武汉通风作业指导书

武汉市轨道交通2号线南延线

风水电装修第三标段

通风与空调作业指导书

中铁二局集团电务工程有限公司

中铁二局集团电务工程有限公司武汉市轨道交通2号线

南延线风水电装修第三标段项目经理部

二〇一七年八月

目录

一 风管安装 ········································································································· 3

1.1工艺流程 ··································································································· 3 1.2操作要点 ··································································································· 3 1.3注意事项 ··································································································· 4 二 风阀安装 ········································································································· 5

2.1工艺流程 ··································································································· 5 2.2操作要点 ··································································································· 5 2.3注意事项 ··································································································· 8 三 风机安装 ········································································································· 9

3.1工艺流程 ··································································································· 9 3.2操作要点 ································································································· 10 3.3注意事项 ·································································································· 11 四 片式消声器安装 ······························································································· 12

4.1工艺流程 ·································································································· 12 4.2操作要点 ·································································································· 12 4.3注意事项 ·································································································· 13

一 风管安装

1.1工艺流程

1.2操作要点

1.2.1风管的支、吊架应采用热镀锌件,下料、开孔应采用机械加

工,严禁采用电气焊开孔或扩孔,支架焊接完后应做防腐处理;紧固螺栓应采取防松动措施(即双螺母固定),吊杆应平直,无明显变形。

1.2.2风管安装,管道与支吊架的接触面要贴紧,并须在支架上

加设3-5㎜减震、耐磨橡胶垫,防止晃动。

加设3-5㎜减震、耐磨橡胶垫,防止晃动

1.2.3风管安装应在风管的弯头、三通、四通等管件上增加吊架,

落地、下排风管应增加支托架。

风管管件及下排风管加设支吊架

1.3注意事项

1.3.1所用风箱均采用2.0mm 镀锌钢板制作,并应按照中压风管要

求采取相应的加固措施,加固措施详见国标图集07K133;风箱应使用

憎水性玻璃棉管壳外裹双层高强度带筋铝箔保冷,保冷材料密度

80kg/m3/,导热系数≤0.033W/m.K,厚度40mm 。

1.3.2通风空调大系统、小系统风机天圆地方规格尺寸根据设备接

口及相应风管尺寸确定,采用厚度为1.2mm 的镀锌钢板制作;空调系统回排风机的天圆地方应采用憎水性玻璃棉管壳外裹双层高强度带筋铝箔进行保温,保温厚度40mm ,密度80kg/m3/,导热系数≤0.033W/m.K。

1.3.3风管连接时密封条应安装到位,两根风管连接时密封条的保

护纸应撕掉,外卡槽式连接时卡条应连接牢固,不得松动。

1.3.4进入混风室、新风室、排风室的敞开式风管应加装防鼠网,

以保证运行安全。

1.3.5风管端部支架距端部距离不大于400㎜。

二 风阀安装

2.1工艺流程

2.2操作要点

2.2.1防火阀的安装方向、位置应正确,距墙表面不应大于

200mm ,以150mm 到200mm 为宜。

防火阀安装离距离设置规范

2.2.2防火阀设独立支、 吊架。

防火阀安装设置独立支吊架

2.2.3风阀安装后现场应有明确的标识,风管外表也应有风向指示

标识。

(1)风阀标识牌模板(A4纸张大小,过塑):

环控系统设备标识牌

(2)风管系统标识牌模板(A4纸张大小) :

小 系 统2

风管系统标识牌模板

(注:箭头须填色,送/新风管、送水管上为艳绿色(G03),回排风管、回 水管上为红色(R03);箭头下方标明系统编号,字体为黑体初号,均与居中)

风阀、风管标识清楚

2.3注意事项

2.3.1防火阀安装未设置独立支吊架或设置不规范,影响管道

强度,存在安全隐患。

防火阀安装未设置独立支吊架

2.3.2相邻风管风阀的安装间距不符合要求(30cm 以上),影响执行器动作和检修。

风管风阀安装无检修空间

2.3.3组合风阀用规格为L100*100*8长度为200mm 的角钢为角码,间隔1000mm 固定。

组合风阀固定

2.3.4风阀安装前提前检测执行器动作情况,对有问题的部件提前在安装前处理,提高一次安装成功率。

三 风机安装

3.1工艺流程

3.2操作要点

3.2.1风机就位未配风管前,应将风机接口做临时封闭(防火布或彩条布封堵),防止杂 物落入设备内。

风机安装接管前成品保护

3.2.2 风管与风机的连接采用柔性短管,入口的柔性短管可适当 紧张安装以防止风机启动被吸入,并应就近采用固定支吊托架紧固,防止移位。

风机接风管采用柔性软接并吊托架固定

3.2.3 风机传动装置的外露部位以及直通大气的进、出口,

须装设防护罩(网) 或采取其他安全设施。

风机防护罩(网) 安装

3.3注意事项

3.3.1 风机存放未按要求进行下垫上盖、分类存放在干燥处,导致设备损坏、污染,无法安装、使用。

风机成品保护不到位

3.3.2 风机安装定位不合理,导致风机无操作、检修空间。

风机安装无检修空间

四 片式消声器安装

4.1工艺流程

4.2操作要点 4.2.1片式消声器安装每个纵向段的消声片应相互平行,其组件 竖直方向接口必须对齐,垂直度允许偏差为1/1000;消声器前端外缘 应处于与气流方向垂直的同一平面内且与中间连接牢固。

片式消声器安装

4.2.2片式消声器的消声片的顶部、底部及消声片临近侧壁方向 应与结构壁面结合牢固,在额定风量下不得出现松动或振颤现象,如与结构墙面的缝隙大于30㎝以上时必须采取封堵措施。

片式消声器安装

4.3注意事项

4.3.1片式消声器进场未进行覆盖保护,导致消声片污染、受潮、 锈蚀、变形,影响消声器消声效果,无法安装,存在安全隐患。

消声器成品保护不到位

4.3.2消声器存放现场应做好成品保护,严谨消声棉进水,及时封堵,以免灰尘进入,影响消声效果。

武汉市轨道交通2号线南延线

风水电装修第三标段

通风与空调作业指导书

中铁二局集团电务工程有限公司

中铁二局集团电务工程有限公司武汉市轨道交通2号线

南延线风水电装修第三标段项目经理部

二〇一七年八月

目录

一 风管安装 ········································································································· 3

1.1工艺流程 ··································································································· 3 1.2操作要点 ··································································································· 3 1.3注意事项 ··································································································· 4 二 风阀安装 ········································································································· 5

2.1工艺流程 ··································································································· 5 2.2操作要点 ··································································································· 5 2.3注意事项 ··································································································· 8 三 风机安装 ········································································································· 9

3.1工艺流程 ··································································································· 9 3.2操作要点 ································································································· 10 3.3注意事项 ·································································································· 11 四 片式消声器安装 ······························································································· 12

4.1工艺流程 ·································································································· 12 4.2操作要点 ·································································································· 12 4.3注意事项 ·································································································· 13

一 风管安装

1.1工艺流程

1.2操作要点

1.2.1风管的支、吊架应采用热镀锌件,下料、开孔应采用机械加

工,严禁采用电气焊开孔或扩孔,支架焊接完后应做防腐处理;紧固螺栓应采取防松动措施(即双螺母固定),吊杆应平直,无明显变形。

1.2.2风管安装,管道与支吊架的接触面要贴紧,并须在支架上

加设3-5㎜减震、耐磨橡胶垫,防止晃动。

加设3-5㎜减震、耐磨橡胶垫,防止晃动

1.2.3风管安装应在风管的弯头、三通、四通等管件上增加吊架,

落地、下排风管应增加支托架。

风管管件及下排风管加设支吊架

1.3注意事项

1.3.1所用风箱均采用2.0mm 镀锌钢板制作,并应按照中压风管要

求采取相应的加固措施,加固措施详见国标图集07K133;风箱应使用

憎水性玻璃棉管壳外裹双层高强度带筋铝箔保冷,保冷材料密度

80kg/m3/,导热系数≤0.033W/m.K,厚度40mm 。

1.3.2通风空调大系统、小系统风机天圆地方规格尺寸根据设备接

口及相应风管尺寸确定,采用厚度为1.2mm 的镀锌钢板制作;空调系统回排风机的天圆地方应采用憎水性玻璃棉管壳外裹双层高强度带筋铝箔进行保温,保温厚度40mm ,密度80kg/m3/,导热系数≤0.033W/m.K。

1.3.3风管连接时密封条应安装到位,两根风管连接时密封条的保

护纸应撕掉,外卡槽式连接时卡条应连接牢固,不得松动。

1.3.4进入混风室、新风室、排风室的敞开式风管应加装防鼠网,

以保证运行安全。

1.3.5风管端部支架距端部距离不大于400㎜。

二 风阀安装

2.1工艺流程

2.2操作要点

2.2.1防火阀的安装方向、位置应正确,距墙表面不应大于

200mm ,以150mm 到200mm 为宜。

防火阀安装离距离设置规范

2.2.2防火阀设独立支、 吊架。

防火阀安装设置独立支吊架

2.2.3风阀安装后现场应有明确的标识,风管外表也应有风向指示

标识。

(1)风阀标识牌模板(A4纸张大小,过塑):

环控系统设备标识牌

(2)风管系统标识牌模板(A4纸张大小) :

小 系 统2

风管系统标识牌模板

(注:箭头须填色,送/新风管、送水管上为艳绿色(G03),回排风管、回 水管上为红色(R03);箭头下方标明系统编号,字体为黑体初号,均与居中)

风阀、风管标识清楚

2.3注意事项

2.3.1防火阀安装未设置独立支吊架或设置不规范,影响管道

强度,存在安全隐患。

防火阀安装未设置独立支吊架

2.3.2相邻风管风阀的安装间距不符合要求(30cm 以上),影响执行器动作和检修。

风管风阀安装无检修空间

2.3.3组合风阀用规格为L100*100*8长度为200mm 的角钢为角码,间隔1000mm 固定。

组合风阀固定

2.3.4风阀安装前提前检测执行器动作情况,对有问题的部件提前在安装前处理,提高一次安装成功率。

三 风机安装

3.1工艺流程

3.2操作要点

3.2.1风机就位未配风管前,应将风机接口做临时封闭(防火布或彩条布封堵),防止杂 物落入设备内。

风机安装接管前成品保护

3.2.2 风管与风机的连接采用柔性短管,入口的柔性短管可适当 紧张安装以防止风机启动被吸入,并应就近采用固定支吊托架紧固,防止移位。

风机接风管采用柔性软接并吊托架固定

3.2.3 风机传动装置的外露部位以及直通大气的进、出口,

须装设防护罩(网) 或采取其他安全设施。

风机防护罩(网) 安装

3.3注意事项

3.3.1 风机存放未按要求进行下垫上盖、分类存放在干燥处,导致设备损坏、污染,无法安装、使用。

风机成品保护不到位

3.3.2 风机安装定位不合理,导致风机无操作、检修空间。

风机安装无检修空间

四 片式消声器安装

4.1工艺流程

4.2操作要点 4.2.1片式消声器安装每个纵向段的消声片应相互平行,其组件 竖直方向接口必须对齐,垂直度允许偏差为1/1000;消声器前端外缘 应处于与气流方向垂直的同一平面内且与中间连接牢固。

片式消声器安装

4.2.2片式消声器的消声片的顶部、底部及消声片临近侧壁方向 应与结构壁面结合牢固,在额定风量下不得出现松动或振颤现象,如与结构墙面的缝隙大于30㎝以上时必须采取封堵措施。

片式消声器安装

4.3注意事项

4.3.1片式消声器进场未进行覆盖保护,导致消声片污染、受潮、 锈蚀、变形,影响消声器消声效果,无法安装,存在安全隐患。

消声器成品保护不到位

4.3.2消声器存放现场应做好成品保护,严谨消声棉进水,及时封堵,以免灰尘进入,影响消声效果。


相关文章

  • 施工生产实习报告范文
  • 本文导航 1.首页2.施工方法 [摘要]很多人初涉职场的时候都会有一个实习的经过,在实习完成时,大家都用一份报告来作一个实习工作总结.那么,个人实习报告怎么写呢?书村网特意为大家整理了施工生产实习报告范文,欢迎阅读. 2005年,在这个不平 ...查看


  • 隧道工程施工的事故分析与安全措施
  • 2008年第34卷第9期 工业安全与环保 Septe mber 2008Industrial Safety and Environmental Protec tion ∀61∀ 安全管理 隧道工程施工的事故分析与安全措施 赵瑞先 伍颖 谢欣 ...查看


  • _石武客运专线郑武段运行试验
  • 石武客运专线郑武段 运行试验大纲 (V3.2) 中国铁道科学研究院 (高速铁路系统试验国家工程实验室) 郑州铁路局 武汉铁路局 京广铁路客运专线河南有限责任公司 武广铁路客运专线有限责任公司 2012年4月 目 录 目 录 一.工程特点.. ...查看


  • 地铁盾构瓦斯隧道通风技术研究
  • 市政·交通·水利工程设计 Municipal ·Traffic ·Water Resources ·Engineering Design [文章编号]1007-9467(2010)07-0111-03 地铁盾构瓦斯隧道通风技术研究 (中铁一 ...查看


  • 武汉市轨道交通规划管理办法
  • 武汉市轨道交通规划管理办法 (送审稿) 第一章 总则 第一条 为加强我市轨道交通规划管理,使轨道交通与周边地区建设相协调,根据有关法律.法规和规章,结合本市实际,制定本办法. 第二条 本办法所称轨道交通,是指城市公共交通系统中大运量的城市地 ...查看


  • 文明施工措施方案
  • 武汉.中国健康谷养生社 区19~22#楼工程 文 明 施 工 措 施 方 案 编制人: 审核人: 审批人: 山河建设集团有限公司 2013年4月1日 文明施工措施方案 前言:文明施工是促进安全生产.保障工程质量.加快施工进度.降低工程成本. ...查看


  • 市政工程施工安全文明标准
  • 一冶二环线市政工程安全文明施工标准 一.严格执行现场临时施工用电安全技术规范. 现场施工用电设备在5台以上或总容量50KW及以上应编制临时施工用电组织设计,施工电缆要按照TN-S系统要求执行"三项五线制"配置五芯电缆,电 ...查看


  • 官店铁矿地下采矿方法设计
  • 武汉工程大学 课 程 设 计 说 明 书 题 目 官店铁矿地下采矿方法设计 专业班级 09级采矿工程01班 学 生 汪长志 指导教师 成 绩 说明书 页 插 图 幅 表 格 个 程 序 个 二O 一一 十二 十七 第一章 矿区地形地貌.地理 ...查看


  • 夏热冬冷地区城市设计生态策略研究
  • 摘要:本文从生态角度对城市设计的方法进行研究.通过对生物气候要素.自然要素和人工要素的整合与应用,初步形成一套适应夏热冬冷地区气候条件的城市设计生态策略和方法.并用此方法分析武汉市一些已落成的节能示范小区. 关键词:城市设计;生态策略;夏热 ...查看


热门内容