,杆间距30米。

(2)交叉路口:单侧布置,采用中杆灯,杆高16米,3×250W高压钠灯。

3.2.2.其他要求

路灯基础施工时,如遇给水、电信、电力等支管时,基础位置可进行适当调整。

3.3. 照明控制:

(1)由配电箱内路灯节电器自控(路灯控制仪)或手动控制路灯起,闭,采用光控、程控、时间控制等控制方式;远期安装路灯处专制的遥控仪进行遥控遥测。

(2)整个区域内的路段远期采用集中控制方式,纳入城市统一控制,近期采用照明配电箱分散控制。

(3)灯杆及基础:

灯杆采用热镀锌喷塑,其镀锌层厚度≥70μm,锥度12/1000,灯杆高度12米以下灯杆厚度≥4mm、12米以上灯杆厚度≥6mm。灯杆焊接质量应符合有关规范要求。

(4)照明供电线路的人孔井盖及手孔井盖、照明灯杆的检修门及路灯户外配电箱,均应设置成都市路灯专用磁性防盗锁。

3.4.电缆、导线的选型及敷设

(1)高压电缆选用YJV22-8.7/15kV电力电缆;配电干线采用YJHLV22-0.6/1KV电力电缆,灯具内支线采用RVV-0.45/0.75kV电线。

(2)YJHLV22-0.6/1KV电力电缆直埋敷设,电缆埋深0.7m;施工详施工图及08D800-7/P13~30。埋地敷设的电缆严禁平行敷设于地下管道的正上方或下方。

电缆与电缆及各种设施平行或交叉最小净距离应满足《民用建筑电气设计规范》 JGJ/T 16-2008 表8.7.2的要求。电缆通过道路应穿钢管保护,保护管的内径不应小于电缆外径的1. 5倍。

3.5.防雷与接地

(1)配电系统接地形式采用 TN-S系统。沿线路通长敷设Φ10圆钢作为接地线并和路灯灯杆基础连接,并在每回路末端作重复接地,接地电阻不大于4Ω。箱式变电站处工作接地与保护接地、防雷接地共用一组接地极,要求接地电阻不大于4Ω。箱变内采用TN—S系统,接地电阻不大于4Ω。

(2)配电柜金属外壳须可靠接地,要求接地电阻不大于4Ω。

(3)灯杆避雷装置由供应商按三类防雷要求配置;灯杆金属外露件与接地极用-40×4热镀锌扁钢跨接,要求接地电阻不大于4Ω,当灯杆基础接地电阻不满足要求时,另加人工接地极。

4)配电箱接地极:采用50×5长为2.5m的角钢,采用-40×4热镀锌扁钢跨接形成接地网。

3.6施工方法

3.6.1管、沟槽开挖方法

照明管线在绿化带中用YJV交联铜芯电缆穿塑料管保护敷设,覆土厚度不小于0.5米,敷设时注意避开行道树。过街部分采用穿钢管保护,过街部分覆土深度不小于0.7米,照明保护管埋深在0.8米左右。

沟槽开挖放坡1:0.33,开挖时先进行测量定位,抄平放线,定出开挖宽度,按放线分段施工。沟槽开挖采用人工开挖,开挖时应控制开挖断面将槽帮挖出,槽帮边坡应不陡于规定坡度,检查时可用坡度尺检验,外观检查不能有亏损、鼓胀现象,表面应平顺。槽底土壤严禁扰动,挖槽在接近槽底时,要加强测量,注意清底,不要超挖。

路灯基础施工时,如遇给水、电信、电力等支管时,基础进行适当的位移。

3.6.2管道铺设

箱变进出线电缆埋管,根据实际方向进行预埋,保护管的埋设数量应考虑用回路。

电缆过街穿钢管保护,管端伸出500~1000,管端用麻丝沥青油封口,电缆

保护板采用150#混凝土制作,板厚35mm。

3.6.3照明手孔井及路灯基础施工

1、井身用75#机砖砌成,内壁1:2水泥砂浆抹面,厚度10mm;

2、盖板采用C20混凝土,Ⅰ级钢筋,双向配筋6@φ150;

3、井底采用手摆块石灌砂,设1%坡度,以免管内积水;

4、垫层采用细砂夯实;

5、路灯基础砼为C25钢筋砼,钢筋保护层厚度不小于50mm;

6、基础栓应与厂家配合做好预埋工作;

7、路灯基底应夯实,压实系数不小于0.85;

8、基坑回填每回填300mm夯实一次,压实系数不小于0.8。

3.6.4箱式变电站基础施工

基坑用C20、S6混凝土浇筑,面层采用1:2水泥砂浆抹平,最薄处厚20mm,按1%坡度向外找坡,表面适当设置导水坑,避免大量积水流进电缆沟,基坑必须落在粘土层上、环境地势较高处;

第四章 质量保证措施

4.1 质保体系及质保要求

4.1.1、本工程的质量目标:工程质量,合同履约率100%,分部、分项工程合格率100%。

4.1.2、建立行之有效的质量管理体系,通过对总体质量目标的合理分解,通过过程管理,实现过程精品,以确保实现总体质量目标。

4.1.3、结合我公司质量目标:单位工程、分部、分项工程合格率100%。,顾客满意率≥90%,返工损失率≤0.5‰,创局优,争创省部优。

4.1.4、为确保工程质量目标的实现,公司按GB/T19002:1994—ISO9002:1994标准建立质量保证体系,并持续保持有效性。

4.1.5、在施工过程中认真加强施工技术管理和质量管理。全体管理人员必须严格执行国家和地方各级政府部门颁发的各项规范、规程和标准,严格执行本公司制定质量程序文件(包括各项技术管理和质量管理制度),严格履行自己的岗位责任制和质量责任制,树“百年大计,质量第一”、“质量是企业的生命”、

“以质量求效益,以质量求信誉,以质量求发展”的思想,树立牢固的质量意识,实现工程质量合同目标。

4.2 技术保证措施

4.2.1、推行全面质量管理,广泛开展QC小组活动。对关键工程,组织专家攻关。贯彻ISO9002国际质量标准体系,编制项目《质量计划》,实行标准化作业。

4.2.2、加强计量、测量、试验工作;严格控制混凝土的配合比;试验室配备足够的试验设备,并随工程进展及时进行试验检验工作。

4.2.3、严格把好材料关。本工程所需的原材料、设备一律从正规厂家购进,只采用通过国家认证合格的产品或建设单位推荐使用的合格产品。地产材料的品质符合国家现行标准。材料进场后经工地试验室进行复检实验合格后使用,不合格材料坚决不用。

4.2.4、混凝土先按设计标号的要求做好配合比实验,拌和前石料用水清洗,严格控制砂、石用量,含泥量和水灰比,保证混凝土和易性,增加振捣的密实度,对接头部位要采用凿毛清洗的措施,保证混凝土的整体性和强度达到要求。

4.2.5、施工过程中认真积累、整理内业及原始施工资料,做到准确、详实、工整,使工程质量检验资料统一规范化,符合工程档案资料立卷归档要求。

第五章 工期计划及保证措施

5.1 工期计划

1、施工准备:包括控制测量工作;原材料检验,砂浆、砼配合比设计;施工用水;电力供应;道路交通疏解;管线调查;施工材料等工作,计划为半个月,即从2012年8月1日始至2012年8月15日止。

2、沟槽开挖:计划从2012年8月16日始至2013年1月16日止。

3、混凝土垫层:计划从2012年8月18日始至2013年1月18日止。

4、安管:计划从2012年8月20日始至2013年1月20日止。

5、手孔井:计划从2012年8月25日始至2013年1月25日止。

6、沟槽回填砂、土:计划从2012年8月28日始至2013年1月28日止。

7、路灯基座:计划从2012年9月28日始至2013年1月28日止。

8、灯杆、灯具安装:计划从2012年10月1日始至2013年1月31日止。 照明工程安排施工工期为180天完成。具体施工进度安排见下表

照明工程施工横道图

5.2 工期保证措施

5.2.1、坚持定期召开由施工负责人主持,各专业工程施工负责人参加的工程施工协调会议,听取关于工程施工进度问题的汇报,协调工程施工外部关系,解决工程施工内部矛盾,对其中有关施工进度的问题,提出明确的计划调整意见。

5.2.2、提前为下道工序的施工,做好人力、物力和机械设备的准备,确保工程一环扣一环地紧凑进行。对于影响工程施工总进度的关键项目、关键工序,主要领导和有关管理人员必须跟班作业,必要时组织有效力量,加班加点突破难点,以确保工程进度计划的实现。

5.2.3、按施工方案的要求配备足够的机械设备和施工机具,及时做好机械设备的保养和维修工作。

5.2.4、采用技术熟练、责任心强的人员负责各工种的管理,并保证施工强度所要求的施工人数。

5.2.5、有节奏、有重点地组织各分部分项工程施工,尽量组织流水作业,避免出现窝工现象,努力降低施工成本。

5.2.6、充分利用无雨天气,集中力量快速施工。工程施工因雨而耽搁的进度,雨后增派力量及时挽回。

5.2.7、材料后勤供应及时、杜绝停工待料现象。

5.2.8、严抓工程质量,杜绝返工。

第六章 安全、文明及其他保证措施

6.1 安全管理总目标

6.1.1、目标

1、重大因工死亡责任事故为0,死亡率为0;

2、因工重伤责任事故为0,因工轻伤责任事故≤2‰;

3、重大交通责任事故为0;

4、火灾责任事故为0;

5、杜绝因管理不善、施工方法不当而造成的机械设备、爆炸、中毒等重大事故。

6.1.2、在施工的过程中,要坚持公司历来的“安全第一,预防为主”的方针,严格执行国务院、部、省、市的安全法规、规范,搞好安全教育与培训,强化员工的安全意识;保证安全专管人员的权威性,保证合理的安全投入,从制度上、组织上、技术上、投入上多管齐下,狠抓施工安全管理。

6.2 安全生产保证措施

1、现场所有作业人员、行政管理、参观、检查、监理工程师人员,进入现场必须戴好安全帽外,登高者必须系好安全带;特种作业人员必须持上岗证作 业;各工序施工中要有严格的安全技术交底。

2、建立电器安全管理和经济责任制度。安质科配一名专职电器工程师负责电器采购、安装和安全工作。专职安全员负责巡视监督检查,专业电工在专管部门的领导下,负责施工现场的电器安全。

3、由专业人员独立编制施工用电组织设计、供电方式、配电装置的设置及其配电容量,供配电线路的走向和现场照明的设置及生活设施的用电负荷情况,编制有针对性的电器安全技术规范。

4、施工现场装备行业统一规定的标准电源箱。电器线路和用电设备安装完成后,由专业管理部门验收合格后方可运行操作。

5、经常对用设备用电设备进行安全检查、测试,每周一次测试漏电开关和接地电阻并有书面记录,发现问题,及时整改。

6、机械设备操作人员(或驾驶员)经过专门训练,经考试取得操作证或驾 驶执照后方可上机(车)。

7、机械操作人员和指挥人员严格遵守安全操作技术规程,工作时集中注意力,谨慎工作,不擅离职守,不酒后驾车。

8、机械设备发生故障后及时检修,严禁带故障运行。

9、机械操作人员严格贯彻例保制度,认真执行清洁、润滑、紧固、防腐、安全的十字作业法。

10、物资部设物资配件仓库,统一对物资进行管理,按照材料的储存要求修建具备相应功能的仓库,做到分门别类储放。

11、仓库设专人负责保管、看护,值班室内设报警系统,随时与派出所和消防部门取得联系。

6.2.5、安全生产内业工作

安全生产“七图二牌”必须上墙。七图即:①施工总平面图;②安全网络图;③电路平面布置图;④管线分布图;⑤临时排水走向图;⑥消防器材布置图;⑦工程进度形象图。二牌即:①无重大伤亡事故累计天数牌;②百日无事故累计天数牌。现场布置安全生产标语和警示牌,做到无违章现象发生。

6.3 文明施工措施

6.3.1、加强现场管理和对全体施工人员的文明教育管理工作,做到紧张有序,文明礼貌,团结协作,刻苦顽强,遵纪守法。

6.3.2、设置宣传标语和标牌,增强环保意识。

6.3.3、车辆不准带泥土出现场,如有泥砂带入场外道路,要及时清扫处理,绝不影响市容环境。

6.3.4、合理规划施工现场,将生产、生活区分开设置。

6.3.5、服从建设单位的管理。

6.3.6、搞好驻地周围的环境卫生,保持良好的生活环境。

6.5 环境保护措施

6.5.1、认真学习地方政府有关环境保护、水利设施保护、文物保护、防止水土流失、施工现场管理等规定和文件,制定相应的措施和办法,并贯穿于施工全过程。

6.5.2、将文明施工与环境保护管理纳入常规施工管理,安排专人负责,对用于工程的各种材料机具设备摆放整齐有序,并设立标志,防、排水设施齐全,性能良好,保持工地整洁。

6.5.3、对于临时用地,不乱取弃土,合理规划,珍惜每一寸土地。施工中认真

做好防护工程,防止水土流失。

6.5.4、随着工程进度的推进,及时清理施工现场,施工废水用汽车清理出场外,不随意排放,尽量维持现有渠道、道路畅通、保护生态平衡。

6.5.5、采取有效措施控制现场的各种粉尘、废气、污水、固体垃圾及噪声震动对环境的污染和危害,不在现场燃烧各种有毒的物质。

6.5.6、工程施工过程中及时清理各种垃圾、废油、废渣,及时处理废气。

6.5.7、运输道路经常洒水,避免扬尘。


相关文章

  • 工程部安全.管理规章制度
  • 河南万安油气设备工程有限公司 工程部管理制度 1.工程部成员必须形成计划→实施→检查→改进的管理模式. 2.工程部成员必须有大局观念,认识并处理好整体与局部的关系:既要分工明 确又要团结协作:时刻树立"公司利益无小事". ...查看


  • 规划建设局工作总结
  • 2014年是天府新区阔步迈进的开篇之年,是顺利升级为国家级新区打基础.奠基石的一年,在党工委管委会的正确领导下,规划建设局牢记自身使命,依法行政,以规划为引领.以项目为抓手.以创新为动力.以服务为宗旨,始终保持急行军状态.勇当新区建设的&q ...查看


  • 1压力容器设计质量保证手册陈鄂2012
  • 湖北万安环保石化设备有限公司 压 力 容 器 设 计 质 量 保 证 手 册 编 制: 卢 雨 审 核: 段洪帝 批 准: 陈 鄂 发布日期:2012年10月01日 实施日期:2012年12月01日 目 录 前 言............. ...查看


  • 专项方案审批表改1
  • 专 项 方 案 审 批 表 专项方案名称 工程名称 建设单位 监理单位 施工单位 (深基坑)施工组织设计 成都 SM 广场二期项目 SM 广场(成都)有限公司 成都万安建设项目管理有限公司 成都市第三建筑工程公司 项目经理 项目经理部 徐荣 ...查看


  • 小区供配电毕业设计(详细)
  • 学生毕业设计(论文)原创性声明 本人以信誉声明:所呈交的毕业设计(论文)是在导师的指导下进行的设计(研究)工作及取得的成果,设计(论文)中引用他(她)人的文献.数据.图件.资料均已明确标注出,论文中的结论和结果为本人独立完成,不包含他人成果 ...查看


  • 房地产项目备案申请报告
  • XXXXX项目 备案申请报告 海南xxx实业有限公司编制 二〇一六年一月 目 录 第一章 项目单位基本情况 .......................... 1 第二章 项目基本情况 .......................... ...查看


  • 万安集团有限公司2015年度第一期短期融资券法律意见书
  • 浙江星韵律师事务所 关于 万安集团有限公司发行 2015 年度第一期短期融资券 之 法律意见书 致: 万安集团有限公司 浙江星韵律师事务所(下称"本所")接受万安集团有限公司(下称"发行人")的委托, ...查看


  • 中国十三大水电基地详情
  • 中国十三大水电基地规划--各水电基地资料详情 1 金沙江水电基地 上游川藏河段规划8个梯级电站总装机容量将达898万千瓦,计划投资上千亿元.开发成功后将成为"西电东送"的重要能源基地. 中游阿海水电站为电梯级开发一库(龙 ...查看


  • 深基坑开挖
  • 北京路项目(四队) 深 基 坑 开 挖 专 项 施 工 方 案 编 制 审 核 批 准 目 录 一.工程概况„„„„„„„„„„„„„„„„„„„„„„„„„„3 1.过程概述„„„„„„„„„„„„„„„„„„„„„„„„„„3 2.气候 ...查看


热门内容