电力工程机组隔离防护施工措施

目 录

一、 工程概况·····························································2 二、 施工依据 ····························································2 三、 施工机械、工器具及措施性材料·········································2 四、 劳动力组织及施工进度·················································3 五、 施工作业方案·························································4 六、 施工工艺流程·························································4 七、 质量要求·····························································4 八、 施工注意事项·························································5 九、 安全施工注意事项·····················································5 十、 环境及文明施工注意事项···············································7 十一、危险因素辨识及控制措施···············································8 十二、附件·································································11

一、工程概况

天津北疆发电厂二期扩建工程2×1000MW 超超临界燃煤发电机组,#3机组1/22轴与#2机组22轴线公用一期已施工完毕的混凝土基础。一期已将22轴线封闭、底部基础已施工完毕,需要将基础地脚螺栓凿出,并将封闭彩板、零米墙体、部分抗风柱拆除,之后进行钢结构安装。

主要工程量:

挡水沿砌筑:16m 3 拆除彩板:1700m 2 双排脚手架:1400m 2 围挡:330m 2 拆除墙体:15m 拆除钢结构:180t 拆除门窗:100m 2 彩板安装:1400m 2 拆除暖气片:14片 二、施工依据

1.《主厂房框架总图》F451ⅡS-T0255

2.《电力建设安全工作规程第1部分:火力发电厂》DL5009.1-2014 3. 《砌体结构工程施工质量验收规范》GB50203—2011 4. 《钢结构焊接规范》GB50661-2011 5、《火力发电厂焊接技术规程》DL/T869-2012 三、施工机械、工器具及措施性材料 3.1计量器具、工具

3

外板拆除 2015.08.28-2015.09.10 内部通道防护 2015.08.31-2015.09.08 内部临时封闭施工 2015.09.10-2015.09.25 #3钢柱及屋架施工 2015.09.30-2015.10.15 行车通行 2015.10.20-2015.11.15 五、施工作业方案

17m 以下采用外排架对彩板及墙体进行拆除,17m 以上采用吊笼对彩板进行拆除。 各层拆除前需先隔离后拆除施工,并将施工通道进行围挡,通道内满铺模板。拆除顺序按照由上至下的顺序进行,所有防护完成后方可进行拆除。

抗风柱第一道横梁以上割除后采用LR1400吊装至地面。 六、施工工艺流程

工艺流程:施工通道围挡及防护→各层档水沿砌筑→双排脚手架搭设→外封闭彩板拆除→防护彩板封闭→墙体、内封闭彩板、门窗、暖气管道及暖气片拆除→抗风柱拆除→#3钢结构安装→行车通道脚手架拆除→行车通道脚手架恢复→#3主厂房封闭后临时防护拆除

(一)拆除外彩板

1、采用吊篮由女儿墙向下设置,对外彩板进行拆除。

2、采用手持式电钻,将外板螺栓拧下,单张板上部螺栓拧下后,采用麻绳或钢丝绳将上端拴牢,之后卸下单张板中部及底部螺栓,待全部螺栓拧下后,单张彩板运至地面。

2、拆除的外板要及时运至地面,并妥善保管,不得损毁外板。见附图四。 (二)、0m 层施工通道围挡及防护

1、将施工所用的通道满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。

2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。

3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离控制室距离200mm ,防止破坏钢化玻璃。 (三)0m 层挡水沿砌筑

1、沿22轴联络平台钢梁内侧垂线,砌体抹灰后与钢梁平齐,墙厚240mm 。

2、将砌体下部楼地面凿毛,形成粗凿面(17m 层地砖可不处理),采用蒸压灰砂砖砌筑,M5砂浆砌筑。

3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (四)0m 层双排脚手架搭设

1、根据平面图位置,将脚手架位置在楼板及墙体上测放,靠近控制室处可距控制室200mm 进行搭设。

2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架与钢柱相连,采用焊接连接,中间设置立杆。见附图三。 (五)0m 层防护彩板封闭

1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。

2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。

3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。

4、单层板封闭完成后进行内板及保温封闭,保温材料必须采用防火玻璃棉进行封闭。 (六)、8.6m 层施工通道围挡及防护

1、将施工所用的通道由0m 层至8.6m 层满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。

2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。

3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离配电间墙体距离200mm ,防止破坏墙体。 (七)8.6m 层挡水沿砌筑

1、沿22轴联络平台钢柱内侧放线,砌体抹灰后与钢柱平齐,墙厚240mm 。 2、将砌体下部楼地面凿毛,形成粗凿面,采用蒸压灰砂砖砌筑,M5砂浆砌筑。 3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (八)8.6m 层双排脚手架搭设

1、根据平面图位置,将脚手架位置在楼板及墙体上测放,靠近配电室处距配电室200mm 进行搭设。

2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架与钢柱相连,采用焊接连接,中间设置立杆。见附图三。 (九)8.6m 层防护彩板封闭

1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。

2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。

3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。

4、12m 层配电间待设计院出图后施工。 (十)、17m 层施工通道围挡及防护

1、将施工所用的通道由8.6m 层至17m 层满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。

2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。

3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离配电间墙体距离200mm ,防止破坏墙体。 (十一)17m 层挡水沿砌筑

1、沿22轴联络平台钢柱内侧放线,砌体抹灰后与钢柱平齐,墙厚240mm 。 2、采用蒸压灰砂砖砌筑,M5砂浆砌筑。

3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (十二)17m 层双排脚手架搭设

1、根据平面图位置,将脚手架位置在楼板及墙体上测放,进行搭设。

2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架横杆与钢柱相连,采用焊接连接,中间设置立杆。第一道抗风柱以上不设置连墙件,由低至顶设置剪刀撑,见附图三。 (十三)17m 层防护彩板封闭

1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。

2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。

3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。

(十四)内彩板拆除

1、采用吊篮由女儿墙向下设置,对内彩板进行拆除。

2、采用手持式电钻,将内板及保温固定螺栓拧下,单张板上部螺栓拧下后,采用麻绳或钢丝绳将上端拴牢,之后卸下单张板中部及底部螺栓,待全部螺栓拧下后,单张彩板运至地面。

2、拆除的内板要及时运至地面,并妥善保管,不得损毁内板。见附图四。 (十五)抗风柱拆除

1、内彩板拆除至第一道横梁以下时,采用LR1400将横梁以上抗风柱拆除。

2、抗风柱第一道横梁上部柱段割除,也可将柱节点螺栓拧下,割除时,先用钢丝绳将钢柱顶部拴牢,用气割将17m 以上第一道横梁出及顶部与屋架相连处割除,之后用LR1400将钢柱吊下,之后继续拆除内彩板。见附图四。 (十六)墙体暖气等拆除施工

1、拆除时,要严格保护拆除物品的完整性,如暖气、门窗等。 2、暖气拆除时,首先关闭阀门,之后进行拆除施工。 3、8.6m 层除配电间北墙不拆除,其他墙体、彩板均需拆除, (十七)过行车

1、达到行车通过条件后,将抗风柱第一道横梁以上的脚手架拆除,保证行车可顺利通过。 2、拆除时由上向下进行拆除,底部连墙件禁止拆除,拆除时设专人进行监护,严禁随意抛掷构件。

(十八)脚手架恢复及防护拆除

行车通过后,将拆除脚手架恢复,直至#3主厂房封闭完,将整体脚手架进行拆除,并将围挡、铺设垫板等运出#2主厂房,并将通道清理干净,挡水沿等均需拆除。见附图五。 七、施工注意事项

1、配电间内施工时,所有施工人员需穿绝缘鞋,不得随意碰触盘柜,施工前办理作业票。 2、所有拆除后构件不得随意抛掷,必须采用溜绳运送至地面,墙体拆除宜使构件向北侧破坏,防止拆除后构件掉落#2主厂房内部。

3、吊笼使用前必须将相关资料上报,并经现场检查后方可进行施工。 4、施工中严禁在#2厂房内胡乱走动,必须在围挡范围内,不得越界。

5、防护施工的通道必须全程铺设模板或橡胶板,保证#2厂房内楼地面不受损坏。 6、所有施工开工前,必须办理相应作业票,无票禁止作业。 八、安全施工注意事项

1、所有施工人员作业前须经安全培训,并经考核合格后持证上岗。作业人员无高血压、心脏病、精神病、癫痫病等危害施工安全的疾病。特殊工种人员应持相应资格证书上岗。

2、每天上班前,班长应根据当天的工作安排对作业人员进行技术、安全交底,并应办理交底签字。

3、作业人员进入施工现场必须正确佩带安全帽,系好下颌带。不准穿着拖鞋、高跟鞋及短裤进入施工现场。不准酒后上班。

4、电气作业必须由持证的专业电工进行,非电工严禁装、拆电气设备与设施。不得单人进行电气作业,在已送电的线路或用电设备上需停电进行作业时,断开电源的开关必须挂牌,并有专人监护。

5、各种起吊设施应完好无缺陷,不准带病运行,不准超限使用。

6、在进行起吊作业时,应设专职指挥人员,指挥人员应持证上岗,指挥信号应清晰明了。 7、高处作业作业人员必须扎安全带,安全带挂在水平安全绳上或稳固构件上,并做到高挂低用。起重工拴、摘钢丝绳时正确使用自锁器。

8、脚手架须由有证架工按规范要求搭设,搭设完的脚手架须经技术负责人验收合格后,方可投入使用。

9、高处操作人员使用的工具、零配件等,应放在随身佩带的工具袋内,或拴上安全绳系

在身上,不可随意上下抛掷。

10、在高处用气割切割时,应采取措施,或在地面设置安全监护人,防止火花落下伤人。 11、禁止在六级或六级以上大风、大雾、大雨天气、夜间等恶劣气侯下进行吊装作业。 12、夜间施工应有足够的照明,照度应符合施工作业的要求。

13、施工现场危险区域禁止使用、拨打、玩手机,执行公司六大禁令。

14、10t 、20t 及15t 卡环、钢丝绳等应经常进行维修保养,并做好拉力试验合格后方可进行使用,使用前认真检查是否损坏,确保无误方可进行吊装作业。

15、气割过程中做好防火措施,施焊前仔细检查周围环境,是否有可燃、易燃物品,及时进行清理,同时做好接火盆,防止火花四溅引发火灾,底部设监护人,发现险情及时采用就近灭火器材灭火,防止火势蔓延。

16、现场发现情况应及时进行汇报,并根据事件大小按照项目部应急预案要求启动相应应急预案,并及时进行汇报。

17、全过程施工设置专职人员进行全程监护,无关人员禁入施工区域,施工人员禁入#2主厂房。

18、施工过程中所需材料在#2主厂房外下料完毕,减少#2主厂房内部扬尘,减少污染,及时清理产生的生产垃圾。

19、吊笼结构应焊接牢固,禁止使用变形、锈蚀、损坏的吊笼,吊笼使用前几使用期间应定期进行检查,合格后方可进行施工。

20、拆除作业现场设置足够的消防器材,与一期生产区域设置可靠的隔离区域,保障生产区域的正常运行。

21、施工用电严格按照五项三线制执行,电动工具必须安装漏电保护器,防止触电事故的发生。

22、夏季施工时,做好防暑降温工作,设置饮水点并配置藿香正气水,防止人员中暑。 23、如遇突发事件及紧急情况,应立即进行应急处理,防止事态发展,并立即向上级进行汇报,及时启动项目部相应应急预案。 九、环境及文明施工注意事项

1、现场所有安全设施,如安全防护栏杆、安全警戒绳等均使用标准的安全防护栏杆、安全警戒绳等。

2、构件吊装时,应拴以溜绳,以控制构件空中方向。 3、施工中产生的边角料、施工垃圾应随时清除。 4、要注意施工机械的日常保养,避免过大的燥音。

5、在施工完的框架附近进行可能污染作业时,应进行防护。 6、要加强和提高全体施工人员的环保意识,认清环保的重要性。

7、运输时要减速慢行,防止扬尘,防止漏油,以免造成道路和场地污染。

十.危险因素辩识与控制

目 录

一、 工程概况·····························································2 二、 施工依据 ····························································2 三、 施工机械、工器具及措施性材料·········································2 四、 劳动力组织及施工进度·················································3 五、 施工作业方案·························································4 六、 施工工艺流程·························································4 七、 质量要求·····························································4 八、 施工注意事项·························································5 九、 安全施工注意事项·····················································5 十、 环境及文明施工注意事项···············································7 十一、危险因素辨识及控制措施···············································8 十二、附件·································································11

一、工程概况

天津北疆发电厂二期扩建工程2×1000MW 超超临界燃煤发电机组,#3机组1/22轴与#2机组22轴线公用一期已施工完毕的混凝土基础。一期已将22轴线封闭、底部基础已施工完毕,需要将基础地脚螺栓凿出,并将封闭彩板、零米墙体、部分抗风柱拆除,之后进行钢结构安装。

主要工程量:

挡水沿砌筑:16m 3 拆除彩板:1700m 2 双排脚手架:1400m 2 围挡:330m 2 拆除墙体:15m 拆除钢结构:180t 拆除门窗:100m 2 彩板安装:1400m 2 拆除暖气片:14片 二、施工依据

1.《主厂房框架总图》F451ⅡS-T0255

2.《电力建设安全工作规程第1部分:火力发电厂》DL5009.1-2014 3. 《砌体结构工程施工质量验收规范》GB50203—2011 4. 《钢结构焊接规范》GB50661-2011 5、《火力发电厂焊接技术规程》DL/T869-2012 三、施工机械、工器具及措施性材料 3.1计量器具、工具

3

外板拆除 2015.08.28-2015.09.10 内部通道防护 2015.08.31-2015.09.08 内部临时封闭施工 2015.09.10-2015.09.25 #3钢柱及屋架施工 2015.09.30-2015.10.15 行车通行 2015.10.20-2015.11.15 五、施工作业方案

17m 以下采用外排架对彩板及墙体进行拆除,17m 以上采用吊笼对彩板进行拆除。 各层拆除前需先隔离后拆除施工,并将施工通道进行围挡,通道内满铺模板。拆除顺序按照由上至下的顺序进行,所有防护完成后方可进行拆除。

抗风柱第一道横梁以上割除后采用LR1400吊装至地面。 六、施工工艺流程

工艺流程:施工通道围挡及防护→各层档水沿砌筑→双排脚手架搭设→外封闭彩板拆除→防护彩板封闭→墙体、内封闭彩板、门窗、暖气管道及暖气片拆除→抗风柱拆除→#3钢结构安装→行车通道脚手架拆除→行车通道脚手架恢复→#3主厂房封闭后临时防护拆除

(一)拆除外彩板

1、采用吊篮由女儿墙向下设置,对外彩板进行拆除。

2、采用手持式电钻,将外板螺栓拧下,单张板上部螺栓拧下后,采用麻绳或钢丝绳将上端拴牢,之后卸下单张板中部及底部螺栓,待全部螺栓拧下后,单张彩板运至地面。

2、拆除的外板要及时运至地面,并妥善保管,不得损毁外板。见附图四。 (二)、0m 层施工通道围挡及防护

1、将施工所用的通道满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。

2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。

3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离控制室距离200mm ,防止破坏钢化玻璃。 (三)0m 层挡水沿砌筑

1、沿22轴联络平台钢梁内侧垂线,砌体抹灰后与钢梁平齐,墙厚240mm 。

2、将砌体下部楼地面凿毛,形成粗凿面(17m 层地砖可不处理),采用蒸压灰砂砖砌筑,M5砂浆砌筑。

3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (四)0m 层双排脚手架搭设

1、根据平面图位置,将脚手架位置在楼板及墙体上测放,靠近控制室处可距控制室200mm 进行搭设。

2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架与钢柱相连,采用焊接连接,中间设置立杆。见附图三。 (五)0m 层防护彩板封闭

1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。

2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。

3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。

4、单层板封闭完成后进行内板及保温封闭,保温材料必须采用防火玻璃棉进行封闭。 (六)、8.6m 层施工通道围挡及防护

1、将施工所用的通道由0m 层至8.6m 层满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。

2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。

3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离配电间墙体距离200mm ,防止破坏墙体。 (七)8.6m 层挡水沿砌筑

1、沿22轴联络平台钢柱内侧放线,砌体抹灰后与钢柱平齐,墙厚240mm 。 2、将砌体下部楼地面凿毛,形成粗凿面,采用蒸压灰砂砖砌筑,M5砂浆砌筑。 3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (八)8.6m 层双排脚手架搭设

1、根据平面图位置,将脚手架位置在楼板及墙体上测放,靠近配电室处距配电室200mm 进行搭设。

2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架与钢柱相连,采用焊接连接,中间设置立杆。见附图三。 (九)8.6m 层防护彩板封闭

1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。

2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。

3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。

4、12m 层配电间待设计院出图后施工。 (十)、17m 层施工通道围挡及防护

1、将施工所用的通道由8.6m 层至17m 层满铺模板,模板底部不得粘有砂石等硬质物体,以免损坏#2主厂房内已施工好的楼地面。

2、在距防护脚手架2m 处,搭设2.5m 高脚手架,脚手架底部铺设脚手架板,脚手架设置斜撑及底部找平杆,设置两道水平杆,间距1m 。

3、采用拆除后的外彩板绑扎固定于围挡脚手架上,并按照附图一所示,设置隔离门。 4、围挡脚手架距离配电间墙体距离200mm ,防止破坏墙体。 (十一)17m 层挡水沿砌筑

1、沿22轴联络平台钢柱内侧放线,砌体抹灰后与钢柱平齐,墙厚240mm 。 2、采用蒸压灰砂砖砌筑,M5砂浆砌筑。

3、砌体施工完毕后,内外侧均进行抹灰,抹灰厚度18mm ,底部200mm 采用防水砂浆抹面,外侧做成圆弧角,圆弧角半径80mm ,详见挡水沿剖面图。见附图二。 (十二)17m 层双排脚手架搭设

1、根据平面图位置,将脚手架位置在楼板及墙体上测放,进行搭设。

2、搭设脚手架,立杆纵横向间距1.5m ,步距1.5m ,脚手架与钢柱连接,连墙件间距2.5m 。脚手架外侧脚手架横杆与钢柱相连,采用焊接连接,中间设置立杆。第一道抗风柱以上不设置连墙件,由低至顶设置剪刀撑,见附图三。 (十三)17m 层防护彩板封闭

1、在已搭设完的双排脚手架外侧,将彩板固定至外横杆处,采用#8铁丝与横杆及内立杆相连,连接间距750mm 。

2、彩板之间相互搭接,搭接长度不小于80mm ,并采用拉铆钉进行锚固。

3、彩板位于挡水沿外侧,彩板底部低于挡水沿顶150mm ,并用射钉枪与墙体相连。见附图三。

(十四)内彩板拆除

1、采用吊篮由女儿墙向下设置,对内彩板进行拆除。

2、采用手持式电钻,将内板及保温固定螺栓拧下,单张板上部螺栓拧下后,采用麻绳或钢丝绳将上端拴牢,之后卸下单张板中部及底部螺栓,待全部螺栓拧下后,单张彩板运至地面。

2、拆除的内板要及时运至地面,并妥善保管,不得损毁内板。见附图四。 (十五)抗风柱拆除

1、内彩板拆除至第一道横梁以下时,采用LR1400将横梁以上抗风柱拆除。

2、抗风柱第一道横梁上部柱段割除,也可将柱节点螺栓拧下,割除时,先用钢丝绳将钢柱顶部拴牢,用气割将17m 以上第一道横梁出及顶部与屋架相连处割除,之后用LR1400将钢柱吊下,之后继续拆除内彩板。见附图四。 (十六)墙体暖气等拆除施工

1、拆除时,要严格保护拆除物品的完整性,如暖气、门窗等。 2、暖气拆除时,首先关闭阀门,之后进行拆除施工。 3、8.6m 层除配电间北墙不拆除,其他墙体、彩板均需拆除, (十七)过行车

1、达到行车通过条件后,将抗风柱第一道横梁以上的脚手架拆除,保证行车可顺利通过。 2、拆除时由上向下进行拆除,底部连墙件禁止拆除,拆除时设专人进行监护,严禁随意抛掷构件。

(十八)脚手架恢复及防护拆除

行车通过后,将拆除脚手架恢复,直至#3主厂房封闭完,将整体脚手架进行拆除,并将围挡、铺设垫板等运出#2主厂房,并将通道清理干净,挡水沿等均需拆除。见附图五。 七、施工注意事项

1、配电间内施工时,所有施工人员需穿绝缘鞋,不得随意碰触盘柜,施工前办理作业票。 2、所有拆除后构件不得随意抛掷,必须采用溜绳运送至地面,墙体拆除宜使构件向北侧破坏,防止拆除后构件掉落#2主厂房内部。

3、吊笼使用前必须将相关资料上报,并经现场检查后方可进行施工。 4、施工中严禁在#2厂房内胡乱走动,必须在围挡范围内,不得越界。

5、防护施工的通道必须全程铺设模板或橡胶板,保证#2厂房内楼地面不受损坏。 6、所有施工开工前,必须办理相应作业票,无票禁止作业。 八、安全施工注意事项

1、所有施工人员作业前须经安全培训,并经考核合格后持证上岗。作业人员无高血压、心脏病、精神病、癫痫病等危害施工安全的疾病。特殊工种人员应持相应资格证书上岗。

2、每天上班前,班长应根据当天的工作安排对作业人员进行技术、安全交底,并应办理交底签字。

3、作业人员进入施工现场必须正确佩带安全帽,系好下颌带。不准穿着拖鞋、高跟鞋及短裤进入施工现场。不准酒后上班。

4、电气作业必须由持证的专业电工进行,非电工严禁装、拆电气设备与设施。不得单人进行电气作业,在已送电的线路或用电设备上需停电进行作业时,断开电源的开关必须挂牌,并有专人监护。

5、各种起吊设施应完好无缺陷,不准带病运行,不准超限使用。

6、在进行起吊作业时,应设专职指挥人员,指挥人员应持证上岗,指挥信号应清晰明了。 7、高处作业作业人员必须扎安全带,安全带挂在水平安全绳上或稳固构件上,并做到高挂低用。起重工拴、摘钢丝绳时正确使用自锁器。

8、脚手架须由有证架工按规范要求搭设,搭设完的脚手架须经技术负责人验收合格后,方可投入使用。

9、高处操作人员使用的工具、零配件等,应放在随身佩带的工具袋内,或拴上安全绳系

在身上,不可随意上下抛掷。

10、在高处用气割切割时,应采取措施,或在地面设置安全监护人,防止火花落下伤人。 11、禁止在六级或六级以上大风、大雾、大雨天气、夜间等恶劣气侯下进行吊装作业。 12、夜间施工应有足够的照明,照度应符合施工作业的要求。

13、施工现场危险区域禁止使用、拨打、玩手机,执行公司六大禁令。

14、10t 、20t 及15t 卡环、钢丝绳等应经常进行维修保养,并做好拉力试验合格后方可进行使用,使用前认真检查是否损坏,确保无误方可进行吊装作业。

15、气割过程中做好防火措施,施焊前仔细检查周围环境,是否有可燃、易燃物品,及时进行清理,同时做好接火盆,防止火花四溅引发火灾,底部设监护人,发现险情及时采用就近灭火器材灭火,防止火势蔓延。

16、现场发现情况应及时进行汇报,并根据事件大小按照项目部应急预案要求启动相应应急预案,并及时进行汇报。

17、全过程施工设置专职人员进行全程监护,无关人员禁入施工区域,施工人员禁入#2主厂房。

18、施工过程中所需材料在#2主厂房外下料完毕,减少#2主厂房内部扬尘,减少污染,及时清理产生的生产垃圾。

19、吊笼结构应焊接牢固,禁止使用变形、锈蚀、损坏的吊笼,吊笼使用前几使用期间应定期进行检查,合格后方可进行施工。

20、拆除作业现场设置足够的消防器材,与一期生产区域设置可靠的隔离区域,保障生产区域的正常运行。

21、施工用电严格按照五项三线制执行,电动工具必须安装漏电保护器,防止触电事故的发生。

22、夏季施工时,做好防暑降温工作,设置饮水点并配置藿香正气水,防止人员中暑。 23、如遇突发事件及紧急情况,应立即进行应急处理,防止事态发展,并立即向上级进行汇报,及时启动项目部相应应急预案。 九、环境及文明施工注意事项

1、现场所有安全设施,如安全防护栏杆、安全警戒绳等均使用标准的安全防护栏杆、安全警戒绳等。

2、构件吊装时,应拴以溜绳,以控制构件空中方向。 3、施工中产生的边角料、施工垃圾应随时清除。 4、要注意施工机械的日常保养,避免过大的燥音。

5、在施工完的框架附近进行可能污染作业时,应进行防护。 6、要加强和提高全体施工人员的环保意识,认清环保的重要性。

7、运输时要减速慢行,防止扬尘,防止漏油,以免造成道路和场地污染。

十.危险因素辩识与控制


相关文章

  • 柴油发电机组安装工艺标准
  • 柴油发电机组安装工艺标准 1 总则 1.1 适用范围 (1)本工艺标准适用于一般工业与民用建筑电气安装工程的单台.联机固定式柴油发电 机组及其附属设备的安装与调试工作,柴油发电机组的连续功率为100-1500kVA. (2)设置在建筑物的首 ...查看


  • 装饰安全监理细则
  • 滨海新都市北塘总部基地东区 1#楼首层北塘泰达御海售楼中心 装 饰 工 程 安 全 监 理 实 施 细 则 编制人: 审批人: 天津港保税区中天建设咨询管理有限公司 项目管理三十部 年 月 日 目 录 一.工程概况 二.编制依据 三.安全监 ...查看


  • 屋面漏水大修工程施工方案
  • 135KW 机组厂房建筑屋顶漏水治理工程 施 工 组 织 设 计 方 案 北京森桦建业防水工程有限公司 年 月 日 第一章 编制说明 第一节 综合说明 135KW 机组厂房建筑屋顶漏水治理工程(包括原防水层铲除,新做防水,彩钢结合缝施工). ...查看


  • 关于工地用配电箱的一些知识
  • 一.建筑工程中,一级电箱,二级电箱,三级电箱有什么区别,怎么去区分 标签: 建筑 工程, 建筑, 区分 一级电箱,二级电箱,三级电箱有什么区别 火柴棍 回答:1 人气:6 解决时间:2008-10-04 14:58 检举 根据跳闸事故的级别 ...查看


  • 空冷岛安装作业指导书
  • 目 录 1工程概况 ..................................................... 1 2编制依据 ................................................ ...查看


  • 水冷式机组利用自然冷源
  • 深圳雷诺威精密空调设备有限公司所生产的机房空调主要配件全部采用进口高端产品,智能模块化设计,主要用于计算机机房.洁净室.实验室.电力通信.配电室.通讯基站.静电实验室.档案馆.博物馆.储藏室等场所,(温湿度范围18~28℃精度±0.5℃DB ...查看


  • 安全及三项业务管理策划(大纲)
  • 环境保护节能减排职业健康 安全管理策划书 目录 第一章 编制说明 ....................................................................................... ...查看


  • 全厂热力设备与管道保温作业指导书
  • 一.施工范围 本作业指导书适用于山东元鸣生物科技有限公司热源厂2#锅炉剩余工程量安装工程中一台泰山集团股份有限公司生产的循环流化床锅炉本体TG-75/5.29-M5+1×12MW汽轮发电机组: 锅炉房辅助设备:疏水扩容器.定期排污扩容器.疏 ...查看


  • 安全施工考核标准20160806
  • 安 全 施 工 考 核 标 准 安全施工考核标准 1总则 1.1 为了加强基建工程的安全管理,贯彻"安全第一.预防为主.综合治理"的安全生产方针,执行国家安全的有关制度.规程.标准,规范建设工程中各类工作人员的行为,结合 ...查看


热门内容