一、 工程概况·····························································2 二、 施工依据 ····························································2 三、 施工机械、工器具及措施性材料·········································2 四、 劳动力组织及施工进度·················································3 五、 施工作业方案·························································4 六、 施工工艺流程·························································4 七、 质量要求·····························································4 八、 施工注意事项·························································5 九、 安全施工注意事项·····················································5 十、 环境及文明施工注意事项···············································7 十一、危险因素辨识及控制措施···············································8 十二、附件·································································11
一、工程概况
天津北疆发电厂二期扩建工程2×1000MW 超超临界燃煤发电机组,#3机组1/22轴与#2机组22轴线公用一期已施工完毕的混凝土基础。一期已将22轴线封闭、底部基础已施工完毕,需要将基础地脚螺栓凿出,并将封闭彩板、零米墙体、部分抗风柱拆除,之后进行钢结构安装。
主要工程量:
挡水沿砌筑:16m 3 拆除彩板:1700m 2 双排脚手架:1400m 2 围挡:330m 2 拆除墙体:15m 拆除钢结构:180t 拆除门窗:100m 2 彩板安装:1400m 2 拆除暖气片:14片 二、施工依据
1.《主厂房框架总图》F451ⅡS-T0255
2.《电力建设安全工作规程第1部分:火力发电厂》DL5009.1-2014 3. 《砌体结构工程施工质量验收规范》GB50203—2011 4. 《钢结构焊接规范》GB50661-2011 5、《火力发电厂焊接技术规程》DL/T869-2012 三、施工机械、工器具及措施性材料 3.1计量器具、工具
3
外板拆除 2015.08.28-2015.09.10 内部通道防护 2015.08.31-2015.09.08 内部临时封闭施工 2015.09.10-2015.09.25 #3钢柱及屋架施工 2015.09.30-2015.10.15 行车通行 2015.10.20-2015.11.15 五、施工作业方案
17m 以下采用外排架对彩板及墙体进行拆除,17m 以上采用吊笼对彩板进行拆除。 各层拆除前需先隔离后拆除施工,并将施工通道进行围挡,通道内满铺模板。拆除顺序按照由上至下的顺序进行,所有防护完成后方可进行拆除。
抗风柱第一道横梁以上割除后采用LR1400吊装至地面。 六、施工工艺流程
工艺流程:施工通道围挡及防护→各层档水沿砌筑→双排脚手架搭设→外封闭彩板拆除→防护彩板封闭→墙体、内封闭彩板、门窗、暖气管道及暖气片拆除→抗风柱拆除→#3钢结构安装→行车通道脚手架拆除→行车通道脚手架恢复→#3主厂房封闭后临时防护拆除
(一)拆除外彩板
1、采用吊篮由女儿墙向下设置,对外彩板进行拆除。
2、采用手持式电钻,将外板螺栓拧下,单张板上部螺栓拧下后,采用麻绳或钢丝绳将上端拴牢,之后卸下单张板中部及底部螺栓,待全部螺栓拧下后,单张彩板运至地面。
2、拆除的外板要及时运至地面,并妥善保管,不得损毁外板。见附图四。 (二)、0m 层施工通道围挡及防护
1、将施工所用的通道满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。
2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。
3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离控制室距离200mm ,防止破坏钢化玻璃。 (三)0m 层挡水沿砌筑
1、沿22轴联络平台钢梁内侧垂线,砌体抹灰后与钢梁平齐,墙厚240mm 。
2、将砌体下部楼地面凿毛,形成粗凿面(17m 层地砖可不处理),采用蒸压灰砂砖砌筑,M5砂浆砌筑。
3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (四)0m 层双排脚手架搭设
1、根据平面图位置,将脚手架位置在楼板及墙体上测放,靠近控制室处可距控制室200mm 进行搭设。
2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架与钢柱相连,采用焊接连接,中间设置立杆。见附图三。 (五)0m 层防护彩板封闭
1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。
2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。
3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。
4、单层板封闭完成后进行内板及保温封闭,保温材料必须采用防火玻璃棉进行封闭。 (六)、8.6m 层施工通道围挡及防护
1、将施工所用的通道由0m 层至8.6m 层满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。
2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。
3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离配电间墙体距离200mm ,防止破坏墙体。 (七)8.6m 层挡水沿砌筑
1、沿22轴联络平台钢柱内侧放线,砌体抹灰后与钢柱平齐,墙厚240mm 。 2、将砌体下部楼地面凿毛,形成粗凿面,采用蒸压灰砂砖砌筑,M5砂浆砌筑。 3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (八)8.6m 层双排脚手架搭设
1、根据平面图位置,将脚手架位置在楼板及墙体上测放,靠近配电室处距配电室200mm 进行搭设。
2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架与钢柱相连,采用焊接连接,中间设置立杆。见附图三。 (九)8.6m 层防护彩板封闭
1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。
2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。
3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。
4、12m 层配电间待设计院出图后施工。 (十)、17m 层施工通道围挡及防护
1、将施工所用的通道由8.6m 层至17m 层满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。
2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。
3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离配电间墙体距离200mm ,防止破坏墙体。 (十一)17m 层挡水沿砌筑
1、沿22轴联络平台钢柱内侧放线,砌体抹灰后与钢柱平齐,墙厚240mm 。 2、采用蒸压灰砂砖砌筑,M5砂浆砌筑。
3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (十二)17m 层双排脚手架搭设
1、根据平面图位置,将脚手架位置在楼板及墙体上测放,进行搭设。
2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架横杆与钢柱相连,采用焊接连接,中间设置立杆。第一道抗风柱以上不设置连墙件,由低至顶设置剪刀撑,见附图三。 (十三)17m 层防护彩板封闭
1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。
2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。
3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。
(十四)内彩板拆除
1、采用吊篮由女儿墙向下设置,对内彩板进行拆除。
2、采用手持式电钻,将内板及保温固定螺栓拧下,单张板上部螺栓拧下后,采用麻绳或钢丝绳将上端拴牢,之后卸下单张板中部及底部螺栓,待全部螺栓拧下后,单张彩板运至地面。
2、拆除的内板要及时运至地面,并妥善保管,不得损毁内板。见附图四。 (十五)抗风柱拆除
1、内彩板拆除至第一道横梁以下时,采用LR1400将横梁以上抗风柱拆除。
2、抗风柱第一道横梁上部柱段割除,也可将柱节点螺栓拧下,割除时,先用钢丝绳将钢柱顶部拴牢,用气割将17m 以上第一道横梁出及顶部与屋架相连处割除,之后用LR1400将钢柱吊下,之后继续拆除内彩板。见附图四。 (十六)墙体暖气等拆除施工
1、拆除时,要严格保护拆除物品的完整性,如暖气、门窗等。 2、暖气拆除时,首先关闭阀门,之后进行拆除施工。 3、8.6m 层除配电间北墙不拆除,其他墙体、彩板均需拆除, (十七)过行车
1、达到行车通过条件后,将抗风柱第一道横梁以上的脚手架拆除,保证行车可顺利通过。 2、拆除时由上向下进行拆除,底部连墙件禁止拆除,拆除时设专人进行监护,严禁随意抛掷构件。
(十八)脚手架恢复及防护拆除
行车通过后,将拆除脚手架恢复,直至#3主厂房封闭完,将整体脚手架进行拆除,并将围挡、铺设垫板等运出#2主厂房,并将通道清理干净,挡水沿等均需拆除。见附图五。 七、施工注意事项
1、配电间内施工时,所有施工人员需穿绝缘鞋,不得随意碰触盘柜,施工前办理作业票。 2、所有拆除后构件不得随意抛掷,必须采用溜绳运送至地面,墙体拆除宜使构件向北侧破坏,防止拆除后构件掉落#2主厂房内部。
3、吊笼使用前必须将相关资料上报,并经现场检查后方可进行施工。 4、施工中严禁在#2厂房内胡乱走动,必须在围挡范围内,不得越界。
5、防护施工的通道必须全程铺设模板或橡胶板,保证#2厂房内楼地面不受损坏。 6、所有施工开工前,必须办理相应作业票,无票禁止作业。 八、安全施工注意事项
1、所有施工人员作业前须经安全培训,并经考核合格后持证上岗。作业人员无高血压、心脏病、精神病、癫痫病等危害施工安全的疾病。特殊工种人员应持相应资格证书上岗。
2、每天上班前,班长应根据当天的工作安排对作业人员进行技术、安全交底,并应办理交底签字。
3、作业人员进入施工现场必须正确佩带安全帽,系好下颌带。不准穿着拖鞋、高跟鞋及短裤进入施工现场。不准酒后上班。
4、电气作业必须由持证的专业电工进行,非电工严禁装、拆电气设备与设施。不得单人进行电气作业,在已送电的线路或用电设备上需停电进行作业时,断开电源的开关必须挂牌,并有专人监护。
5、各种起吊设施应完好无缺陷,不准带病运行,不准超限使用。
6、在进行起吊作业时,应设专职指挥人员,指挥人员应持证上岗,指挥信号应清晰明了。 7、高处作业作业人员必须扎安全带,安全带挂在水平安全绳上或稳固构件上,并做到高挂低用。起重工拴、摘钢丝绳时正确使用自锁器。
8、脚手架须由有证架工按规范要求搭设,搭设完的脚手架须经技术负责人验收合格后,方可投入使用。
9、高处操作人员使用的工具、零配件等,应放在随身佩带的工具袋内,或拴上安全绳系
在身上,不可随意上下抛掷。
10、在高处用气割切割时,应采取措施,或在地面设置安全监护人,防止火花落下伤人。 11、禁止在六级或六级以上大风、大雾、大雨天气、夜间等恶劣气侯下进行吊装作业。 12、夜间施工应有足够的照明,照度应符合施工作业的要求。
13、施工现场危险区域禁止使用、拨打、玩手机,执行公司六大禁令。
14、10t 、20t 及15t 卡环、钢丝绳等应经常进行维修保养,并做好拉力试验合格后方可进行使用,使用前认真检查是否损坏,确保无误方可进行吊装作业。
15、气割过程中做好防火措施,施焊前仔细检查周围环境,是否有可燃、易燃物品,及时进行清理,同时做好接火盆,防止火花四溅引发火灾,底部设监护人,发现险情及时采用就近灭火器材灭火,防止火势蔓延。
16、现场发现情况应及时进行汇报,并根据事件大小按照项目部应急预案要求启动相应应急预案,并及时进行汇报。
17、全过程施工设置专职人员进行全程监护,无关人员禁入施工区域,施工人员禁入#2主厂房。
18、施工过程中所需材料在#2主厂房外下料完毕,减少#2主厂房内部扬尘,减少污染,及时清理产生的生产垃圾。
19、吊笼结构应焊接牢固,禁止使用变形、锈蚀、损坏的吊笼,吊笼使用前几使用期间应定期进行检查,合格后方可进行施工。
20、拆除作业现场设置足够的消防器材,与一期生产区域设置可靠的隔离区域,保障生产区域的正常运行。
21、施工用电严格按照五项三线制执行,电动工具必须安装漏电保护器,防止触电事故的发生。
22、夏季施工时,做好防暑降温工作,设置饮水点并配置藿香正气水,防止人员中暑。 23、如遇突发事件及紧急情况,应立即进行应急处理,防止事态发展,并立即向上级进行汇报,及时启动项目部相应应急预案。 九、环境及文明施工注意事项
1、现场所有安全设施,如安全防护栏杆、安全警戒绳等均使用标准的安全防护栏杆、安全警戒绳等。
2、构件吊装时,应拴以溜绳,以控制构件空中方向。 3、施工中产生的边角料、施工垃圾应随时清除。 4、要注意施工机械的日常保养,避免过大的燥音。
5、在施工完的框架附近进行可能污染作业时,应进行防护。 6、要加强和提高全体施工人员的环保意识,认清环保的重要性。
7、运输时要减速慢行,防止扬尘,防止漏油,以免造成道路和场地污染。
十.危险因素辩识与控制
目 录
一、 工程概况·····························································2 二、 施工依据 ····························································2 三、 施工机械、工器具及措施性材料·········································2 四、 劳动力组织及施工进度·················································3 五、 施工作业方案·························································4 六、 施工工艺流程·························································4 七、 质量要求·····························································4 八、 施工注意事项·························································5 九、 安全施工注意事项·····················································5 十、 环境及文明施工注意事项···············································7 十一、危险因素辨识及控制措施···············································8 十二、附件·································································11
一、工程概况
天津北疆发电厂二期扩建工程2×1000MW 超超临界燃煤发电机组,#3机组1/22轴与#2机组22轴线公用一期已施工完毕的混凝土基础。一期已将22轴线封闭、底部基础已施工完毕,需要将基础地脚螺栓凿出,并将封闭彩板、零米墙体、部分抗风柱拆除,之后进行钢结构安装。
主要工程量:
挡水沿砌筑:16m 3 拆除彩板:1700m 2 双排脚手架:1400m 2 围挡:330m 2 拆除墙体:15m 拆除钢结构:180t 拆除门窗:100m 2 彩板安装:1400m 2 拆除暖气片:14片 二、施工依据
1.《主厂房框架总图》F451ⅡS-T0255
2.《电力建设安全工作规程第1部分:火力发电厂》DL5009.1-2014 3. 《砌体结构工程施工质量验收规范》GB50203—2011 4. 《钢结构焊接规范》GB50661-2011 5、《火力发电厂焊接技术规程》DL/T869-2012 三、施工机械、工器具及措施性材料 3.1计量器具、工具
3
外板拆除 2015.08.28-2015.09.10 内部通道防护 2015.08.31-2015.09.08 内部临时封闭施工 2015.09.10-2015.09.25 #3钢柱及屋架施工 2015.09.30-2015.10.15 行车通行 2015.10.20-2015.11.15 五、施工作业方案
17m 以下采用外排架对彩板及墙体进行拆除,17m 以上采用吊笼对彩板进行拆除。 各层拆除前需先隔离后拆除施工,并将施工通道进行围挡,通道内满铺模板。拆除顺序按照由上至下的顺序进行,所有防护完成后方可进行拆除。
抗风柱第一道横梁以上割除后采用LR1400吊装至地面。 六、施工工艺流程
工艺流程:施工通道围挡及防护→各层档水沿砌筑→双排脚手架搭设→外封闭彩板拆除→防护彩板封闭→墙体、内封闭彩板、门窗、暖气管道及暖气片拆除→抗风柱拆除→#3钢结构安装→行车通道脚手架拆除→行车通道脚手架恢复→#3主厂房封闭后临时防护拆除
(一)拆除外彩板
1、采用吊篮由女儿墙向下设置,对外彩板进行拆除。
2、采用手持式电钻,将外板螺栓拧下,单张板上部螺栓拧下后,采用麻绳或钢丝绳将上端拴牢,之后卸下单张板中部及底部螺栓,待全部螺栓拧下后,单张彩板运至地面。
2、拆除的外板要及时运至地面,并妥善保管,不得损毁外板。见附图四。 (二)、0m 层施工通道围挡及防护
1、将施工所用的通道满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。
2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。
3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离控制室距离200mm ,防止破坏钢化玻璃。 (三)0m 层挡水沿砌筑
1、沿22轴联络平台钢梁内侧垂线,砌体抹灰后与钢梁平齐,墙厚240mm 。
2、将砌体下部楼地面凿毛,形成粗凿面(17m 层地砖可不处理),采用蒸压灰砂砖砌筑,M5砂浆砌筑。
3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (四)0m 层双排脚手架搭设
1、根据平面图位置,将脚手架位置在楼板及墙体上测放,靠近控制室处可距控制室200mm 进行搭设。
2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架与钢柱相连,采用焊接连接,中间设置立杆。见附图三。 (五)0m 层防护彩板封闭
1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。
2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。
3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。
4、单层板封闭完成后进行内板及保温封闭,保温材料必须采用防火玻璃棉进行封闭。 (六)、8.6m 层施工通道围挡及防护
1、将施工所用的通道由0m 层至8.6m 层满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。
2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。
3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离配电间墙体距离200mm ,防止破坏墙体。 (七)8.6m 层挡水沿砌筑
1、沿22轴联络平台钢柱内侧放线,砌体抹灰后与钢柱平齐,墙厚240mm 。 2、将砌体下部楼地面凿毛,形成粗凿面,采用蒸压灰砂砖砌筑,M5砂浆砌筑。 3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (八)8.6m 层双排脚手架搭设
1、根据平面图位置,将脚手架位置在楼板及墙体上测放,靠近配电室处距配电室200mm 进行搭设。
2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架与钢柱相连,采用焊接连接,中间设置立杆。见附图三。 (九)8.6m 层防护彩板封闭
1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。
2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。
3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。
4、12m 层配电间待设计院出图后施工。 (十)、17m 层施工通道围挡及防护
1、将施工所用的通道由8.6m 层至17m 层满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。
2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。
3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离配电间墙体距离200mm ,防止破坏墙体。 (十一)17m 层挡水沿砌筑
1、沿22轴联络平台钢柱内侧放线,砌体抹灰后与钢柱平齐,墙厚240mm 。 2、采用蒸压灰砂砖砌筑,M5砂浆砌筑。
3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (十二)17m 层双排脚手架搭设
1、根据平面图位置,将脚手架位置在楼板及墙体上测放,进行搭设。
2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架横杆与钢柱相连,采用焊接连接,中间设置立杆。第一道抗风柱以上不设置连墙件,由低至顶设置剪刀撑,见附图三。 (十三)17m 层防护彩板封闭
1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。
2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。
3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。
(十四)内彩板拆除
1、采用吊篮由女儿墙向下设置,对内彩板进行拆除。
2、采用手持式电钻,将内板及保温固定螺栓拧下,单张板上部螺栓拧下后,采用麻绳或钢丝绳将上端拴牢,之后卸下单张板中部及底部螺栓,待全部螺栓拧下后,单张彩板运至地面。
2、拆除的内板要及时运至地面,并妥善保管,不得损毁内板。见附图四。 (十五)抗风柱拆除
1、内彩板拆除至第一道横梁以下时,采用LR1400将横梁以上抗风柱拆除。
2、抗风柱第一道横梁上部柱段割除,也可将柱节点螺栓拧下,割除时,先用钢丝绳将钢柱顶部拴牢,用气割将17m 以上第一道横梁出及顶部与屋架相连处割除,之后用LR1400将钢柱吊下,之后继续拆除内彩板。见附图四。 (十六)墙体暖气等拆除施工
1、拆除时,要严格保护拆除物品的完整性,如暖气、门窗等。 2、暖气拆除时,首先关闭阀门,之后进行拆除施工。 3、8.6m 层除配电间北墙不拆除,其他墙体、彩板均需拆除, (十七)过行车
1、达到行车通过条件后,将抗风柱第一道横梁以上的脚手架拆除,保证行车可顺利通过。 2、拆除时由上向下进行拆除,底部连墙件禁止拆除,拆除时设专人进行监护,严禁随意抛掷构件。
(十八)脚手架恢复及防护拆除
行车通过后,将拆除脚手架恢复,直至#3主厂房封闭完,将整体脚手架进行拆除,并将围挡、铺设垫板等运出#2主厂房,并将通道清理干净,挡水沿等均需拆除。见附图五。 七、施工注意事项
1、配电间内施工时,所有施工人员需穿绝缘鞋,不得随意碰触盘柜,施工前办理作业票。 2、所有拆除后构件不得随意抛掷,必须采用溜绳运送至地面,墙体拆除宜使构件向北侧破坏,防止拆除后构件掉落#2主厂房内部。
3、吊笼使用前必须将相关资料上报,并经现场检查后方可进行施工。 4、施工中严禁在#2厂房内胡乱走动,必须在围挡范围内,不得越界。
5、防护施工的通道必须全程铺设模板或橡胶板,保证#2厂房内楼地面不受损坏。 6、所有施工开工前,必须办理相应作业票,无票禁止作业。 八、安全施工注意事项
1、所有施工人员作业前须经安全培训,并经考核合格后持证上岗。作业人员无高血压、心脏病、精神病、癫痫病等危害施工安全的疾病。特殊工种人员应持相应资格证书上岗。
2、每天上班前,班长应根据当天的工作安排对作业人员进行技术、安全交底,并应办理交底签字。
3、作业人员进入施工现场必须正确佩带安全帽,系好下颌带。不准穿着拖鞋、高跟鞋及短裤进入施工现场。不准酒后上班。
4、电气作业必须由持证的专业电工进行,非电工严禁装、拆电气设备与设施。不得单人进行电气作业,在已送电的线路或用电设备上需停电进行作业时,断开电源的开关必须挂牌,并有专人监护。
5、各种起吊设施应完好无缺陷,不准带病运行,不准超限使用。
6、在进行起吊作业时,应设专职指挥人员,指挥人员应持证上岗,指挥信号应清晰明了。 7、高处作业作业人员必须扎安全带,安全带挂在水平安全绳上或稳固构件上,并做到高挂低用。起重工拴、摘钢丝绳时正确使用自锁器。
8、脚手架须由有证架工按规范要求搭设,搭设完的脚手架须经技术负责人验收合格后,方可投入使用。
9、高处操作人员使用的工具、零配件等,应放在随身佩带的工具袋内,或拴上安全绳系
在身上,不可随意上下抛掷。
10、在高处用气割切割时,应采取措施,或在地面设置安全监护人,防止火花落下伤人。 11、禁止在六级或六级以上大风、大雾、大雨天气、夜间等恶劣气侯下进行吊装作业。 12、夜间施工应有足够的照明,照度应符合施工作业的要求。
13、施工现场危险区域禁止使用、拨打、玩手机,执行公司六大禁令。
14、10t 、20t 及15t 卡环、钢丝绳等应经常进行维修保养,并做好拉力试验合格后方可进行使用,使用前认真检查是否损坏,确保无误方可进行吊装作业。
15、气割过程中做好防火措施,施焊前仔细检查周围环境,是否有可燃、易燃物品,及时进行清理,同时做好接火盆,防止火花四溅引发火灾,底部设监护人,发现险情及时采用就近灭火器材灭火,防止火势蔓延。
16、现场发现情况应及时进行汇报,并根据事件大小按照项目部应急预案要求启动相应应急预案,并及时进行汇报。
17、全过程施工设置专职人员进行全程监护,无关人员禁入施工区域,施工人员禁入#2主厂房。
18、施工过程中所需材料在#2主厂房外下料完毕,减少#2主厂房内部扬尘,减少污染,及时清理产生的生产垃圾。
19、吊笼结构应焊接牢固,禁止使用变形、锈蚀、损坏的吊笼,吊笼使用前几使用期间应定期进行检查,合格后方可进行施工。
20、拆除作业现场设置足够的消防器材,与一期生产区域设置可靠的隔离区域,保障生产区域的正常运行。
21、施工用电严格按照五项三线制执行,电动工具必须安装漏电保护器,防止触电事故的发生。
22、夏季施工时,做好防暑降温工作,设置饮水点并配置藿香正气水,防止人员中暑。 23、如遇突发事件及紧急情况,应立即进行应急处理,防止事态发展,并立即向上级进行汇报,及时启动项目部相应应急预案。 九、环境及文明施工注意事项
1、现场所有安全设施,如安全防护栏杆、安全警戒绳等均使用标准的安全防护栏杆、安全警戒绳等。
2、构件吊装时,应拴以溜绳,以控制构件空中方向。 3、施工中产生的边角料、施工垃圾应随时清除。 4、要注意施工机械的日常保养,避免过大的燥音。
5、在施工完的框架附近进行可能污染作业时,应进行防护。 6、要加强和提高全体施工人员的环保意识,认清环保的重要性。
7、运输时要减速慢行,防止扬尘,防止漏油,以免造成道路和场地污染。
十.危险因素辩识与控制