配网 1钢管杆.铁塔组立安装作业

钢管杆、铁塔组立安装作业指导书

编码:DLGT-01

目 次

1 适用范围 ···················································································································································· 3 2 编写依据 ···················································································································································· 3 3 作业流程图 ················································································································································ 3 4 安全风险辨析与预控 ································································································································· 3 5 作业准备 ···················································································································································· 4 6 作业方法 ···················································································································································· 5 7 质量控制措施及检验标准 ························································································································· 6

1 适用范围

1.1 电压等级

35kV 及以下配网工程。 1.2 电气类别

钢管杆、铁塔组立工程的安装。 2 编写依据

表2 编 写 依 据

3 作业流程图

图3 作业流程图

4

安全风险辨析与预控

4.1 钢管杆、铁塔组立安装前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。 4.2 按《指南》中与钢管杆、铁塔组立安装相关联的《电网建设安全施工作业票》(编码:DLGT-01-01/01),结合现场实际情况进行差异化分析,确定风险等级,

现场技术员填写安全

施工作业票,安全员审核,施工负责人签发。

4.3 施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。

4.4 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。 5 作业准备

5.1 作业前施工条件

表5.1 作业前施工条件

5.2 人员、主要工器具及仪器仪表配置

表5.2 人员、主要工器具及仪器仪表配置

6 作业方法

表6 作业方法

7 质量控制措施及检验标准 7.1质量控制措施

7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。

7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗证。

7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治措施。

7.1.4作业现场必须有经审核批准的设计图纸和施工方案,作业人员必须按图施工。 7.1.5施工质量检验一般按以下方式进行。质量检验一般采用三级检验制,施工队(组)对所施工的分项工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。 7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。

7.1.7混凝土浇筑施工,应提前24小时通知监理进行现场旁站。 7.2 质量控制点

质量控制点表单

7.3检验标准

质量检验按中国南方电网有限公司《配网工程质量检验及评定标准》中Q/CSG表7.1-7.3进行,并应符合标准要求。

钢管杆、铁塔组立安装作业基准风险分析表

编码:DLGT-01-01/01

钢管杆、铁塔组立安装作业安全施工作业票

工程名称:

施工班组: 编号:

钢管杆、铁塔组立安装作业指导书

编码:DLGT-01

目 次

1 适用范围 ···················································································································································· 3 2 编写依据 ···················································································································································· 3 3 作业流程图 ················································································································································ 3 4 安全风险辨析与预控 ································································································································· 3 5 作业准备 ···················································································································································· 4 6 作业方法 ···················································································································································· 5 7 质量控制措施及检验标准 ························································································································· 6

1 适用范围

1.1 电压等级

35kV 及以下配网工程。 1.2 电气类别

钢管杆、铁塔组立工程的安装。 2 编写依据

表2 编 写 依 据

3 作业流程图

图3 作业流程图

4

安全风险辨析与预控

4.1 钢管杆、铁塔组立安装前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。 4.2 按《指南》中与钢管杆、铁塔组立安装相关联的《电网建设安全施工作业票》(编码:DLGT-01-01/01),结合现场实际情况进行差异化分析,确定风险等级,

现场技术员填写安全

施工作业票,安全员审核,施工负责人签发。

4.3 施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。

4.4 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。 5 作业准备

5.1 作业前施工条件

表5.1 作业前施工条件

5.2 人员、主要工器具及仪器仪表配置

表5.2 人员、主要工器具及仪器仪表配置

6 作业方法

表6 作业方法

7 质量控制措施及检验标准 7.1质量控制措施

7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。

7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗证。

7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治措施。

7.1.4作业现场必须有经审核批准的设计图纸和施工方案,作业人员必须按图施工。 7.1.5施工质量检验一般按以下方式进行。质量检验一般采用三级检验制,施工队(组)对所施工的分项工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。 7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。

7.1.7混凝土浇筑施工,应提前24小时通知监理进行现场旁站。 7.2 质量控制点

质量控制点表单

7.3检验标准

质量检验按中国南方电网有限公司《配网工程质量检验及评定标准》中Q/CSG表7.1-7.3进行,并应符合标准要求。

钢管杆、铁塔组立安装作业基准风险分析表

编码:DLGT-01-01/01

钢管杆、铁塔组立安装作业安全施工作业票

工程名称:

施工班组: 编号:


相关文章

  • 竣工报告模板(城网工程项目)
  • 工程项目 竣工报告书 项目名称: 项目地址: 项目编号: 项目性质: (城网工程项目名称) (工程项目具体地点.位置) (城网工程项目工程编号) 城网改造 工程施工单位全称(章) 年 月 (城网工程项目名称) 竣工报告 (城网工程项目名称) ...查看


  • 电力线路基础知识
  • 输电线路是电力系统的重要组成部分,它担负着输送和分配电能的任务. 输电线路有架空线路和电缆线路之分.按电能性质分类有交流输电线路和直流输电线路.按电压等级有输电线路和配电线路之分.输电线电压等级一般在35kV 及以上.目前我国输电线路的电压 ...查看


  • 河南移动铁塔建设规范
  • 河南移动铁塔建设规范 (自建铁塔) 河南移动通信有限责任公司 河南省电信规划设计院 2013年5月 目 次 1.总则 ................................................. 1 1.1.概述 .. ...查看


  • 钢管塔吊装组立施工方案及措施
  • 外部供电工程潭松-金川双回路220kV线路工程 钢 管 塔 吊 装 组 立 施 工 方 案 及 措 施 批准: 审核: 编写: 外部供电工程潭松-金川双回路220kV线路工程项目部 2013年03月21日 我公司承建的外部供电工程潭松至金川 ...查看


  • 土石方开挖施工方案
  • 河源市龙川县2010年新建配网工程(G 标段) 土石方开挖工程 施 工 方 案 审核: 编制: 广东省源天工程公司河源市2010年新建配网工程项目部 2010-8-21 一. 工程概述 工程名称:龙川县2010年新建配网工程(G 标段) 2 ...查看


  • 5 施工安全基本知识
  • 施工安全基本知识 为了提高基层施工人员安全专业技能,使得施工安全风险可控,本章节重点叙述了施工人员"四步工作法",安全基本技能,施工过程中常用的几种行之有效的系扣方法,交叉作业及危险区域划分,现场应急处置,共5个章节内容 ...查看


  • 配电线路工技师技术总结2015
  • 我一直在xx供电公司工作.这16 年多来先后在线路班.四个供电所.生产技术部.市场与客户服务部.输变电管理所工作.参加过35kV.10kV.0.4kV线路等电力生产一线建设工作,电力工程验收工作.一直从事着和输配电有关的工作.在工作中,我尊 ...查看


  • 配电线路技师技术总结
  • 配电线路技师技术总结 --刻苦钻研业务技术,努力提高技能水平 从1997年7月至今,我一直在xx供电公司工作.这16 年多来先后在线路班.四个供电所.生产技术部.市场与客户服务部.输变电管理所工作.参加过35kV.10kV.0.4kV线路等 ...查看


  • 三电迁改方案
  • 迁改工程 迁改整体原则 三电迁改工作的整体原则是:经济合理.技术可行.安全可靠. 具体实施时应做到:现场调查,优化方案:充分准备.超前安排:精心组织,确保进度:作好协调,迁改到位:优质高效,服务全程. 以设计文件为准则,严格依据设计标准施工 ...查看


热门内容