锚固桩专项施工方案 1

目 录

1.工程概况.......................................................................................................................................................................................2 2.施工准备.......................................................................................................................................................................................2 3.施工工艺.......................................................................................................................................................................................3 4.施工注意事项 ............................................................................................................................................................................12 5.安全措施.....................................................................................................................................................................................12 6.环保措施.....................................................................................................................................................................................13 7.成品保护.....................................................................................................................................................................................13

- 1 -

1.工程概况

龙华山隧道进口左侧仰坡设置2根Ⅰ型锚固桩和1根Ⅱ型锚固桩防护。隧道洞口右侧仰坡设置1根Ⅰ型锚固装和1根Ⅱ型锚固桩防护。Ⅰ型桩截面为2.25m×2.5m, Ⅱ型桩截面为2.5m×2.5m。 洞口左侧Ⅰ型桩长自洞口分别为20m,21m,Ⅱ型桩长21m,洞口右侧Ⅰ型桩长23m,Ⅱ型桩长22m,锚固桩布置见附图;

地洞口左侧边坡防护正面图洞口右侧边坡防护正面图

2.施工准备

- 2 -

1)现场核对设计,按设计测定桩位,进行施工放样。放样时,要根据工地具体情况和施工可能发生的误差,每边较设计尺寸略大一些(一般为5cm)。然后整平孔口场地。锚固桩施工一般先开挖桩顶以上土石方,形成工作面,然后开挖基坑,灌注桩身。

2)在井口上竖立井架式三角架或摇头扒杆出碴、进料,起吊高度应高出井口3m以上,搭设临时风雨棚,做好井口排水沟。为了施工人身安全,井口设栏杆(薄壳支护高出地面者可不设)及供起吊人员装卸料用的脚踏板和井口开关门。

3)备置起吊用箩筐或特制的活底箱、桶及0.5t的卷扬机。当桩间距离较短(5~7m)要考虑开挖与护壁混凝土灌注有工序间隔时间。

4)配置井内开挖用的短镐、铲、锹和钻岩机、风镐与空压机及管道,供人员上下用的梯子。

5)配备井内用的高压送电线路及低压照明、发电机和变配电设备、爆破器材、通风设备及管路和安装材料。

6)当井内有地下水时,还应配备、潜水泵或其他类型的高扬程抽水机。

3.施工工艺

见施工工艺框图3.1。 1)施工放样

用全站仪放出桩排位置。 2)第一节桩身开挖及锁口

第一节开挖长度为1m,按设计的桩身形状(含护壁)开挖,用镐、锹进行,遇坚硬土层用锤、钎破碎,允许尺寸误差为3cm。锁口用C15钢筋混凝土,长度不小于1m,高出地面20cm,厚30 cm。模板采用组合钢模板,特殊部位配自制钢模板,混凝土在拌合站统一搅拌,混凝土运输车运输,人工浇筑,振捣棒振捣。混凝土强度达到1MPa即可拆模。

3)桩身开挖及护壁

桩身开挖采取分段挖土、分段护壁的方法施工。从上而下逐层用镐、锹进行,遇坚硬土层用锤、钎破碎。孔内如遇岩石,采用浅眼弱爆破,爆破前

- 3 -

对炮眼附近的支撑予以防护。挖孔过程中经常检查桩身尺寸和平面位置,在锁口上设十字控制点,每一节设横杆吊大线坠作中心线,

锚固桩施工工艺框图3.1

用水平尺杆找桩身尺寸。弃土装入吊桶,采用洞口安支架、卷扬机提升的垂直运输,吊至地面上后,用机动翻斗车或手推车运出。

- 4 -

根据土质情况,A型桩护壁采用C15钢筋混凝土现浇,厚0.3m,适用于全风化和强风化地层;B型桩护壁采用C15素混凝土现浇,厚0.2m,使用于弱风化岩层段。护壁每节长1m,土石分界和滑动面处不能分节。开挖每1~2m

0.5m即进行护壁。

2.25m×2.5m型桩A型护壁平剖面图

D

12,525×3=75

12,5

D-D 剖面图

- 5 -

100

94

E

D

E-E 剖面图

E

2.25m×2.5m型桩B型护壁平剖面图

310

282.5

282

桩A型护壁剖面图

- 6 -

12,525×3=7512,5

94

4NF1φ10

L=94.0

D-D 剖面图

挖孔至设计高程时,核对断面尺寸及土质情况进行清底,做到平整、无松碴和污泥。经检查合格签证后,进行下一步施工。

4)通风、出渣

孔内要经常检查有害气体浓度,当二氧化碳浓度超过0.3%,其他有害气体超过允许浓度或孔深超过10m时,均需采取通风措施。孔内空气质量达标后方可入孔开挖及清渣。

出渣采用在桩孔上口架设垂直运输支架。支架有:木搭、钢管吊架、木吊架或工字钢导轨支架几种形式;要求搭设稳定、牢固。

在垂直运输支架上安装滑轮组和电动葫芦或穿卷扬机的钢丝绳,选择适当位置安装卷扬机。浅的桩孔,也可以用木吊架、辘轳或人工直接借助粗麻绳作提升工具。

将桩渣垂直吊至孔外,地面运土用手推车或翻斗车,所开挖出来的土方要弃至指定位置平整整齐,且在桩基周边2m范围内不得随意弃土,以减少孔周边对孔的侧压力。

5)钢筋笼制作

钢筋笼采用现场分节加工,用汽车起重机吊放钢筋笼就位,上下节之间采用焊接方式搭接,搭接接头不得设在土石分界和滑动面处。钢筋笼与护壁采用钢筋耳环支撑牢固。个别困难地段,也可以采用孔内绑扎钢筋的方式。

钢筋布设及锚固桩剖面附图:

I型桩以①号桩剖面图为例,Ⅱ型桩以③号桩剖面图为例,②④⑤号桩剖

- 7 -

面图与①③号桩剖面图相同,长度不同。

①号2.25m×2.5m型锚固桩桩剖面及钢筋布置图

`

B

C

- 8 -

234,4

70N3φ16L=909.2

210,2

235,2

70N4φ16L=224.5

209,4

钢筋大样图

L=1980

61N5φ28

- 9 -

1

23.6×8=188.8

2

1③号2.5m×2.5m型锚固桩钢筋及剖面布置图

11

1523,2

250

2.5m-2.5m型桩A-A剖面图

70N4φ16L=240

235.6

钢筋大样

- 10 -

235.8

L=2080

93N4φ28

10

250

Ⅱ型桩

1-1侧面

- 11 -

120

35×69=2070

20002080

6)混凝土灌注

锚固桩混凝土由砼拌合站供应,混凝土运输车运至施工现场,泵送串筒漏斗法(有水情况采用导管法)入孔。

浇砼前及时将砼护壁上的渗漏处堵塞,然后把井内积水抽干,以保证桩基混凝土质量,堵漏的方法,大面积堵成小面积的、小面积堵成点漏而最后堵塞之。

孔桩混凝土灌注方式视现场开挖情况而定,对于地下水较大,为了保证砼的浇注质量,采用导管法进行水下灌注;对于地下水较少,采用加串筒式的方式进行,但串筒底口砼直接倾落高度不超过2米。串筒方式灌注时控制孔底的水深不超过5cm,浇筑前要抽干孔内积水,抽水的潜水泵要装设逆流阀,保证提出水泵时,不致使抽水管中残留水又流入桩孔内,灌注速度尽可能快,使混凝土对孔壁的侧压力尽快大于渗水压力,以防水渗入孔内,每一孔内混凝土一次性连续灌注完毕不留施工缝,混凝土振捣由井下操作人员采用插入式振动棒进行振捣,前层厚度不超过50cm,插入形式为垂直式,插点间距约40-50cm,并且做到“快插慢拔”。

7)挡土板预制及安装

待桩身混凝土强度达到设计要求时,开挖桩前、桩间岩体。滑坡地段,桩间土体间隔从上至下逐层开挖,随挖随安装挡土板。挡土板采用预制场集中预制,汽车运到现场。

4.施工注意事项

1)在施工过程中,为确保施工人员的安全和建筑部位的准确性,应建立观测系统,布置对滑坡体、建筑物位置的准确观测,防止发生突然事故。

2)吊放钢筋入桩孔时,应绑紧系牢(下口宜用铁盘兜住),确保不溜脱坠落。应待钢筋吊入孔底后,才能下人进入桩孔解钩。

3)抗滑桩若有支挡建筑物、永久排水和防渗设施等,应使这些建筑设施与抗滑桩体正确连接,配套完成。

5.安全措施

- 12 -

抗滑桩开挖应符合下列规定:

1)桩口应设防止地表水流入的设施及防止坠物的护栏; 2)人员上下应有安全可靠的设施,不得携带任何工具、材料;

3)孔下必须设掩避所,工作人员不宜超过2人,起吊时应明确联系信号,统一指挥;

4)孔下有害气体含量应随时检测,超过规定标准时应进行通风,达到允许浓度标准后方可作业;

5)井下作业,不得攀扶箍筋上下;

6)灌注混凝土及挖桩时闲杂人员不得靠近,防止杂物下落伤人。

6.环保措施

1)弃土应按规定堆放,不得随意丢弃,应集中处理。 2)施工完毕后应清楚现场垃圾。

7.成品保护

1)混凝土浇灌完成后孔口应加盖保护,并及时养护。 2)隧道开挖设专人指挥,防止施工机械破坏桩体。

- 13 -

目 录

1.工程概况.......................................................................................................................................................................................2 2.施工准备.......................................................................................................................................................................................2 3.施工工艺.......................................................................................................................................................................................3 4.施工注意事项 ............................................................................................................................................................................12 5.安全措施.....................................................................................................................................................................................12 6.环保措施.....................................................................................................................................................................................13 7.成品保护.....................................................................................................................................................................................13

- 1 -

1.工程概况

龙华山隧道进口左侧仰坡设置2根Ⅰ型锚固桩和1根Ⅱ型锚固桩防护。隧道洞口右侧仰坡设置1根Ⅰ型锚固装和1根Ⅱ型锚固桩防护。Ⅰ型桩截面为2.25m×2.5m, Ⅱ型桩截面为2.5m×2.5m。 洞口左侧Ⅰ型桩长自洞口分别为20m,21m,Ⅱ型桩长21m,洞口右侧Ⅰ型桩长23m,Ⅱ型桩长22m,锚固桩布置见附图;

地洞口左侧边坡防护正面图洞口右侧边坡防护正面图

2.施工准备

- 2 -

1)现场核对设计,按设计测定桩位,进行施工放样。放样时,要根据工地具体情况和施工可能发生的误差,每边较设计尺寸略大一些(一般为5cm)。然后整平孔口场地。锚固桩施工一般先开挖桩顶以上土石方,形成工作面,然后开挖基坑,灌注桩身。

2)在井口上竖立井架式三角架或摇头扒杆出碴、进料,起吊高度应高出井口3m以上,搭设临时风雨棚,做好井口排水沟。为了施工人身安全,井口设栏杆(薄壳支护高出地面者可不设)及供起吊人员装卸料用的脚踏板和井口开关门。

3)备置起吊用箩筐或特制的活底箱、桶及0.5t的卷扬机。当桩间距离较短(5~7m)要考虑开挖与护壁混凝土灌注有工序间隔时间。

4)配置井内开挖用的短镐、铲、锹和钻岩机、风镐与空压机及管道,供人员上下用的梯子。

5)配备井内用的高压送电线路及低压照明、发电机和变配电设备、爆破器材、通风设备及管路和安装材料。

6)当井内有地下水时,还应配备、潜水泵或其他类型的高扬程抽水机。

3.施工工艺

见施工工艺框图3.1。 1)施工放样

用全站仪放出桩排位置。 2)第一节桩身开挖及锁口

第一节开挖长度为1m,按设计的桩身形状(含护壁)开挖,用镐、锹进行,遇坚硬土层用锤、钎破碎,允许尺寸误差为3cm。锁口用C15钢筋混凝土,长度不小于1m,高出地面20cm,厚30 cm。模板采用组合钢模板,特殊部位配自制钢模板,混凝土在拌合站统一搅拌,混凝土运输车运输,人工浇筑,振捣棒振捣。混凝土强度达到1MPa即可拆模。

3)桩身开挖及护壁

桩身开挖采取分段挖土、分段护壁的方法施工。从上而下逐层用镐、锹进行,遇坚硬土层用锤、钎破碎。孔内如遇岩石,采用浅眼弱爆破,爆破前

- 3 -

对炮眼附近的支撑予以防护。挖孔过程中经常检查桩身尺寸和平面位置,在锁口上设十字控制点,每一节设横杆吊大线坠作中心线,

锚固桩施工工艺框图3.1

用水平尺杆找桩身尺寸。弃土装入吊桶,采用洞口安支架、卷扬机提升的垂直运输,吊至地面上后,用机动翻斗车或手推车运出。

- 4 -

根据土质情况,A型桩护壁采用C15钢筋混凝土现浇,厚0.3m,适用于全风化和强风化地层;B型桩护壁采用C15素混凝土现浇,厚0.2m,使用于弱风化岩层段。护壁每节长1m,土石分界和滑动面处不能分节。开挖每1~2m

0.5m即进行护壁。

2.25m×2.5m型桩A型护壁平剖面图

D

12,525×3=75

12,5

D-D 剖面图

- 5 -

100

94

E

D

E-E 剖面图

E

2.25m×2.5m型桩B型护壁平剖面图

310

282.5

282

桩A型护壁剖面图

- 6 -

12,525×3=7512,5

94

4NF1φ10

L=94.0

D-D 剖面图

挖孔至设计高程时,核对断面尺寸及土质情况进行清底,做到平整、无松碴和污泥。经检查合格签证后,进行下一步施工。

4)通风、出渣

孔内要经常检查有害气体浓度,当二氧化碳浓度超过0.3%,其他有害气体超过允许浓度或孔深超过10m时,均需采取通风措施。孔内空气质量达标后方可入孔开挖及清渣。

出渣采用在桩孔上口架设垂直运输支架。支架有:木搭、钢管吊架、木吊架或工字钢导轨支架几种形式;要求搭设稳定、牢固。

在垂直运输支架上安装滑轮组和电动葫芦或穿卷扬机的钢丝绳,选择适当位置安装卷扬机。浅的桩孔,也可以用木吊架、辘轳或人工直接借助粗麻绳作提升工具。

将桩渣垂直吊至孔外,地面运土用手推车或翻斗车,所开挖出来的土方要弃至指定位置平整整齐,且在桩基周边2m范围内不得随意弃土,以减少孔周边对孔的侧压力。

5)钢筋笼制作

钢筋笼采用现场分节加工,用汽车起重机吊放钢筋笼就位,上下节之间采用焊接方式搭接,搭接接头不得设在土石分界和滑动面处。钢筋笼与护壁采用钢筋耳环支撑牢固。个别困难地段,也可以采用孔内绑扎钢筋的方式。

钢筋布设及锚固桩剖面附图:

I型桩以①号桩剖面图为例,Ⅱ型桩以③号桩剖面图为例,②④⑤号桩剖

- 7 -

面图与①③号桩剖面图相同,长度不同。

①号2.25m×2.5m型锚固桩桩剖面及钢筋布置图

`

B

C

- 8 -

234,4

70N3φ16L=909.2

210,2

235,2

70N4φ16L=224.5

209,4

钢筋大样图

L=1980

61N5φ28

- 9 -

1

23.6×8=188.8

2

1③号2.5m×2.5m型锚固桩钢筋及剖面布置图

11

1523,2

250

2.5m-2.5m型桩A-A剖面图

70N4φ16L=240

235.6

钢筋大样

- 10 -

235.8

L=2080

93N4φ28

10

250

Ⅱ型桩

1-1侧面

- 11 -

120

35×69=2070

20002080

6)混凝土灌注

锚固桩混凝土由砼拌合站供应,混凝土运输车运至施工现场,泵送串筒漏斗法(有水情况采用导管法)入孔。

浇砼前及时将砼护壁上的渗漏处堵塞,然后把井内积水抽干,以保证桩基混凝土质量,堵漏的方法,大面积堵成小面积的、小面积堵成点漏而最后堵塞之。

孔桩混凝土灌注方式视现场开挖情况而定,对于地下水较大,为了保证砼的浇注质量,采用导管法进行水下灌注;对于地下水较少,采用加串筒式的方式进行,但串筒底口砼直接倾落高度不超过2米。串筒方式灌注时控制孔底的水深不超过5cm,浇筑前要抽干孔内积水,抽水的潜水泵要装设逆流阀,保证提出水泵时,不致使抽水管中残留水又流入桩孔内,灌注速度尽可能快,使混凝土对孔壁的侧压力尽快大于渗水压力,以防水渗入孔内,每一孔内混凝土一次性连续灌注完毕不留施工缝,混凝土振捣由井下操作人员采用插入式振动棒进行振捣,前层厚度不超过50cm,插入形式为垂直式,插点间距约40-50cm,并且做到“快插慢拔”。

7)挡土板预制及安装

待桩身混凝土强度达到设计要求时,开挖桩前、桩间岩体。滑坡地段,桩间土体间隔从上至下逐层开挖,随挖随安装挡土板。挡土板采用预制场集中预制,汽车运到现场。

4.施工注意事项

1)在施工过程中,为确保施工人员的安全和建筑部位的准确性,应建立观测系统,布置对滑坡体、建筑物位置的准确观测,防止发生突然事故。

2)吊放钢筋入桩孔时,应绑紧系牢(下口宜用铁盘兜住),确保不溜脱坠落。应待钢筋吊入孔底后,才能下人进入桩孔解钩。

3)抗滑桩若有支挡建筑物、永久排水和防渗设施等,应使这些建筑设施与抗滑桩体正确连接,配套完成。

5.安全措施

- 12 -

抗滑桩开挖应符合下列规定:

1)桩口应设防止地表水流入的设施及防止坠物的护栏; 2)人员上下应有安全可靠的设施,不得携带任何工具、材料;

3)孔下必须设掩避所,工作人员不宜超过2人,起吊时应明确联系信号,统一指挥;

4)孔下有害气体含量应随时检测,超过规定标准时应进行通风,达到允许浓度标准后方可作业;

5)井下作业,不得攀扶箍筋上下;

6)灌注混凝土及挖桩时闲杂人员不得靠近,防止杂物下落伤人。

6.环保措施

1)弃土应按规定堆放,不得随意丢弃,应集中处理。 2)施工完毕后应清楚现场垃圾。

7.成品保护

1)混凝土浇灌完成后孔口应加盖保护,并及时养护。 2)隧道开挖设专人指挥,防止施工机械破坏桩体。

- 13 -


相关文章

  • 锚固桩专项施工方案
  • AAAAAAAAAAAAAA铁路专用线项目 锚固桩专项施工方案 编 制: 复 核: 审 核: AAAAAAAA有限公司AAAAAA AAAAAAAA铁路专用线工程二标项目经理部 二0一四年十一月 AAAAAAAAAAAAA 铁路专用线项目 ...查看


  • 人工铺轨专项施工方案
  • 人工铺轨专项施工方案 一.工程概况 兰新铁路红柳河至烟墩段电气化改造工程是兰新铁路红柳河至乌西段的组成部分.我单位负责兰新铁路从YDK1173+636.4-YDK1250+800段铺架工程,正线长度85.541km (双线),站线长度2.5 ...查看


  • 高层填充墙植筋工程专项施工方案
  • 宿迁市盛世家园二期四标建设工程 砌 体 植 筋 工 程 施 工 方 案 编 制: 审 核: 审 批: 日 期: 浙江新东阳建设集团有限公司 盛世家园二期四标项目部 2015年4月 目 录 一.工程概况 ------------------- ...查看


  • 主体钢筋工程施工方案
  • 瀚宇天悦湾5号院19号楼 主体钢筋工程施工方案 编制: 审核: 审批: 河南领域建设工程有限公司瀚宇天悦湾5号院第三项目部 2015年08月15日 19#楼主体钢筋工程专项施工方案 目 录 一. 工程概况 二. 编制依据 ......... ...查看


  • F11.钢筋工程专项施工方案
  • 施 工 方 案 [建设单位]: 常熟滨江热力有限公司 [工程名称]: 常熟市沿江片区集中供热管网工程 [方案名称]: 钢筋工程专项施工方案 [方案编号]: CS01-2015092501 中国化学工程第十四建设有限公司 常熟市沿江片区集中供 ...查看


  • 安全检查计划书
  • 建设工程安全监督工作计划书为了加强建设工程安全监督管理,认真贯彻"安全第一.预防为主.综合治理"的 方针, 保障施工现场人员的人身和财产安全, 根据 <建筑工程安全生产监督管理工作导则> . <湖北省房 ...查看


  • 保温节能专项施工方案
  • 目 录 一.编制依据 02 二.工程概况 02 三.技术要求 03 四.江苏省相关保温节能方面施工质量验收标准规程 03 五.工程实体质量监督的内容及重点 04 六.本工程节能保温原材料的检测 05 七.外墙面施工分层操作顺序 05 八.屋 ...查看


  • 挂篮安装及拆除专项施工方案
  • 目录 1.工程概况 .............................................................................................................. ...查看


  • 桩基础施工及土方开挖专项方案
  • 旭东嘉景杜村民安置边坡支护工程 桩基础施工及土方开挖专项方案 湖南益阳工程公司 二〇一〇年二月十日 桩基础施工及土方开挖专项方案报审表 桩基础施工 首先解决山坡及滑坡体的地表水的排水问题,在施工面靠坡体方向2M做截水明沟,明沟用MU10红砖 ...查看


热门内容